What was decided
Cabinet awarded the Hamara Ghar refurbishment contract to Mulalley & Co Ltd by direct call-off under the LHC Refurbishment and Modernisation (RM3) Framework, valued at £8.1m.
Cabinet approved a total estimated project budget of £9m, covering the contract and additional costs, to be met from uncommitted capital allocations within the Retrofit Programme Budget.
Authority to agree variations within the £9m envelope was delegated to the Corporate Director of Inclusive Economy, in consultation with the Cabinet Member for Council Housing Improvements.
Why
The in-house repairs and maintenance team, RMS, does not have the capacity to carry out works of this nature, ruling out an in-house option.
Not awarding the contract would mean failing to meet the council's obligations as a landlord, which the Cabinet treated as a non-viable option.
What happens next
The Corporate Director of Inclusive Economy, with the Cabinet Member for Council Housing Improvements, will agree any variations within the £9m total budget.
The money
- £8.1m Contract sum for the Hamara Ghar refurbishment, modernisation and retrofit works
- £9m Total estimated project budget provision, including additional costs, from uncommitted capital allocations in the Retrofit Programme Budget
Options considered
- Chosen: Award the contract to Mulalley & Co Ltd under the LHC RM3 Framework. Provides the required specialist capacity to deliver the refurbishment and meet landlord obligations
- Rejected: Undertake the works in-house using RMS. RMS does not have the capacity to undertake works of this nature
- Rejected: Do not award the contract. Would result in the failure to meet the council's obligations as landlord
Implications
- Financial: Up to £9m of uncommitted capital within the Retrofit Programme Budget will be committed to this project.
- Legal: Awarding the contract is treated as necessary to discharge the council's obligations as a landlord.
- Other: Operational delivery will be by an external contractor rather than the in-house RMS team.
Who and where
- Residents of Hamara Ghar council housing, who will receive refurbishment, modernisation and retrofit works
- The council's in-house repairs and maintenance team (RMS), which is not delivering these works
Timeline
- 2025-12-16: Cabinet decision to award contract and approve budget
Plain English for the jargon
- LHC RM3 Framework: A procurement framework for refurbishment and modernisation works, used here for a direct call-off award.
- Retrofit Programme Budget: The council's capital budget covering energy efficiency and modernisation works to existing housing.
- Call-off: Awarding a contract to a supplier already appointed on a framework agreement, without a fresh competitive tender.