Resolved
Agreed That details of the final outturn report, the reasons for the overspend and lessons learned from the project, be noted.
Governance and Audit Committee agreed this item on Thursday 24 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed That details of the final outturn report, the reasons for the overspend and lessons learned from the project, be noted.
Audit Committee Part 1
Date: 24 September 2015
Item No: 06
Subject Update: Market Square Bus Station – Project Overspend Purpose To update the Audit Committee on Market Square Bus Station project.
Author Streetscene Head of Service (Interim)
Ward ALL
Summary As required by Standing Orders (projects likely to overspend by 10% of more) the Audit Committee received a paper of a potential overspend on the above project.
Proposal To provide a final outturn report to the committee of the overspend encountered on the above scheme
Action by Head of Streetscene
Timetable Immediate Background The project comprised of two distinct phases:
Phase 1 main construction which was due to commence 12th November 2012. Phase 2 the fit out which was due to commence 27th July 2013.
Members should refer to previous papers produced and discussed in November last year.
Progress since last Member Briefing The original bus station project awarded to Encon construction Ltd was forecast to be completed for a sum of £1.7 million. The final certificated outturn has recorded an excess cost of £163,000 following extensive negotiations on the substantial elements of contractual claims submitted by Encon .with a final certificate of £1.863,000
Whilst this still represents an overspend for NCC, it is a considerable reduction on the liability reported at the previous Committee.( circa £2`065`000 ) Members will already be aware – from the earlier report- the significant areas where improvements could be made.
A key aspect is to better understand the risk associated with major project delivery and to both make provision for ‘optimism bias’ where people can be overly optimistic in assessing costs; but equally the skills and capacity of the NCC staff in delivering projects.
It should be noted the contractor who built the bus station entered in to negotiations and had a very strong and lucid account of issues and complications in the project. Equally NCC drew on the skills and resources of officers and an interim consultant in negotiating a marked reduction and refund from the contractor. As stated above, whilst any overspend of public project must be challenged, the quantum of that overspend has reduced markedly.
Given the nature of public funding and recent experiences , the NCC Project team has been dissolved as funding for that team no longer exists and several key Officers left NCC last year. Equally, Streetscene project processes have improved significantly , and there is a clear requirement for formal project management qualification (i.e. Prince 2) for all significant projects officers in the future. . Moreover the choice of engineering contract is one that demands appropriate expertise – if NCC does not have that in house capability it will consider how to fund appropriate external expertise to be engaged within any future major project delivery.
Streetscene Management has already instigated a lessons learnt investigation. This is seeking to understand what happened and crucially how to mitigate the risk of such future issues. This report will consider issues of Governance, Project Management expertise and the skills and experience of our supply chain partners.
Action As reported in the previous report “In accordance with Council Standing Orders and Financial Regulations, any contractual overspend of more than 10% must be reported to Audit Committee.
Financial Summary
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Overspend on Market Square Bus SchemeReport | 147 KB | DownloadRead as text |
Follow Governance and Audit Committee at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Mar 2024 | Member Development Self Evaluation ExerciseAgreed the wording of the draft self-assessment questionnaire which was appended to the report. iii. Agreed a timesca... | Agreed | Open |
| 25 May 2023 | Update on PTU Taxi Contracts resulting in Second Unsatisfactory Opinion- January 2023The Governance and Audit Committee noted the update from the Head of City Services and requested further updates for ... | Noted | Open |
| 25 May 2023 | Update on Call in of Director of Social Services and Head of Service re the internal Audit of Adoption Allowances resulting in a Second Unsatisfactory Opinion- January 2023That the Committee noted the comments of The Acting Chief Internal Auditor and that the Strategic Director for Social... | Noted | Open |
| 25 May 2023 | Forward Work ProgrammeThe Governance and Audit Committee endorsed the proposed schedule for future meetings, confirmed the list of people i... | Decided | Open |
| 30 Mar 2023 | Work ProgrammeThe Governance and Audit Committee endorsed the proposed schedule for future meetings, confirmed the list of people i... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.