Cabinet, Wednesday 20 December 2017 at 4.00pm

Development Loan Facility: IAC Building

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 20 December 2017. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

CAB 70/17 The Leader of the Council presented the report, which asked Cabinet to decide whether or not to agree the proposed loan arrangement for the IAC building in principle. The preferred option was to agree the loan arrangement in principle, because the redevelopment of the IAC building was a significant investment that was critical to the future of the city centre. The Cabinet Members present all spoke in favour of the proposal, outlining the benefits and wide ranging impact of the outlined scheme, including: · The proposal would bring a key economic anchor to the Northern end of the city, stimulating the creation of future high-quality office space and encouraging further investment and footfall into the city centre. · Ancillary benefits included the creation of construction jobs, training opportunities, and financial benefit to local construction companies. · The property was obsolete in its current manifestation and served little purpose other than to demean perceptions of the city centre to its visitors. · If Newport was to maintain the momentum generated by the regeneration of the city centre then it was vital that aspirational and transformational developments such as the proposal for the IAC building were secured and delivered. 1. To approve a loan facility of up to £12 million for the redevelopment of the IAC Building by Garrison Barclay on commercial terms to be agreed by the Head of Finance and the Head of Law and Regulation, subject to satisfactory due diligence and financial appraisal. 2. To authorise the Head of Law and Regulation and the Head of Finance to agree the terms of the Funding Agreement and to attend to the sealing and signing of the appropriate legal documentation in relation to the loan and security. Leader of the Council; Strategic Director – Place; Head of Finance; Head of Law and Regulation; Head of People and Business Change. Implemented By: Head of Regeneration, Investment and Housing; Head of Law and Regulation; Head of Finance. Implementation Timetable: Immediate 1. To approve a loan facility of up to £12 million for the redevelopment of the IAC Building by Garrison Barclay on commercial terms to be agreed by the Head of Finance and the Head of Law and Regulation, subject to satisfactory due diligence and financial appraisal. 2. To authorise the Head of Law and Regulation and the Head of Finance to agree the terms of the Funding Agreement and to attend to the sealing and signing of the appropriate legal documentation in relation to the loan and security.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 20 December 2017

Subject Development Loan Facility: IAC Building Purpose To seek commitment from Cabinet to provide a loan facility (up to 12,000,000) to Garrison Barclay Estates to finance the regeneration of 22-29 Mill Street (the IAC building).

Author Keir Duffin Head of Regeneration Investment and Housing Gareth Price – Head of Law & Regulation Meirion Rushworth – Head of Finance

Ward Allt -yr -yn

Summary The redevelopment of the IAC building (also known locally as the former sorting office) has long been a key regeneration site for the authority. The long-vacant building has a deleterious effect on the city centre due to its high visibility, dereliction, and adjacency to the main railway line. NCC is now at a point where a private developer has approached the council to seek a loan facility in order to redevelop the property as ‘grade A’ office space with an associated hotel facility. The opportunity to redevelop this premises will therefore address the poor impact the building has on the city centre, in addition to supporting the emerging strategic need to encourage the development of high-quality office and hotel accommodation in close proximity to major geographic transport nodes within the city centre.

Proposal (a) To approve a loan facility of up to £12 million for the redevelopment of the IAC Building by Garrison Barclay on commercial terms to be agreed by the Head of Finance and the Head of Law and Standards, subject to satisfactory due diligence and financial appraisal.

(b) To authorise the Head of Law and Standards and the Head of Finance to agree the terms of the Funding Agreement and to attend to the sealing and signing of all the appropriate legal documentation in relation to the loan and security.

Action by Keir Duffin, Head of Regeneration, Investment & Housing Head of Law & Regulation Head of Finance

Timetable Immediate This report was prepared after consultation with:

 Leader of the Council  Strategic Director - Place  Head of Finance (Chief Finance Officer)  Head of Law and Regulation (Monitoring Officer)  Cabinet Member for Regeneration and Housing

Signed  Background

.1 The IAC building, also known as the former sorting office, is a large vacant property (circa 55,000 square feet) that occupies a key location within the city centre. Whilst the site on Mill Street is on the periphery of the centre, the stature of the building makes its vacancy and poor aspect highly visible to visitors to the city centre and particularly those arriving into the city via the railway station. The adjacency of the south Wales main line ensures the derelict property is visible even to those passing through Newport via train. Its ongoing lack of use thus paints an unfortunate view of the city centre and its offering.

.2 Newport currently has a wealth of vacant office space available, but as none of it within the city centre is of a high standard vacancy is prevalent. The tired accommodation is generally unappealing to potential tenants, particularly high-value, high-growth occupiers who prefer to be based in the more expensive but desirable office districts of Bristol and Cardiff. Nevertheless, the strategic location of the city centre and its relative affordability, improving quality of offer and transport infrastructure mean that it is an unexploited resource in terms of the development of high-quality office space.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Development Loan Facility: IAC BuildingReport 316 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
DW
Councillor Debbie WilcoxChair, present
PC
Councillor Paul CockeramCommittee Member, present
GG
Councillor Gail GilesCommittee Member, present
DH
Councillor Debbie HarveyCommittee Member, present
RJ
Councillor Roger JeavonsCommittee Member, present
DM
Councillor David MayerCommittee Member, present
JM
Councillor Jane MuddCommittee Member, present
RT
Councillor Ray TrumanCommittee Member, present
MW
Councillor Mark WhitcuttCommittee Member, apologies

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies