CAB 44/17 The Cabinet Member for Education and Skills presented the report to approve the basis for the Council’s submission to Band B of the Welsh Government’s 21 st Century Schools Programme. Band B of the programme was due to begin in April 2019 and last until March 2024. The Cabinet Member highlighted the projects which had been completed through Band A of the programme, and the approach that had been taken to putting together and prioritising the Band B submission. It was highlighted that the list had to be prioritised, as the system worked on match funding – this was an ambitious bid based on what the local authority could afford. Decisions on which schools to include had not been taken lightly, and were the result of extensive analysis of the condition and needs of buildings across the school estate. To approve the preferred option as the basis for submitting Newport’s Strategic Outline Programme for 21 st Century Band B. Cabinet Member for Education and Skills, Chief Executive Officer, Strategic Director – People, Strategic Director – Place, Head of Finance, Head of Law and Regulation, Managing Director – Newport NORSE. Implemented By: Cabinet Members, Head of Finance, Senior Leadership Implementation Timetable: Immediate To approve the preferred option as the basis for submitting Newport’s Strategic Outline Programme for 21 st Century Band B.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject 21st Century Schools Programme – Submission of Strategic Outline Programme Purpose To approve the basis upon which the City Council makes its submission to Band B of the Welsh Government’s 21st Century Schools Programme.
Author Lucy Jackson, Service Manager, Planning and Resources
Ward All
Summary Welsh Government’s 21st Century Schools Programme provides investment for school infrastructure improvement.
Band B of this programme is due to begin in April 2019 and last until March 2024.
A short list of schools to be included within Newport’s programme has been identified. Priority for inclusion has been determined by the Council’s strategic aims and those of the 21st Century Schools Programme namely to reduce the number of poor condition schools and ensure that there are the right size schools in the right location.
Scoping has been undertaken of individual proposals to ensure the cost of the overall programme will be within the intended £70m value of the programme.
The deadline for local authorities to submit their Strategic Outline Programme is 31 July 2017.
Proposal To approve the preferred option as the basis for submitting Newport’s Strategic Outline Programme for 21st Century Band B.
Action by Chief Education Officer
Timetable The Strategic Outline Programme to be submitted to Welsh Government by 31 July 2017. This report was prepared after consultation with:
Cabinet Member for Education and Skills Chief Executive Officer Strategic Director – People Strategic Director - Place Head of Finance Head of Law and Regulation Managing Director, Newport NORSE Signed Background
The 21st Century Schools Programme
The 21st Century Schools and Education Programme is Welsh Government’s flag ship schools infrastructure improvement programme. The aims of the programme are to:
Reduce the number of poor condition schools and colleges; Ensure that we have the right size schools and colleges, in the right location that:
o Provide enough places to deliver Welsh and English medium education; and o Ensure the effective and efficient use of the educational estate
It is acknowledged by Welsh Government that demand for investment is high, with around 450 schools and college campuses in Wales identified as suffering from serious deterioration or being life expired. Further background about the 21st century Schools Programme is at APPENDIX ONE.
In December 2016, following a request by Welsh Government, the Council provided an ‘in principle’ submission that our Band B programme would include:
Secondary school remodelling to a level of c£35m Primary school re-development to a level of c£35m
Whilst it is acknowledged that significant investment in the school estate is required, this submission was made on the assumption that a 50/50 grant intervention rate would be in place. A new medium term capital programme and its impact on the MTFP is currently being developed in line with budget headroom and strategic priorities and the investment available for the 21CS programme will be factored in to the programme.
Schools to be included within the programme
Following the in principle submission, feasibility and scoping has been undertaken utilising the expertise of the Council’s delivery partner, Newport Norse. Internal workshops have taken place to identify schools that are a priority for inclusion within the programme and engagement has taken place with proposed short listed schools in order to develop the scope and cost of potential work.
The following education criteria were the basis for developing a prioritised list of schools:
• Sufficiency of School Places (SSP)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.