WAO Corporate assessment

Decided Executive 1 paper

Cabinet decided this item on Wednesday 21 December 2016. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

CAB 67/16 The Leader of the Council introduced a report setting out the progress made in addressing the recommendations and proposals for improvement made by the Wales Audit Office. (WAO) The WAO presented their most recent review of the Corporate Assessment at the October Cabinet meeting, it contained four recommendations which was a reduction from the seven recommendations that the Council previously had. The action plan presented to Cabinet allowed for monitoring of progress in addressing the remaining recommendations and proposals for improvement. The Leader stated that good progress is being made towards achieving the actions and embedding the changes made into our everyday work. The Leader stated that the report also included progress made against proposals for improvement from previous corporate assessment reviews and other WAO reviews – there are 14 of these and 10 are now considered closed. The remaining four are on-going although good progress has been made and further actions will continue to be monitored. Cabinet was reminded that Newport was the first authority to go through this process and this probably contributed to the original number of recommendations. The improvement was continuing despite financial and legislative pressures .
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 25th November 2016

Item No:

Subject Progress update on the action plan to address the Wales Audit Office recommendations and proposals for improvement. Purpose To present Cabinet with the progress made in addressing the recommendations and proposals for improvement made by the Wales Audit Office in their Review of progress in addressing the Corporate Assessment and Corporate Assessment Follow-up recommendations 2015/16.

Author Chief Executive

Ward All

Summary  This update used to form part of the Improvement Plan Quarterly Update report, it is now a separate report to address comments from the Wales Audit Office regarding the visibility and discussion of the Corporate Assessment Action Plan. There is also some uncertainty around the future of the Improvement Plan due to possible changes in legislation. This new separate report allows greater visibility and oversight for Cabinet Members.

 At the October 2016 Cabinet meeting the Wales Audit Office presented the findings from their ‘Review of progress in addressing the Corporate Assessment and Corporate Assessment Follow-up recommendations 2015/16’ which examined the Council’s progress in addressing recommendations made in the full Corporate Assessment of the Council in 2013 and the Review that took place in 2014/15.

 This reduced the number of recommendations from 7 to 4 and with 3 proposals for improvement.

 The Council compiled an action plan to address the WAO’ recommendations and proposals for improvement which was also presented to Cabinet in October 2016.

 There are also a number of proposals for improvement outstanding from previous corporate reviews; progress made against these is also included.

 This report is a quarterly update of progress made against the actions outlined in the Council’s action plan and actions planned for the next quarter. This enables Cabinet Members to consider whether actions remain appropriate to meet the recommendations and proposals for improvement, and to evaluate whether actions have been completed in a timely manner. Proposal Cabinet are requested to:  Note the progress made towards meeting the recommendations and proposals for improvement and query any areas where progress has been delayed.  Receive further quarterly monitoring reports on the progress towards meeting recommendations and proposals for improvement.

Action by Chief Executive, Strategic Directors and Heads of Service

Timetable immediate This report was prepared after consultation with:

 Chair of Cabinet  Chief Executive  Strategic Directors  Heads of Service

Signed Background The Corporate Assessment Review presented the Wales Audit Office findings of progress following the full Corporate Assessment of the Council in 2013.

The full Corporate Assessment 2013 examined the council’s capability to deliver its priorities and improved outcomes for citizens.

Corporate Assessment Review During 2014/15 the Wales Audit Office reviewed the progress that the Council had made in implementing the Recommendations and Proposals for Improvement from the full Corporate Assessment in 2013. The Corporate Assessment Review contained seven recommendations.

The overall conclusions from the Corporate Assessment Review were: “The Council has made improvements in some aspects of its arrangements, however in other areas the scale and pace of change required has not been achieved, and longstanding governance weaknesses remain”

Review of progress in addressing the Corporate Assessment and Corporate Assessment Follow- up recommendations During February 2016 the WAO completed fieldwork and a document review to assess the progress made against the recommendations made in the original 2013 Corporate Assessment as well as the 2014/15 review.

The 2015/16 Review of progress in addressing the Corporate Assessment and Corporate Assessment Follow-up recommendations contained four recommendations which was a reduction from the seven recommendations in the 2014/15 review.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WAO Corporate assessmentReport 409 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
DW
Councillor Debbie WilcoxChair, present
PC
Councillor Paul CockeramCommittee Member, present
GG
Councillor Gail GilesCommittee Member, present
DH
Councillor Debbie HarveyCommittee Member, present
RJ
Councillor Roger JeavonsCommittee Member, present
RP
Councillor Robert PooleCommittee Member, present
JR
Councillor John RichardsCommittee Member, present
RT
Councillor Ray TrumanCommittee Member, present
MW
Councillor Mark WhitcuttCommittee Member, present

On this subject at Newport

Search all
  1. WAO Corporate assessmentThis decision
  2. WAO Report - Corporate SafeguardingAgreed
  3. WAO Corporate Assessment - Review of Progress and Corporate Assessment Follow-up Recommendations 2015-16Decided

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open