(1) That the Internal Audit Progress Report for the period to 1 December 2017 be noted; (2) That the proposed amendments to the 2017/18 Annual Audit Plan be noted; and (3) That the implementation status of high priority recommendations be noted. REASON FOR DECISION: To allow the Committee to review, comment and challenge the current status of the Internal Audit Plan. (1) That the ... view the full minutes text for item 55.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Members are recommended to: Note the Internal Audit Progress Report for the period to 1 December 2017, Note the proposed amendments to the 2017/18 Annual Audit Plan, and Note the implementation status of high priority recommendations.
FAR COMMITTEE (18.12.17) Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.4 Medium Priority Recommendations 2.5 High Priority Recommendations 2.8 Proposed Amendments to the 2017/18 Annual Audit Plan 2.9 Performance Management
Appendices
A Progress against the 2017/18 Audit Plan
B Implementation Status of High Priority Recommendations
C 2017/18 Audit Plan Items – Start dates agreed with management
D Audit Recommendation Ratings
FAR COMMITTEE (18.12.17) Page 1 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2017/18 as at 1 December 2017. b) Implementation status of previously agreed high priority audit recommendations and request to agree removal of completed actions. c) Proposed amendments to the 2017/18 Annual Audit report d) An update on performance management information as at 1 December 2017.
Background
1.2The 2017/18 Annual Audit Plan was approved by the Finance, Audit and Risk Committee (the FAR Committee) on 22 March 2017.
1.3The Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the third report giving feedback on the delivery of the 2017/18 Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 1 December 2017, 56% of the 2017/18 Audit Plan days had been delivered.
2.2The following 2016/17 final report has been issued since 28 August 2017 (cut-off date for the SIAS Update Report for 21 September 2017 FAR Committee):
Audit Title Date of Assurance Number of Issue Level Recommendations N/A (5 suggested control Joint review - Nov 2017 N/A enhancements – 2 PREVENT with relevance to NHDC)
FAR COMMITTEE (18.12.17) Page 2 The following 2017/18 final reports have been issued since 28 August 2017 (cut-off date for the SIAS Update Report for 21 September 2017 FAR Committee):
Audit Title Date of Assurance Number of Issue Level Recommendations Office 2 medium Accommodation Sept 2017 Substantial 2 merits attention Project DFG Capital Sept 2017 N/A N/A Grant Certification Serious N/A (3 audit advisory Organised Crime Nov 2017 N/A actions) Checklist N/A (consultancy Income Nov 2017 N/A review with 7 Generation recommendations)
2.3Details on the status of all audits in this year’s plan can be found in Appendix A.
Medium Priority Recommendations
2.4The table below provides a summary of the medium priority recommendations made in the period:
Audit Summary of medium priority recommendations Office The tolerances within which the Project Manager Accommodation works are agreed and clarified. Project The Project Board meets at the specified frequency.
High Priority Recommendations
2.5Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of Officers to implement the recommendations by the agreed date.
2.6No high priority recommendations have been made as a consequence of the work undertaken in the audits detailed in paragraph 2.2 above.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.