(1) That the contents of the report be noted; (2) That a report continue to be presented on an annual basis to each of the Area Committees; and (3) That, other than where a contribution has been negotiated for a specific purpose or project, Ward Members of the area where Section 106 or Unilateral Undertaking funding is generated and the Area Committee be consulted prior to funding being allocated away from that area or from a village location to a town. REASON FOR DECISION: To ensure that there is a robust system for negotiating and managing Section 106 and Unilateral Undertakings. (1) That the contents of the report be noted; (2) That a report continue to be presented on an annual basis to each of the Area Committees; and (3) That, other than where a contribution has been negotiated for a specific purpose or project, Ward Members of the area where Section 106 or Unilateral Undertaking funding is generated and the Area Committee be consulted prior to funding being allocated away from that area or from a village location to a town. REASON FOR DECISION: To ensure that there is a robust system for negotiating and managing Section 106 and Unilateral Undertakings.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1This report and appendix provides Members of the Area Committees with the annual update on the details of the current Section 106 agreements and Unilateral Undertakings within the wards/parishes in the area as at the 20th February 2018. It also provides an update on the relevant legislation.
1.2As with previous years, this does not include the Hertfordshire County Council contributions over which this Council does not have any control.
1.3The appendix shows the contributions received and where monies have been committed to specific projects i.e. the Council’s capital projects and the associated timescales where possible. Comments have also been included, where appropriate, as to the justification for the receipt of certain contributions.
1.4Where Section 106 obligations are negotiated for a site, contributions tend to be for a specific purpose whereas the unilateral undertakings entered into and agreed use the formula set out in the Supplementary Planning Document: - Planning Obligations adopted in November 2006.
Recommendations
2.1That the contents of the report be noted.
2.2That a report shall continue to be presented on an annual basis to each of the Area Committees.
2.3That, other than where a contribution has been negotiated for a specific purpose or project, Ward Members of the area where Section 106 or Unilateral Undertaking funding is generated and the Area Committee be consulted prior to funding being allocated away from that area or from a village location to a town. 3. REASONS FOR RECOMMENDATIONS
3.1To ensure that there is a robust system for negotiating and managing Section 106 and Unilateral Undertakings.
3.2To ensure that this is kept under constant review and that the risk associated with this activity is managed in an appropriate manner.
Alternative options considered
4.1It is not considered that an alternative viable option is available for the Council to manage and maintain records of Section 106 and Unilateral Undertakings.
5. CONSULTATION WITH EXTERNAL ORGANISATIONS AND WARD MEMBERS
5.1This report is being presented to each Area Committee so that all Ward Members are fully aware of the progress and updated in relation to this matter. No external organisations have been consulted.
6. FORWARD PLAN
6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan.
Background
7.1The Council introduced a Planning Obligations supplementary planning document (SPD) in 2006 giving a formula for developers to calculate as to what their section 106 costs might be. Its introduction has led to the majority of sites within the District since 2006 contributing towards the cost of infrastructure. Unilateral undertakings are a particular type of obligation under section 106 that are only signed by the developer, instead of bilaterally by both the Council, and the developer.
7.2The main objective of the SPD was to ensure that the additional demands upon infrastructure, services and facilities from new development are provided for and are put in place at the right time and contribute to the Council’s priorities and capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Baldock and District Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
Election of a chair and vice chair(1) That the Committee elected Councillor Steve Jarvis as Chair of the Baldock and District Committee for the remaind...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.