Cabinet Approvals - Allocation of Reserves

Approved Executive 1 paper

AI summaryCabinet approved use of reserves and a change of use of a previously agreed reserve, and added a capital project to the Council's capital programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUse of reserves and a capital project addition
MoneyNot stated
What happens nextJune/July CabinetTo confirm 2025/26 budget underspend and top up Transformation Reserve
Who it affectsCouncil capital programme and reservesIncluding the Transformation Reserve

What was decided

Cabinet reviewed and approved the use of reserves and the change of use of a previously agreed reserve, and approved a capital project for inclusion in the Council's capital programme.

Cabinet noted the Head of Finance recommendation that further funds be transferred into the Transformation Reserve from any 2025/26 budget underspending.

Why

The papers supplied do not set out the reasons for the decisions.

What happens next

Any 2025/26 budget underspend, once confirmed at the June/July Cabinet meeting, is to be transferred into the Transformation Reserve to support further in-year requests for financial support.

Implications

  • Financial: The Transformation Reserve is to receive further funds from any 2025/26 underspend, once confirmed, to support in-year requests for financial support.

Who and where

  • The Council's capital programme
  • The Council's reserves, including the Transformation Reserve

Timeline

  • June/July Cabinet meeting: Confirmation of any 2025/26 budget underspend and transfer into the Transformation Reserve.

Plain English for the jargon

  • Transformation Reserve: A council reserve held to fund transformation work and in-year requests for financial support.
  • Capital programme: The Council's planned spending on capital projects such as buildings and infrastructure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Cabinet - Reviewed and approved the use of reserves and the change of use of a previously agreed reserve set out in the body of the report and the capital project to be included in the Council’s capital programme. Noted the Head of Finance recommendation that further funds were transferred into the Transformation Reserve from any 2025/26 budget underspending (when confirmed – June/July Cabinet meeting) to enable it to support any further in-year requests for financial support.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 18 May 2026

Subject Cabinet Approvals - Allocation of Reserves Purpose This report set’s out various requests for ‘use of reserves’ and ‘capital schemes’ which require Cabinet review and approval.

Author Head of Finance

Ward N/A

Summary Cabinet approve new ‘use of reserves’ requests not already covered in the Council’s base budget and inclusion of ‘capital projects’ in the Council’s capital programme within limits set by Council. There are a number of requests currently requiring approval and the next regular financial monitoring reports where these would ordinarily be dealt with is not until June. This separate report therefore lists these out for review and approval in order to provide earlier decisions and clarity for officers on funding / progression of capital schemes.

Proposal That:

- Cabinet review and approve the use of reserves and the change of use of a previously agreed reserve set out in the body of this report and the capital project to be included in the Council’s capital programme.

-Cabinet notes the HoF recommendation that further funds are transferred into the Transformation Reserve from any 2025/26 budget underspending (when confirmed – June/JULY Cabinet meeting) to enable it to support any further in-year requests for financial support.

Action by Service Manager – business partnering / Chief Accountant – update budgets in line with decisions.

Timetable Immediate

This report was prepared after consultation with:

▪ Statutory Officers ▪ Directors Background

Cabinet approve ‘use of reserves’’ and approve ‘capital projects’ into the Councils Capital programme in line with limits set by Council. These are ordinarily listed within and approved as part of the regular financial monitoring for the Cabinet. Due to the time of year around year-end, the next set of meetings are not until June, and a number of reserve requests and capital funding are currently required by officers. Therefore, currently, a separate report here lists these out and Cabinet are asked to review and approve these.

Use of Reserves

1. £250k from the Transformation Reserve. Funding to develop an accommodation strategy for office buildings, including the future use of the Civic Centre.

2. £474k from the Transformation Reserve.The work will focus on developing a clearer understanding of the key drivers of demand and cost within Adult Social Care, with particular emphasis on reablement and independence‑based approaches. The findings will inform whether changes to the current operating model could support more sustainable service delivery, reduce longer‑term reliance on commissioned domiciliary care, and contribute to managing forecast cost pressures in future years, while continuing to improve outcomes for residents.

3. £40k from the Transformation Reserve. Requested to commission specialist external support to undertake a review of the Council’s fees and charges. The work will provide independent challenge, benchmarking and robust methodologies to support a consistent and sustainable approach to cost recovery and income planning and will inform future budget setting and longer‑term financial sustainability.

4. £157k from the Transformation Reserve. Additional request linked to the £474k requested above in point 2. This is to support the commissioning of an external consultant and provide support for internal resources for a period of 2 years.

Transformation Fund – Summary Forecast £000 Balance b/f 31st March 2025 (5,308)

Previously Approved Programmes 3,994

Transfer from Prior Year Underspend (1,500) Revenue budget allocation (1,000)

Transformation Fund Balance (3,814)

New transformation fund requests 921

Transformation Balance available for future use (2,893)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet Approvals: Allocation of ReservesReport 143 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
DB
Councillor Dimitri BatrouniChair, present
DD
Councillor Deb DaviesCommittee Member, apologies
MS
Councillor Mark SpencerCommittee Member, present
ES
Councillor Emma Stowell-CortenCommittee Member, apologies
LL
Councillor Laura LaceyCommittee Member, present
JH
Councillor Jason HughesCommittee Member, present
JC
Councillor James ClarkeCommittee Member, present
YF
Councillor Yvonne ForseyCommittee Member, present
SA
Councillor Saeed AdanCommittee Member, present
RH
Councillor Rhian HowellsCommittee Member, expected, virtual

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open