To delegate to the Head of Education the authority to take and/or approve such steps as are necessary to implement the delivery of the Strategic Outline Programme approved by the Welsh Ministers in August 2024, including the approval of any expenditure and the details of any scheme, design, plan or budget, provided that such expenditure or details are consistent with the provisions of the approved Strategic Outline Programme and any relevant Council plans, policies or procedures and all prevailing legislative requirements and provided further that: a) The Head of Education shall provide regular reports on progress to the Cabinet Member for Education and Early Years; and b) The Cabinet shall be provided with a report: on progress at the end of each phase of the programme; or in any instance where a variation to the agreed programme, requires consideration and/or approval by the Cabinet or should it become apparent that the allocated budget would no longer be sufficient to deliver the agreed programme.
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject Sustainable Communities for Learning Rolling Programme Purpose To confirm that the Head of Education has authority to progress the individual projects within the approved Sustainable Communities for Learning Rolling Programme at the relevant time and within the agreed parameters.
Author Assistant Head of Education – Resources
Ward All
Summary Welsh Government’s Sustainable Communities for Learning Programme provides match funded investment for school infrastructure improvements at a 65% intervention rate. In March 2024, Cabinet agreed the investment objectives for the next wave of the Council’s scheme and confirmed that a Strategic Outline Programme (SOP) could be submitted to Welsh Government for consideration. Newport’s SOP was subsequently drafted and submitted and was approved by Welsh Government in August 2024.
The new 9-year programme is split onto three 3-year phases, reflecting priorities driven by strategic aims which include reducing poor quality school accommodation, ensuring a sufficiency of school places to meet demand across primary and secondary sectors, and creating additional Welsh-medium places and pathways to meet the ambitious targets outlined in the Council’s Welsh in Education Strategic Plan.
Earlier this year, Cabinet approved the 9-year Rolling Programme as an addition to the overall Capital Programme, at the funding profile agreed within the approved SOP. The Council has also approved its overall Capital and Treasury Strategy for 2025/26, and this includes the next 5-year Capital Programme. Alongside this, early planning for Phase 1 projects has now commenced.
Proposal To delegate to the Head of Education the authority to take and/or approve such steps as are necessary to implement the delivery of the Strategic Outline Programme approved by the Welsh Ministers in August 2024, including the approval of any expenditure and the details of any scheme, design, plan or budget, provided that such expenditure or details are consistent with the provisions of the approved Strategic Outline Programme, any relevant Council plans, policies or procedures and all prevailing legislative requirements.
Action by Chief Education Officer
Timetable Immediate This report was prepared after consultation with: ▪ Cabinet Member for Education & Early Years ▪ Corporate Management Team Background The Welsh Government’s Sustainable Communities for Learning programme is delivered in partnership with local authorities and is a long-term investment in schools to develop them as hubs for learning and to reduce the number of poor condition buildings by focusing on providing the right schools in the right places. The programme was launched in 2014 and was initially based on 5-year fixed investment bands. However, following the end of the phase known as Band B, the programme transitioned to a more flexible Rolling Programme, based on 9-year investment plans which should be reviewed at least every 3 years.
In March 2024, Cabinet agreed the investment objectives upon which the Rolling Programme should be based, and the resultant Strategic Outline Programme (SOP) was subsequently approved by Welsh Government in August 2024. Earlier this year, Cabinet approved the Rolling Programme as an addition to the overall Capital Programme, at the funding profile agreed within the approved SOP. The Council has also approved its overall Capital and Treasury Strategy for 2025/26, and this includes the next 5- year Capital Programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.