[Prior to the consideration of this item and Minute 90 below, Councillors Bernard Lovewell, Ray Shakespeare-Smith and Michael Weeks declared that they would be withdrawing from the meeting, as they were Members of the Cabinet Sub-Committee (Council Charities), which was responsible for making decisions on the North Hertfordshire Museum and Community Facility on behalf of the Hitchin Town Hall: Gymnasium and Workmans Hall Trust. Accordingly, they withdrew from the meeting.] [Note: this item was considered after Minute 90.]
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
The purpose of this report is to further advise Cabinet of the progress of discussions for the acquisition of 14 and 15 Brand Street from Hitchin Town Hall Ltd (HTHL). Such an acquisition would allow the building to operate as intended by the Council in an integrated way for the local community following the withdrawal of funding to HTHL from the Social Investment Business (SIB).
Recommendations
2.1That Cabinet notes the current position in relation to the negotiations.
2.2That Cabinet requires officers to progress the alternative options as detailed in this report to enable the museum to open fully (whilst keeping open the possibility of a negotiated settlement).
2.3That Cabinet note that approval of some elements of any settlement agreement may be required from the Cabinet Sub-Committee (Council Charities).
Reasons for recommendations
3.1To enable the Council to complete the development of the North Hertfordshire Museum/Hitchin Town Hall project as intended by Council and operate the facility for the benefit of the local community.
3.2To protect the Council’s interests and obtain best return from the Council’s existing investment and to secure projected income from the facility to offset some of the operational and fixed costs.
Alternative options considered
4.1The options to open the facility without occupancy of 14/15 Brand Street has been fully investigated and a number of options are available to the Council. Whilst the preferred option is through the agreed acquisition of land formerly known as 14/15 Brand Street CABINET (23.1.18) this has not proved possible on terms agreeable to the Council despite over 15 months of negotiation. A costed options appraisal considering a number of scenarios for the occupation of the land which the Council currently owns has also been undertaken to guide the commercially confidential negotiations. The potential compulsory purchase of the properties known as 14/15 Brand Street is an option that has been investigated, and is being further explored via further specialist advice to enable the facility to operate as envisaged by the scheme which has the benefit of planning permission.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation on the general parameters for seeking to acquire 14/15 Brand Street as authorised by Full Council on 20 January 2016 has been on going with Executive Members prior to engaging in discussions with HTHL and HTH Finance Ltd.
6. FORWARD PLAN
6.1This report contains a recommendation on a key decision, which has been notified to the public in the Forward Plan on 22 December 2017.
Background
7.1The decision making history in relation to this project is extensive and has been reported to both Council and Cabinet on a number of occasions. The reports are available on the website (https://www.north-herts.gov.uk/home/museums/north- hertfordshire-museum-and-hitchin-town-hall/hitchin-town-hall-museum-proposals).
7.2As Cabinet will be aware, under the terms of the Development Agreement HTHL were to provide finance to the project in the sum of £550k (£490k for Hall and £60k for kitchen fit-out) and transfer the former 14/15 Brand Street to the Council Charity, in return for a lease over the main Mountford Hall. With the breakdown in the relationship between the parties, the Council has had to make additional funding available to replace the contribution of £550k which was not forthcoming, but the ownership of the former 14/15 Brand Street remains with HTHL.
7.3It should be noted that Council has approved in principle the acquisition of 14/ 15 Brand Street to allow the project to be completed in line with the original plans, subject to the financial limits as set out in the Council’s Constitution.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.