Resolved
Agreed: For the Annual Government Statement to be updated.
Governance and Audit Committee agreed this item on Thursday 24 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed: For the Annual Government Statement to be updated.
Report Audit Committee Part 1
Date: 24 January 2019
Item No: 6
Subject Internal Audit – Progress against audit plan 2018/19 Quarter 3 Purpose To inform Members of the Council’s Audit Committee of the Internal Audit Section’s progress against the 2018/19 agreed audit plan for the first 9 months of the year by providing information on audit opinions given to date and progress against key performance targets.
Author Chief Internal Auditor
Ward General
Summary The attached report identifies that the Internal Audit Section is making good progress against the 2018/19 audit plan and internal performance indicators. The majority of Internal Audit reviews have been given a Reasonable opinion; adequately controlled although risks identified which may compromise the overall control environment; improvements required; reasonable level of assurance.
Proposal 1) The report be noted by the Council’s Audit Committee
Action by The Audit Committee
Timetable Immediate This report was prepared after consultation with:
Chief Financial Officer Monitoring Officer Head of People and Business Change
Signed Background
1. This report aims to inform Members of the Audit Committee of progress of work undertaken by the Internal Audit Section of the Council against the agreed audit plan. Progress against the audit plan for the first 9 months of the year will be reported.
2. The report gives Members assurance (or otherwise) on the adequacy of the internal control environment operated within the Council by providing the audit opinions on work undertaken at the end of Q3.
Internal Audit Staffing
3. The team currently operates with an establishment of 8 audit staff. At the start of the year there were 8 audit staff in the team, reduced to 7 during Q2 due to an internal promotion; we have had a vacancy in the team since August 2018.
4. In order to take account of the budget savings contribution and the delayering exercise required by senior management following the job evaluation exercise, the Internal Audit team was restructured and reduced in numbers in 2016/17.
5. The relationship with Monmouthshire County Council (for sharing of the Chief Internal Auditor) continues.
Audit Plan
6. The Public Sector Internal Audit Standards (PSIAS) (IIA) came into force from April 2013 (updated March 2017) which the team needs to ensure it is compliant with as it carries out work in line with the Audit Plan. These standards replace the former Code of Practice for Internal Audit within Local Government (CIPFA).
7. A requirement of the PSIAS is for the Internal Audit team to be externally assessed once every five years to ensure compliance with these Standards. The Welsh Chief Auditors’ Group proposed an option of a peer review in order to meet the requirements of this external assessment, which has been agreed by respective S 151 Officers of local authorities in Wales. Newport’s peer review took place in 2017/18; the outcome being that the team is generally compliant with the Standards, with no significant areas of non-compliance; this is the highest standard of compliance.
8. The 2018/19 Draft Audit Plan was agreed by the Audit Committee on the 28th March 2018 with the Final being approved on the 24th May 2018.
Performance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan: Progress (Quarter 3)Report | 144 KB | DownloadRead as text |
Follow Governance and Audit Committee at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Mar 2024 | Member Development Self Evaluation ExerciseAgreed the wording of the draft self-assessment questionnaire which was appended to the report. iii. Agreed a timesca... | Agreed | Open |
| 25 May 2023 | Update on PTU Taxi Contracts resulting in Second Unsatisfactory Opinion- January 2023The Governance and Audit Committee noted the update from the Head of City Services and requested further updates for ... | Noted | Open |
| 25 May 2023 | Update on Call in of Director of Social Services and Head of Service re the internal Audit of Adoption Allowances resulting in a Second Unsatisfactory Opinion- January 2023That the Committee noted the comments of The Acting Chief Internal Auditor and that the Strategic Director for Social... | Noted | Open |
| 25 May 2023 | Forward Work ProgrammeThe Governance and Audit Committee endorsed the proposed schedule for future meetings, confirmed the list of people i... | Decided | Open |
| 30 Mar 2023 | Work ProgrammeThe Governance and Audit Committee endorsed the proposed schedule for future meetings, confirmed the list of people i... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.