Decision The Local Development Committee RESOLVED to AGREE: 1. The reasons for refusal as set out in the Committee Report and associated updated report; and 2. Delegate authority to the Director of Planning and Development to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) based on the Heads of Terms identified on Appendix 10 of the Committee Report and conditions listed on Appendix 9 of the Committee report.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
21/05/2024 O you to respond to, or interact with, the organisation that provided you with the data. You are not permitted to copy, sub-licence, distribute or sell any of this data to third parties in any form. Produced by LBN Geospatial Team. E-mail [email protected] for further details Scale: 1:45,000 Land At 2 To 8, Water Lane, Stratford, London, E15 4NH 23/00972/FUL
Demolition of existing buildings and creation of a new six storey building Proposal: with upper 2 storeys set back, providing 20 residential units and Class E use at ground floor with associated landscaping, refuse & cycle storage.
The purpose of this report is to set out the Officer recommendations to the Local Development Committee regarding an application for planning permission relating to the proposal outlined above.
Officer Recommendations:
The Local Development Committee is asked to resolve to:
1. Agree the reasons for approval as set out in this report; and
2. Delegate authority to the Director of Planning and Development to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) based on the Heads of Terms identified at Appendix 10 of this report and the Conditions listed in Appendix 9 of this report.
Conditions Summary:
Mandatory conditions 1. Time 2. Approved Drawings and Documents
Prior to all works/commencement Conditions 3. Demolition and Construction Management Plan 4. Sustainable Urban Drainage (SuDs) 5. Written Scheme of Investigation (GLAAS) 6. Secured by Design 7. Bat Roosting
Prior to piling works Conditions 8. Piling Method Statement Prior to above ground works Conditions 9. External Materials 10. Mock-up Façade 11. Detailed Drawings 12. Hard and Soft Landscaping 13. Environmental Noise - Residential
Prior to first occupation and/or use Conditions 14. Cycle Parking 15. Delivery and Servicing Plan 16. Travel Plan 17. Waste Management 18. Groundbourne Noise
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.