Cabinet noted this item on Wednesday 18 October 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet 1. Noted the need for a ... view the full minutes text for item 5.
Report Cabinet Part 1
Date: 18 October 2023
Subject Bassaleg Bridge Purpose To update Cabinet on the current position related to Bassaleg Bridge and to advise on next steps.
Author Head of Infrastructure
Ward Graig
Summary Bassaleg Bridge connects Caerphilly Road to a small residential development known as Forge Mews, located east of the River Ebbw at Bassaleg. The bridge also facilitates pedestrian movements in the locality including learners at Bassaleg Comprehensive School. The bridge also carries multiple utility services with other utility services in close proximity.
The bridge suffered significant scour damage undermining its support resulting in an emergency closure in August 2021 Following initial closure, works to stabilise the structure were completed in September 2021, which allowed the reopening of the bridge to pedestrians, with the associated implementation of a monitoring system to detect any movement to ensure ongoing safe use of the structure. An emergency vehicle access from the adjacent A467 has been maintained. This method of maintaining access for pedestrians with ongoing monitoring and the maintenance of the access for emergencies will be continued.
Following this initial stabilisation work, the Council’s Consultants progressed work to seek to repair and rehabilitate the structure as the preferred option, but it has become clear that this is not viable.
Following this conclusion, the Council has commissioned an options appraisal report from its consultants to consider the future of the structure and options that could be progressed in lieu of repair.
Proposal Cabinet to note the need for a new structure and agree that Option 3 is preferred option. Agree and note the Weltag assessment required to assist in the above and to assist in securing external funding.
Action by Head of Infrastructure
Timetable Immediate This report was prepared after consultation with: ▪ Executive Board ▪ Council’s Consultants
Signed Background Bassaleg Bridge is a reinforced concrete structure built in the 1940`s and carries a two-way single lane carriageway that connects Caerphilly Road to a small residential development known as Forge Mews, being a development of nineteen properties located east of the River Ebbw at Bassaleg. The bridge also facilitates pedestrian movements in the locality including learners at Bassaleg Comprehensive School.
The bridge has suffered significant damage caused by floodwater scour to the western pier, whereby the foundations were washed away. The western pier foundation was found to have detached itself from the structure due to a scour hole beneath, leaving only a small portion of support remaining to the downstream beams. Extensive structural cracking occurred because of the loss of support to the pier.
Following an initial analysis by the Council’s Consultants, the structure was found to have no live load capacity and was under significant risk of collapsing under its own weight if further loss of support occurred to the remainder of the western pier. The bridge was deemed to be at risk of failure and a decision was taken by the Council to immediately close the bridge on 6 August 2021.
As the bridge is the only means of access for residents, their vehicles, goods and services, a temporary gated emergency access road was created off the adjacent A467 dual carriageway.
In addition to the temporary closure of the bridge, NCC commissioned significant structural monitoring and pier stabilisation works.
These works were undertaken in two phases, the first to fill the scour hole beneath the pier and the second to grout the void between the pier and the foundation. The stabilisation works were completed in September 2021.
Although the stabilisation works addressed the immediate risk of the pier succumbing to scour and the collapse of the bridge deck under its own weight, these intervention measures alone were not enough to allow the bridge to be re-opened to vehicles.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bassaleg BridgeReport | 149 KB | DownloadRead as text |
Follow Cabinet at Newport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. | Approved | Open |
| 8 Jul 2026 | Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... | Approved | Open |
| 8 Jul 2026 | Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. | Approved | Open |
| 8 Jul 2026 | Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... | Agreed | Open |
| 17 Jun 2026 | Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.