Resolved
Cabinet agreed to meet the increased costs of the project in order to allow the proposal to proceed.
Cabinet agreed this item on Wednesday 15 June 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet agreed to meet the increased costs of the project in order to allow the proposal to proceed.
Report Cabinet Part 1
Date: 15 June 2022
Subject: Information Station Project Purpose To provide an update on project costs and seek a commitment to meet the costs of project overspend in order to proceed with the delivery of the scheme.
Author Head of Regeneration and Economic Development
Ward All
Summary In December 2019 Cabinet agreed to seek an alternative commercial use for the ground and first floor of the Information Station as a tech hub and to relocate current staff and services to the Central Museum and Library. The sub lease of the Information Station was offered as part of a competitive tender to technology providers. On the basis of the tendered rent and their proposed business model, Tramshed Tech were identified as the successful operator. The face-to-face services were to relocate to the Central Library and Museum (CL&M) building and £1.3m of Welsh Government Transforming Towns funding was awarded for the refurbishment of the CL& M building.
In March 2020 the UK went into lockdown and face to face services were closed in line with government regulations. Face to face provision was restarted in September 2021 from the temporary location at the Riverfront. However due to extensive issues with the landlord of the Information Station (ArchCo) with regard to the consent to sub-lease, coupled with the global increase in price for construction projects and the ongoing delays, this has resulted in a budget variance of £140k.
ArchCo have now given their consent to the sub lease to Tramshed Tech and the works package for the CL&M building has been retendered. This price is held until 30th June 2022.
Proposal To agree to meet the increased costs of the project in order to allow the proposal to proceed.
Action by Head of Regeneration and Economic Development
Timetable Immediate This report was prepared after consultation with:
Chief Executive Head of Law and Standards Head of Finance Head of People & Business Change
Signed Background In December 2019 Cabinet agreed to seek an alternative commercial use for the ground and first floor of the Information Station and to relocate current staff and services to the Central Museum and Library (CL&M). The building is not owned by the Council and the upper floors of the building have already been sub leased to Cardiff University to deliver the National Software Academy. The Council’s remaining term on the building was offered as a sub lease to technology providers in order to deliver a tech hub in the City Centre. In addition to supporting regeneration and economic development of the City Centre, sub-leasing the ground and first floor of the Information Station was seen as an opportunity to reduce expenditure and dependency on third party owned property. This also aligns with corporate commitments to rationalise and maximise the Council’s asset portfolio and use our own buildings more effectively.
A competitive tendering exercise was undertaken and on the basis of the tendered rent and proposed business model, Tramshed Tech were identified as the successful operator.
The face-to-face services were to relocate to the CL&M building and £1.3m of Welsh Government Transforming Towns funding was awarded for the refurbishment of the CL& M building. However in March 2020 the UK went into lockdown and face to face services were closed in line with government regulations. Face to face provision was restarted in September 2021 from the temporary location at the Riverfront. This temporary location was considered reasonable due to the need to be move at pace to deliver this project as well as minimise disruption for residents which would arise from multiple moves of the service. However due to extensive issues with the landlord of the Information Station (ArchCo) with regard to the consent to sub-lease coupled with the global increase in price for construction projects, the overall budget has increased by £140k.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Information Station ProjectReport | 291 KB | DownloadRead as text |
Follow Cabinet at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. | Approved | Open |
| 8 Jul 2026 | Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... | Approved | Open |
| 8 Jul 2026 | Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. | Approved | Open |
| 8 Jul 2026 | Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... | Agreed | Open |
| 17 Jun 2026 | Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.