Report Performance Board Part 1
Date: 29th March 2016
Item No:
Subject Data Quality Review Purpose To advise the Board of the findings from the Wales Audit Office’s recent review of the Council’s data quality.
Author Rachel Kalahar – Senior Performance Management Officer
Ward All
Summary The Wales Audit Office has recently conducted a data quality review which looked at how the Council collects analyses and retains its performance data. As part of this review, the Wales Audit Office identified some areas for improvement; the conclusions of this report will be included in the corporate assessment review 2016.
Proposal The board are requested to receive the Wales Audit Office report and note its findings
Action by Corporate Performance Team
Timetable Immediate This report was prepared after consultation with:
Heads of Service Operational Performance Network Background As part of the 2014/15 Data Quality review the WAO made a recommendation that National Strategic Indicator data be collected and published in accordance with the Welsh Government definitions. A Proposal for Improvement was also made that data collection arrangements needed to be more robust including the arrangements in place for performance management being rigorously implemented in Service Areas, reconciliation of data held in VIEWS and that submitted and a complete audit trail of the validation of data.
In the review carried out in 2015/16 the WAO have recognised the work undertaken to address the recommendation made in 2014/15 and “found that the Council has addressed our statutory recommendation and is continuing to improve its data quality arrangements. However, there are still weaknesses in these arrangements, which need to be addressed to ensure that its published performance data is accurate.” And they have issued the following proposal for improvement;
Action Plan New software has been purchased to replace the current Performance Management System; this will lead to new processes around data quality and accuracy. Over the next 12 months focus will be on:
Ensuring all relevant measures are recorded on the new software. Training and supporting staff – ensuring that staff are confident in using the new software Embedding changes to data entry, visibility and quality Providing greater challenge and accountability on accuracy of data through sample checking. Recording risk assessment approach used to identify indicators for Internal Audit. Ensuring Internal audits findings are reported at an appropriate level. Greater checking of published documents.
Financial Summary There are no direct financial implications arising from this report Risks:
Risk Impact of Probability What is the Council doing or Who is Risk if it of risk what has it done to avoid the responsible for occurs* occurring risk or reduce its effect dealing with the (H/M/L) (H/M/L) risk? Improvements M M Embed processes and HoS, service not made to procedures to mitigate managers, data quality against data inaccuracies Operational processes Performance Network, Performance Team Data is M L Ensuring that the self- HoS, service inaccurate assessment processes are managers, robust and all staff involved operational are trained with a good performance understanding of the network, processes and the impact on Performance the council if data is Team inaccurate
Links to Council Policies and Priorities Accurate performance data underpins the Council’s key policies including service plans, and the Improvement Plan.
Options Available a) To note the contents of the Data Quality Review and approve the proposed actions and monitor their effectiveness b) Reject the proposed actions
Preferred Option The preferred option is a. The Board is well positioned to drive forward the data quality improvements by monitoring the proposed actions and roll out of the new software.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Data Quality ReviewReport | 300 KB | DownloadRead as text |
PDF |
NCC DQR report 2015-16 FinalReport | 238 KB | Download |
Follow Previous Term - Performance Board at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Mar 2016 | Improvement Plan 2016-2018Agreed I. To endorse the eight Improvement Objectives included in the Improvement Plan for 16-18 II. To agree the Imp... | Agreed | Open |
| 29 Mar 2016 | Ensuring the best educational outcomes for childrenAgreed To note the outcomes as reported and to endorse the action being taken by the Cabinet Member and Officers | Agreed | Open |
| 29 Mar 2016 | Improving outcomes for youth justiceAgreed To note progress and receive further reports on progress on this important service at future meetings | Agreed | Open |
| 9 Dec 2015 | Adult and Community Services: Theme 1: Supporting older people leaving hospitalAgreed To note progress on the priorities and the activities planned to maintain progress. | Agreed | Open |
| 9 Dec 2015 | Adult and Community Services: Theme 2: Improving care and support services for adultsAgreed To note progress on the priorities and the activities planned to improve progress. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.