What was decided
Cabinet approved a procurement exercise to secure a contractor to upgrade Stratford Library's mechanical and electrical infrastructure, funded by capital investment and an external grant contribution.
Cabinet agreed to use a £0.531m grant from the Carbon Offset Fund to deliver the project.
Cabinet delegated authority to the Corporate Director of Inclusive Economy and Housing to award the contract to the successful contractor.
Why
The library's heating and cooling system is at the end of its life, and doing nothing would risk non-compliance with statutory legislation, further deterioration, costly repairs, service disruption and complaints from residents.
Procurement colleagues reviewed framework options and found no suitable framework on which all the recommended contractors are listed, ruling out a framework route.
What happens next
Run a procurement exercise to appoint a contractor for the Stratford Library works.
The Corporate Director of Inclusive Economy and Housing will award the contract to the successful contractor.
The money
- £0.531m Grant contribution from the Carbon Offset Fund towards the Stratford Library upgrade project
Options considered
- Rejected: Do nothing. Heating and cooling system is at end of life, with risk of non-compliance, deterioration, costly repairs, service disruption and resident complaints
- Rejected: Use a procurement framework. No suitable frameworks exist on which all the recommended contractors are listed
Implications
- Legal: Inaction would risk non-compliance with statutory legislation covering the building's heating and cooling system.
- Risk: Failure to act could lead to further deterioration, costly repairs, service disruption and complaints from residents.
- Climate: Project draws on a Carbon Offset Fund grant, supporting carbon reduction objectives for the building.
- Financial: Project is funded through a combination of capital investment and an external grant contribution of £0.531m.
Who and where
- Users of Stratford Library and local residents
Timeline
- 2026-10-20: Cabinet approved the procurement exercise and delegated contract award authority
Plain English for the jargon
- HVAC: Heating, ventilation and air conditioning systems within a building
- Carbon Offset Fund: A grant fund used to support projects that reduce carbon emissions