AI summaryNewham Cabinet notes progress on housing improvement programme following C4 regulatory downgrade, with tenant satisfaction at 59% and fire safety remediation underway
Written from the decision and the officer reportPDF Pro
OutcomeAgreed
MoneyResource costs met from allocated programme budget; no specific figures given
What happens nextVU milestone 2 due October 2026Three amber commitments to be recovered before September; focus on resident outcomes
Who it affectsCouncil tenants in NewhamApproximately 60,000 residents in council homes
What was decided
Cabinet agreed to note progress in delivering HSIP and the Voluntary Undertaking with the Regulator of Social Housing as shown in Appendix A Report P14
Cabinet agreed to note the increased focus on three resident outcomes: safe homes, well-maintained homes, and reliable resident-focused services Report P15
Cabinet agreed to note the compliance position and direction of travel, data and governance improvements, Tenant Satisfaction Measures, and principal risks Report P16, P17, P18, P19
Why
The Regulator of Social Housing issued the Council with a non-compliant C4 grading in October 2024, requiring a formal response through a Voluntary Undertaking given in April 2026 Report 3.1
Tenant Satisfaction Measures show 59% overall satisfaction with the landlord service, indicating continued need to improve resident experience, trust and satisfaction Report 1.6, P18
The programme supports the Council's wider improvement activity in response to the Best Value Notice and Corporate Plan Priority 5 for homes for residents Report 3.1, 9.1
What happens next
Deliver VU milestone 2 by October 2026, with milestones 3 and 4 due in March and December 2027 respectively Report 7.5, 8.3
Progress three amber VU commitments back to green before September 2026 through identified recovery plans Report 7.5
Complete the Asset Management System by March 2027 and the stock condition survey by April 2027 Report 1.4, 5.3, P29
Options considered
Rejected: Do nothing. Given the C4 rating, it is not possible for the Council to do nothing. Under the Social Housing (Regulation) Act 2023, the Council is required to comply with the Regulator's judgement and reach compliance with Consumer Standards. C4 and C3 ratings are non-compliant, so the Council must achieve a C2 or C1 grade Report 10.1
Implications
Legal: The voluntary undertaking forms a binding commitment by the Council to meet all obligations in its compliance recovery plan. The Regulator may take into account any failure to honour the undertaking when making determinations about enforcement or regulatory action Report P76
Equalities: HSIP is expected to drive improvements to equalities outcomes, particularly across the Resident Access and Transparency theme where improving capture and analysis of tenant data will enable services to be better tailored to tenants and leaseholders with diverse needs Report P78
Risk: Principal risks include failure to deliver VU commitments within agreed timescales, legacy data quality issues impacting confidence in management information, capacity constraints across specialist professional and technical disciplines, and maintaining regulatory confidence whilst transformation activity is underway Report P59, P60, P61, P62
Financial: The costs of the programme's resource requirements will be met from the allocated budget for the programme. Any material variance from existing approved budget will be subject to further approval in accordance with the Council's financial regulations and governance arrangements Report P73, P74
Who and where
Council tenants in Newham Report P43, P44, P45, P46, P47
Tenants in temporary accommodation owned by the Council Report 6.5
October 2024: Regulator of Social Housing issued C4 grading Report 3.1
March 2026: VU milestone 1 achieved Report 7.5
April 2026: Council gave Voluntary Undertaking to the Regulator Report 3.1
June 2026: More than 10,000 tenancy audits completed Report P38
30 June 2026: Tenant Satisfaction Measures published on time Report 6.7
31 July 2026: Fire remedial actions progress reported to Report 1.4
October 2026: VU milestone 2 due Report 7.5
March 2027: Asset Management System implementation milestone due; VU milestone 3 due Report 1.4, 7.5
April 2027: Stock condition survey due to complete Report 5.3
December 2027: VU milestone 4 due Report 7.5
Plain English for the jargon
HSIP: Housing Services Improvement Programme, the Council's coordinated response to regulatory judgement
TSM: Tenant Satisfaction Measures, 22 performance measures set by the Regulator of Social Housing covering tenant perception and management metrics
VU: Voluntary Undertaking, a binding commitment given by the Council to the Regulator of Social Housing in April 2026 setting out its compliance recovery plan
Consumer Standards: Standards set by the Regulator of Social Housing that all registered providers must comply with, covering safety, quality, transparency and resident involvement
Decent Homes Standard: Government standard requiring social housing to be safe, warm and free from damp
C4 grading: Non-compliant regulatory judgement issued by the Regulator of Social Housing in October 2024
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Decision For the reasons set out in the report and its appendices, Cabinet RESOLVED to Agree to note i) The progress in delivering HSIP and the Council's Voluntary Undertaking with the Regulator of Social Housing as shown in Appendix A. ii) The increased focus on three resident outcomes: safe homes; well-maintained homes; and reliable, resident-focused services. iii) The compliance position and direction of travel set out in this report and Appendix B. iv) The progress in strengthening the data, systems, governance and assurance required to support these outcomes and sustain regulatory compliance. v) The 2025/26 Tenant Satisfaction Measures and the continues need to improve resident experience, trust and satisfaction. vi) The principal risks and dependencies affecting delivery and the arrangement in place to manage and assure these. Alternatives Considered Do nothing: given the C4 rating, it is not possible for the Council to do nothing. Under the terms of the Social Housing (Regulation) Act 2023, the Council is required to comply with the Regulator’s judgement and reach compliance with the Consumer Standards. C4 and C3 ratings are non-compliant, so in order to achieve compliance, the Council would be required to meet a C2 or C1 grade.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
1.1The purpose of the Housing Services Improvement Programme (HSIP) is to ensure residents live in safe, well-maintained homes and receive reliable services from a landlord that listens and responds to their needs. The Regulator of Social Housing's C4 judgement in October 2024 demonstrated that the Council could not consistently provide sufficient assurance that these outcomes were being achieved. HSIP is addressing the areas requiring improvement and delivering the commitments subsequently made through the Council’s Voluntary Undertaking (VU).
1.2A progress update against VU commitments is shown in Appendix A.
1.3As the programme moves into its next phase, the Council is increasingly assessing improvement through outcomes experienced by residents rather than the volume of programme activity undertaken. This report therefore considers progress through three key questions:
- Are residents living in safe homes?
- Are residents living in well-maintained homes?
- Are residents receiving reliable tenant-focused services?
1.4Good progress has been made this quarter. Delivery of compliance improvements and VU commitments are currently assessed as green. The
1 Council has strengthened its approach to assurance; priority housing data improvement has progressed; and delivery of an Asset Management System remains on track for March 2027. The compliance data summary in Appendix B provides the detailed trajectory across individual compliance measures, including progress in reducing outstanding fire remedial actions for the period ending 31 July 2026.
1.5The Council is also taking a more rigorous approach to understanding the condition of its homes. Properties are now only recorded as meeting the Decent Homes Standard where sufficient evidence exists to demonstrate this. Where information is incomplete, homes are recorded as non-Decent until their condition can be evidenced.
1.6Resident experience demonstrates why sustained improvement remains necessary. The 2025/26 Tenant Satisfaction Measures show 59% overall landlord satisfaction, 64% satisfaction among tenants receiving a repair, 54% satisfaction that the Council listens to tenant views and acts upon them, and 68% agreement that tenants are treated fairly and with respect.
1.7More than 10,000 tenancy audits have been completed, resulting in more than 4,000 referrals to Council services and partner agencies, including repairs, tenancy support, independent living, social care and advice services.
1.8The next phase of HSIP will therefore focus increasingly on demonstrating outcomes rather than reporting activity: whether residents are safe, whether homes are well maintained, whether services are improving, and whether the Council has the evidence and organisational capability to sustain those improvements.
Recommendations
2.1Cabinet is recommended to note:
2.1.1 Progress in delivering HSIP and the Council's Voluntary Undertaking with the Regulator of Social Housing as shown in Appendix A.
2.1.2 The increased focus on three resident outcomes: safe homes; well- maintained homes; and reliable, resident-focused services.
2.1.3 The compliance position and direction of travel set out in this report and Appendix B.
2.1.4 Progress in strengthening the data, systems, governance and assurance required to support these outcomes and sustain regulatory compliance.
2.1.5 The 2025/26 Tenant Satisfaction Measures and the continues need to improve resident experience, trust and satisfaction.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.