North Hertfordshire District Council
Overview and Scrutiny Committee, Tuesday 19 September 2017 at 7.30pm

FIRST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2017/18

Noted Scrutiny 2 papers

Overview and Scrutiny Committee noted this item on Tuesday 19 September 2017. Below is the council's own wording, with the papers it was decided on.

Item44

Resolved

(1) That the report entitled First Quarter Monitoring Report on Key Projects for 2017/18 be noted: (2) That the project entitled Bancroft Gardens MUGA be removed from the 2017/18 monitoring reports but be included in the 2018/19 monitoring reports: REASON FOR DECISION: To enable the Overview and Scrutiny Committee to monitor delivery of key projects against targets. (1) That the report entitled First Quarter Monitoring Report on Key Projects for 2017/18 be noted: (2) That the project entitled Bancroft Gardens MUGA be removed from the 2017/18 monitoring reports but be included in the 2018/19 monitoring reports: REASON FOR DECISION: To enable the Overview and Scrutiny Committee to monitor delivery of key projects against targets.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Executive summary

This monitoring report provides a first quarter update on the delivery of the key projects for 17/18, first identified to the Committee in March 2017.

Recommendations

2.1That delivery against the key projects for 17/18 be noted and commented on by the Overview & Scrutiny Committee

Reasons for recommendations

3.1To enable achievements against the key projects for 2017/18 to be considered.

Alternative options considered

4.1There are not alternative options as this is a monitoring report.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1No external consultation has been undertaken in the preparation of this report as it is a monitoring report. Members will, however, be aware that a report setting out the key projects was brought to this Committee on 21 March 2017.

O&S (19.09.17) 6. FORWARD PLAN

6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan.

Background

7.1This report provides details on the status of the key projects for 17/18. It does not include any projects initiated after the document was agreed and is not a full report on all the projects that the Council is undertaking.

7.2This report summarises the status of each of the key projects. Overall, where the delivery has been solely down to the Council good progress has been made. The following symbols have been used to summarise progress.

Status key Project Halted / funding not available. Project behind original due date/ unlikely to hit original due date. Project not due for completion in 2017/18 or has not reached due date Project Completed.

8. RELEVANT CONSIDERATIONS

8.1At the Overview & Scrutiny committee meeting in July 2016, it was agreed that monitoring progress against key projects would take place on a more frequent basis and be reported quarterly.

8.2The 1st Quarter monitoring report against key projects for 2017/18 is included in Appendix A.

8.3Appendix A includes the original milestones for reporting progress which were reported to this Committee in March 2017 and progress made against those actions. In addition, updates may have been provided to Executive Members and where relevant through the Members Information Service. Progress against some, will also have been monitored through the Capital monitoring reports to the Finance Audit and Risk Committee and to Cabinet.

8.4At the Overview & Scrutiny committee meeting in June 2017 it was agreed that the report should include reference as to whether Projects were Prince II. Therefore Appendix A shows whether the project is classified as Prince II, and includes, the date of the last Project Board meeting and whether any exception reports have been produced since the last monitoring report.

O&S (19.09.17) 9. LEGAL IMPLICATIONS

9.1No direct legal implications arise from this report. Legal implications for the projects listed in Appendix A are considered as part of those projects and will include (but are not limited to ) governance, property, planning and contractual issues. Under the Local Government Act 2000 there is a legal requirement for Councils operating Executive arrangements to appoint an overview and scrutiny committee with remit to review decisions and other actions.

9.2Overview and Scrutiny’s terms of reference include at paragraph 6.2.7(s) of the Constitution “to review performance against the Council’s agreed priorities and scrutinise the performance of the Council in relation to its policy objectives, performance targets and/or service areas”. This report gives the Committee an opportunity to comment on progress made against the projects that have been identified for delivery against the Council’s objectives.

Financial implications

10.1There are no specific revenue implications.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Key Projects First Quarter First Quarter 2017/18Appendix A 487 KB Download
PDF
FIRST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2017/18Report 275 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. FIRST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2017/18This decision
  2. First quarter revenue budget monitoring 2026/27Noted
  3. First quarter capital budget monitoring review 2026/27Noted
  4. First quarter treasury management review 2026/27Noted
  5. First quarter revenue budget monitoring 2026/27Approved
  6. First quarter capital budget monitoring review 2026/27Approved

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies