Audio Recording – Start of item - 1 hour 30 minutes 41 seconds The Committee received an Information Note entitled Churchgate Update.
Hitchin Committee decided this item on Tuesday 11 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Audio Recording – Start of item - 1 hour 30 minutes 41 seconds The Committee received an Information Note entitled Churchgate Update.
1.1This information note is provided in order to update the Committee on the proposals for the regeneration of the Churchgate Shopping Centre which were considered by Full Council on 8 February 2018.
2. STEPS TO DATE
2.1Full Council received a report on a proposal for the regeneration of the Churchgate Shopping Centre and adjacent Hitchin Market and public realm, whereby the Council would work in partnership with Shearer Property Group. That report set out the initial indicative proposals for the area, with the Council acting as funder for the regeneration. Full Council agreed to support the principle of joint venture regeneration with the Council as funder and authorised that negotiations progress on the terms of a potential joint venture, subject to Full Council’s final approval.
2.2Cabinet on 27 March 2018 received a report on the Future Management of Hitchin Market, given the expiry of the contract with Hitchin Markets Limited (HML) on 31 July 2018 and in light of the proposals for the regeneration. One of the options considered, as indicated in the Full Council report, was whether to bring back in-house the management of the market. Cabinet decided to defer a decision on the future management of the market until there was greater clarity on the deliverability of the proposals for the Churchgate Centre and Hitchin Market. Authorisation was given to enter into negotiations with HML to extend the existing management contract. 2.3 In March and April 2018 the Council carried out a survey seeking the views of people who live and/or work in North Hertfordshire on the broad principles of the proposals considered by Full Council, in order to inform our thinking going forward. The survey was carried out online, although paper copies were also made available on request. Additionally some members of the community took the opportunity to put forward their views generally, rather than answer the survey.
3. INFORMATION TO NOTE
3.1Over the last few months negotiations have been progressing with Shearer Property Group (SPG) on the terms of a deal between SPG and the Council. These negotiations have been informed by legal and financial advice, in order to ensure the structure of the relationship gives the proposals the best possible chance of succeeding whilst complying with the various statutory obligations on the Council. Negotiations are ongoing on the proposed Heads of Terms, which would be reported to Full Council for approval prior to any work being undertaken on the detailed legal agreements which would be required for a project of this nature. Full Council would then be reported to, to make a final decision once those legal agreements had been negotiated.
3.2Agreement has been reached with HML on the terms of an extension to their management contract and that new contract commenced on 1 August 2018. As with previous management contracts with HML there are clauses protecting the Council’s position in the event that the regeneration proposals are able to proceed.
3.3In July the Council published the results of the overwhelmingly positive response to the questionnaire. The results have been published in full on the Council’s website, accompanied by an Executive Summary of the key findings. Members received copies of the summary and results in Members Information Service. The survey generated responses from 578 people, with some 86% of respondents supporting the idea of regenerating the existing Churchgate Centre to provide improved shop units. An overwhelming majority (93%) of respondents also supported the principle of investing in Hitchin’s market to ensure it is fit for the 21st Century.
3.4Key Findings:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INFORMATION NOTE: CHURCHGATE UPDATEReport | 211 KB | DownloadRead as text |
Follow Hitchin Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Mar 2023 | Apologies for absenceApologies for absence were received from Councillor Raj Bhakar. | Decided | Open |
| 28 Mar 2023 | Minutes - 8 december 2022That the Minutes of the Meeting of the Committee held on 8 December 2022 be approved as a true record of the proceedi... | Approved | Open |
| 28 Mar 2023 | Notification of other businessThere was no other business notified. | Decided | Open |
| 28 Mar 2023 | Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be audio recorded. | Decided | Open |
| 28 Mar 2023 | Hitchin bid - updateA verbal presentation was received from Tom Hardy of Hitchin BID. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.