(1) That the Overview and Scrutiny Committee Work Programme be noted; (2) That the following be added to the list of potential Task and Finish Groups/Reviews: · Communication in a crisis; · Implementation of the new waste and recycling contract (3) That Councillors Kate Aspinwall, Steve Deakin-Davies, Elizabeth Dennis-Harburg, Jean Green and Janine Paterson be requested to meet at 6.30pm on 24 July 2018 in order to draw up a draft scope for a review of the Implementation of the new waste and recycling contract; (4) That, in addition to the list of proposed items for consideration at the meeting due to be held on 24 July 2018, the following also be considered: · Whether Items due to be considered by Council could be considered by this Committee; · Draft scope for a review of the implementation of the new waste and recycling contract. (5) That the following be added to the list of Items to be scheduled for future meetings: · Local Plan Modifications REASON FOR DECISION : To enable the Overview and Scrutiny Committee to plan and carry out its workload efficiently and effectively. (1) That the Overview and Scrutiny Committee Work Programme be noted; (2) That the following be added to the list of potential Task and Finish Groups/Reviews: · Communication ... view the full minutes text for item 15.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
1.1This report highlights items scheduled in the Overview and Scrutiny Committee’s work programme for 2018/19 and includes details of those that have yet to be assigned to a specific meeting.
1.2The work programme includes both items previously agreed by the Committee and those that the Committee is required by the Constitution to consider.
Recommendations
2.1That the Committee notes and comments where appropriate on the items scheduled for inclusion in the work programme.
2.2That the Committee agrees the list of items to be considered at its meeting of 24 July 2018.
Reasons for recommendations
3.1To allow the Committee to set a work programme which provides meaningful Member oversight, encourages open debate and seeks to achieve service improvement through effective policy development and meaningful policy and service change.
Alternative options considered
4.1Over recent years, the Committee has varied its approach to overview and scrutiny activity. Most recently, it has been entering the process of policy development at an earlier stage and consequently on occasion may consider items associated with service action plans.
4.2The need to ensure constitutional requirements are observed remains a key aspect of work programming as does the monitoring of the Forward Plan for appropriate items to scrutinise. 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Each Committee meeting includes the opportunity for Members to comment on and input to the Committee’s work programme.
5.2Work is currently being undertaken to establish the types of training provided by the Centre for Public Scrutiny in order to develop a training proposal that addresses amongst others: the identification and prioritisation of issues and topics for scrutiny review (minute 16, June 2017) the maximisation of the benefits of scrutiny (minute 31, July 2017) effective methods of overview and scrutiny (minute 32, July 2017)
6. FORWARD PLAN
6.1This report does not contain a recommendation on a key decision and has not been referred to in the Forward Plan.
6.2The Committee is asked to review the Forward Plan at each regular meeting and identify potential issues for inclusion in the work programme. Identification of a focus for the Committee’s future activity should be identified at this stage if appropriate.
Background
7.1Regular presentations on a rotational basis are no longer delivered by Executive Members. It was determined that more benefit could be derived from Executive Members being invited to either speak on a specific issues of interest to the Committee or present a report being considered for constitutional reasons.
7.2The Committee is now considering a wider range of topics as potential agenda items and if appropriate, seeking to commence its reviews earlier in the policy development process. By doing this it seeks to ensure assumptions are challenged at an early stage, mistakes are avoided and eventual outcomes provide optimal benefit to the community.
7.3The Committee will continue to use the Forward Plan and meet its statutory obligations when setting the work programme. This approach may be adapted in the light of outcomes from the proposed training event.
7.4The Committee seeks to ensure that consideration of agenda items minimises additional burdens on staff resources. Wherever possible, requests made should be for the presentation of documents already in existence rather than the production of new documents specifically for the Committee.
8. RELEVANT CONSIDERATIONS
Work Programme
8.1A work programme is set out at Appendix B for the Committee’s consideration.
Forward Plan
8.2The Forward Plan for 25 April 2018 is attached at Appendix C Other Topics
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.