New risk management policy strategy and plan

Noted Finance 2 papers

AI summaryNewham's Audit and Governance Committee noted a new Risk Management Strategy and Policy for 2026/27, introducing a Bow Tie model aligned with ISO 31000 and HM Treasury's Orange Book.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the new strategy and policy
MoneyNo new spendingCosts managed within existing Service Directorate budgets
What happens nextStrategy applies in 2026/27Sets the framework for the year ahead
Who it affectsCouncil-wide risk oversightSupports the Building a Fairer Newham Corporate Plan

What was decided

The Committee noted the Risk Management Strategy and Policy 2026/27, which sets the framework for the Council's approach to risk during the year. Report 2.1, 3.1

The Committee endorsed a move from the current Corporate and Inherent risk register format to a Bow Tie analysis of principal strategic risks. Report P3, 1.2, 3.3

Why

The existing register did not consistently show risk drivers, inherent exposure, control effectiveness or mitigation tracking, limiting strategic oversight. Report 3.3

The refreshed framework aligns with recognised best practice, including ISO 31000 and HM Treasury's Orange Book, improving clarity and consistency. Report 1.2

A clearer approach supports resilient delivery of the Council's strategic priorities and statutory responsibilities. Report 3.2, 4.1

What happens next

The Strategy and Policy will operate as the framework for risk management throughout 2026/27, with the Bow Tie model used to present principal strategic risks. Report 3.1, P3

Any cost implications will be managed within existing agreed Service Directorate budgets. Report P18

Options considered

  • Chosen: Adopt the new Risk Management Strategy and Policy 2026/27, including the Bow Tie model. Aligns with ISO 31000 and Orange Book best practice and improves clarity of risk drivers, controls and mitigation. Report 1.2, P3, 3.4
  • Rejected: Retain the existing Corporate and Inherent risk register format. Current structure limits clarity of risk drivers, control effectiveness and mitigation tracking. Report 5.1, P13, 3.3

Implications

  • Financial: Any cost implications of the strategy will be managed within existing agreed Service Directorate budgets; the strategy may identify additional financial risk for the Council to manage. Report P18
  • Legal: The proposals concern internal risk management arrangements and do not give rise to direct legal implications. Report P19
  • Equalities: No Equalities Impact Assessment is required; the proposals relate to internal governance and do not change service delivery. Report P20
  • Other: No procurement activity is involved, so no Procurement Initiation Form reference is required. Report P22, 7.4
  • Other: No significant climate, HR, ICT or property implications arise from the proposals. Report P24, 7.5

Who and where

  • Senior leadership requiring strategic oversight of principal risks Report P26
  • Service Directorates holding the budgets that will absorb any cost implications Report P18
  • Delivery of the Building a Fairer Newham Corporate Plan priorities Report 4.1, 4.2

Timeline

  • 2026/27: Risk Management Strategy and Policy operates as the framework for the Council's approach to risk. Report 3.1, 1.1

Plain English for the jargon

  • Bow Tie model: A risk analysis method showing risk drivers, controls and consequences on either side of a central event, used here to improve visibility of risk drivers, control effectiveness and mitigation.
  • ISO 31000: International standard for risk management, used as a benchmark for the refreshed framework.
  • Orange Book: HM Treasury's framework on risk management, used as a benchmark for the refreshed framework.
  • PIF: Procurement Initiation Form; not required because no procurement activity is involved.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED that the report be noted.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Audit and Governance Committee

Executive summary

1.1This report presents an update to strengthen the Council’s strategic risk management framework through the Risk Management Strategy & Policy 2026/27.

1.2The refreshed Strategy and Policy aligns the Council’s risk management framework with recognised best practice, including ISO 31000 and HM Treasury’s Orange Book, improving clarity and consistency in how risk is assessed and governed.

1 1.3. The Bow Tie model strengthens the analysis and presentation of principal strategic risks, improving visibility of risk drivers, control effectiveness and mitigation delivery.

Recommendations

The Audit and Governance Committee is recommended to:

2.1Note and comment on the Risk Management Strategy and Policy 2026/27.

Background

3.1The Risk Management Strategy and Policy 2026/27 sets the framework for how the Council will approach Risk Management throughout the year.

3.2The Risk Management Strategy and Policy 2026/27 strengthens corporate accountability, consistency and transparency in risk management. This supports resilient and effective delivery of the Council’s strategic priorities and statutory responsibilities

3.3Council currently maintains Corporate and Inherent risk registers to provide oversight of risks managed at corporate level. The existing format does not consistently articulate risk drivers, inherent exposure, control effectiveness, or systematic tracking of mitigation delivery, which can limit clarity of strategic oversight.

3.4In line with recognised best practice, the framework has been reviewed to strengthen clarity and structure.

4. Delivering Council Policy and Corporate Priorities

4.1The strengthening of the Council’s strategic risk management framework supports delivery of the Building a Fairer Newham Corporate Plan by improving governance, oversight and assurance across all corporate priorities.

4.2A clearer and more structured approach to strategic risk analysis enhances the Council’s ability to identify, manage and mitigate risks that may affect delivery of its strategic objectives.

5. Alternatives Considered

5.1The alternative option was to retain the existing Corporate and Inherent risk register format. This was not recommended as the current structure limits clarity of risk drivers, control effectiveness and mitigation tracking.

2 6. Consultation

6.1N/A

7. Implications

Financial implications

7.1.1. Any cost implications of the strategy will be managed within existing agreed Service Directorate budgets. The financial strategy and policy may identify additional financial risk for the Council to manage.

7.2.1. The proposals concern internal risk management arrangements and do not give rise to direct legal implications.

Equalities implications

7.3.1. The proposals relate to internal governance and do not introduce changes to service delivery. No Equalities Impact Assessment is required.

7.4Procurement Implications (and include PIF database ref)

7.4.1 The proposals do not involve procurement activity. No PIF reference is required.

7.5Other Implications [Climate, HR, IT etc only when significant]

7.5.1. The proposals relate to internal governance arrangements and do not give rise to significant climate, HR, ICT or property implications.

Background papers

8.1None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management Strategy and Policy 2026 (Final Draft)Appendix 6 904 KB Download
PDF
New risk management policy strategy and planReport 801 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
DM
Daniel Mark CarrChair, apologies
TP
Councillor Terence PaulVice-Chair, present
AA
Councillor Aktharul AlamMember, present
AC
Councillor Areeq ChowdhuryMember, present, as expected, virtual
AI
Councillor Anamul IslamMember, absent
CL
Councillor Carleene Lee-PhakoeMember, absent
AM
Councillor Anthony McAlmontMember, present
TO
Councillor Thelma OdoiMember, present
MO
Councillor Melanie OnovoMember, present
AN
Alexandra NginiMember, non-voting, present, as expected, virtual
JP
Joanne PittMember, non-voting, present, as expected, virtual
PE
Pauline EganSecretary, present

All 18 on the meeting page

On this subject at Newham

Search all
  1. New risk management policy strategy and planThis decision
  2. Newham Corporate Risk Register and Annual Review of Risk Management Policy and StrategyNoted
  3. Newham Risk Management Policy and StrategyAgreed

More from Newham Audit and Governance Committee

All decisions
MeetingDecisionOutcome
30 Jul 2026 Election of Vice Chair to the CommitteeFollowing nominations and a vote, Councillor Kelly Drake was elected Vice Chair of the Audit and Governance Committee... Decided Open
11 Mar 2026 Minutes of the Last MeetingRESOLVED that the minutes of the last meeting held on 25 February 2026 (as amended) be agreed. Agreed Open
11 Mar 2026 Actions LogRESOLVED that the report be noted. Noted Open
11 Mar 2026 Quarterly Counter Fraud Progress ReportRESOLVED that the report be noted. Noted Open