RECOMMENDED TO CABINET: (1) That, with the exception of Recommendations 3, 4 and 9, the Recommendations contained in the Task and Finish Group Report on the Council’s Management of Larger Projects be supported; (2) That Recommendation 3 contained in the Task and Finish Group Report on the Council’s Management of Larger Projects be amended to read: “ The Council’s financial information should be comprehensive and presented in the form of a business plan so the extent of profits and losses can be easily understood.” (3) That Recommendation 4 contained in the Task and Finish Group Report on the Council’s Management of Larger Projects be amended to read: “When exception reports are produced by project boards, they should be circulated to all members of Council through the Members’ Information Service or by e mail and,unless they are confidential, made available to the public via the Council’s website.” (4) That Recommendation 9 contained in the Task and Finish Group Report on the Council’s Management of Larger Projects be amended to read: “The Council should ensure there is meaningful consultation with the public prior to it finalising its plans; and make sure it continues to engage with the public throughout the life of the project. “ REASON FOR DECISION: To enable the Overview and Scrutiny Committee to consider and comment on the Task and Finish Group report on the Council’s Management of Larger Projects prior to consideration by Cabinet.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
The report of the Task and Finish Group on the Council’s Management of Larger Projects is attached for the Committee’s consideration.
Recommendations
2.1The Committee is asked to: Consider the revised report of the Task and Finish Group and its recommendations at Appendix A; Consider the comments of the Senior Management Team at Appendix B; Agree the final wording of the recommendations; and refer the report to Cabinet for consideration at its meeting on 25 July 2017.
Reasons for recommendations
3.1To enable the Committee and Cabinet to consider the report of the Task and Finish Group.
Alternative options considered
4.1The Task and Finish Group discussed the evidence it heard and reached the conclusions set out in the report.
O&S (18.07.17) 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1There was no formal consultation about the report. Five members of the public took part in the Task and Finish Group and their contributions have been included as part of the evidence.
5.2Four members of the public made presentations on the report to the Committee’s meeting on 6 June 2017.
6. FORWARD PLAN
6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan.
Background
7.1The Committee established this Task and Finish Group to consider how the Council manages its larger projects. The Task and Finish Group is obliged to report back to the Committee before the report can be sent to Cabinet.
7.2The Committee considered a previous version of this report at its meeting on 6 June. Four members of the public made presentations to the Committee and the Committee had a number of comments of its own on the recommendations. These can be found in the minutes of the Committee’s meeting for 6 June which can found in your bundle of papers for this meeting.
7.3The Committee asked the Task and Finish Group to review its recommendations and report back to the Committee in July. The Task and Finish Group re-considered its report in the light of the comments made at the Committee and as a resulted changed some of its recommendations. The revised report of the Task and Finish Group is attached at Appendix A.
7.4The Committee also agreed to consider the comments of the Senior Management Team (SMT) alongside the report.
8. RELEVANT CONSIDERATIONS
8.1The conclusions and recommendations are in section 1 of the Task and Finish group Report. The Committee is asked to consider and comment on: the revised report of the Task and Finish Group which is attached at Appendix A; the comments of the Senior Management Team at Appendix B (NB – to follow).
8.2The Scrutiny Officer circulated some suggested changes to the recommendations based on the discussions at the Committee on 6 June 2017. Revisions to three recommendations - recommendations 2,5 and 10 - were agreed by all of the members of the Task and Finish Group. The Chairman Cllr Weeks did not agree with his colleagues that two other recommendations – recommendations 4 and 9 - should be changed.
O&S (18.07.17) Changes to Recommendations Agreed by the Task and Finish Group
8.3Recommendations 2, 5 and 10 have been changed to reflect the Committee’s discussion. The changes have been made to the report and are shown in bold underlined italics below for clarity and are: Minor drafting change (recommendation 2); The need for proper resourcing of projects has been beefed up (recommendation 5); Leaving open the possibility of using the competitive dialogue process in some circumstances (recommendation 10).
8.4Revised Recommendation 2: The Council should not introduce unnecessary complexity into its invitations to tender because it is unclear about its preferred outcome. It should decide what it wants and then invite bidders to tender for it.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.