CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Cabinet, Tuesday 17 December 2019 at 7.30pm

INVESTMENT STRATEGY (CAPITAL AND TREASURY) MID-YEAR REVIEW 2019/20

Noted Executive 3 papers

Cabinet noted this item on Tuesday 17 December 2019. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

(1) That the forecast expenditure of £5.886million in 2019/20 on the capital programme, paragraph 8.2 refers, be noted; (2) That the adjustments to the capital programme for 2019/20 onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2020/21 and beyond by £1.369million be approved; (3) That the position of the availability of capital resources, as detailed in table 3 paragraph 8.6 and the requirement to keep the capital programme under review for affordability be noted; RECOMMENDED TO COUNCIL: That the position of Treasury Management activity as at the end of September 2019 be noted. REASONS FOR DECISIONS: (1) Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded; (2) To ensure the Council’s continued compliance with CIPFA’s code of practice on Treasury Management and the Local Government Act 2003 and that the Council manages its exposure to interest and capital risk. (1) That the forecast expenditure of £5.886million in 2019/20 on the capital programme, paragraph 8.2 refers, be noted; (2) That the adjustments to the capital programme for 2019/20 onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2020/21 and beyond by £1.369million be approved; (3) That the position of the availability of capital resources, as detailed in table 3 paragraph 8.6 and the requirement to keep the capital programme under review for affordability be noted. RECOMMENDED TO COUNCIL: That the position of Treasury Management activity as at the end of September 2019 be noted. REASONS FOR DECISIONS: (1) Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded; (2) To ensure the Council’s continued compliance with CIPFA’s code of practice on Treasury Management and the Local Government Act 2003 and that the Council manages its exposure to interest and capital risk.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 11 pages

Executive summary

1.1To update Cabinet on progress with delivering the capital and treasury strategy for 2019/20, as at the end of September 2019.

1.2To update Cabinet on the impact upon the approved capital programme for 2020/21 – 2023/24. The current estimate is a decrease in spend in 2019/20 of £1.936million and an increase in spend in future years of £1.369million. The most significant individual change relates to the withdrawal of the Hitchin Swim Centre Car Park scheme.

1.3To inform Cabinet of the Treasury Management activities in the first six months of 2019/20. The current forecast is that the amount of investment interest expected to be generated during the year is £0.372million. This remains unchanged from the value reported at the first quarter.

Recommendations

2.1That Cabinet notes the forecast expenditure of £5.886million in 2019/20 on the capital programme, paragraph 8.2 refers.

2.2That Cabinet approves the adjustments to the capital programme for 2019/20 onwards as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in 2020/21 and beyond by £1.369million.

2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 3 paragraph 8.6 and the requirement to keep the capital programme under review for affordability.

2.4Cabinet is asked to note the position of Treasury Management activity as at the end of September 2019. 3. REASONS FOR RECOMMENDATIONS

3.1Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.

3.2To ensure the Council’s continued compliance with CIPFA’s code of practice on Treasury Management and the Local Government Act 2003 and that the Council manages its exposure to interest and capital risk.

Alternative options considered

4.1Options for capital investment are considered as part of the Corporate Business Planning process.

4.2The primary principles governing the Council’s investment criteria are the security of its investments (ensuring that it gets the capital invested back) and liquidity of investments (being able to get the funds back when needed). After this the return (or yield) is then considered, which provides an income source for the Council. In relation to this the Council could take a different view on its appetite for risk, which would be reflected in the Investment Strategy. In general, greater returns can be achieved by taking on greater risk. Once the Strategy has been set for the year, there is limited scope for alternative options as Officers will seek the best return that is in accordance with the Investment Strategy.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.

5.2There are quarterly updates with the Authority’s Cash Manager, Tradition and regular meetings with Treasury advisors (Link).

6. FORWARD PLAN

6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan on the 6th September 2019.

Background

7.1In February 2019, Council approved the Integrated Capital and Treasury Strategy for 2019/20 to 2022/23. This was a change from having a separate Capital Programme and Treasury Strategy. The change was in response to guidance from the Ministry for Housing, Communities and Local Government (MHCLG) and the Chartered Institute of Public Finance and Accountancy (CIPFA). To be consistent with the strategy (and the guidance), the monitoring reports for Capital and Treasury are also integrated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Detail including Funding 2018/19 onwardsAppendix A 1 pages Download
PDF
Treasury Management UpdateAppendix B 16 pages Download
PDF
INVESTMENT STRATEGY (CAPITAL AND TREASURY) MID-YEAR REVIEW 2019/20Report 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. INVESTMENT STRATEGY (CAPITAL AND TREASURY) MID-YEAR REVIEW 2019/20This decision
  2. Investment strategy 2026/27Approved
  3. Investment strategy 2026/27Approved
  4. Investment strategy 2026/27Approved
  5. Investment strategy (capital and treasury) end of year review 2024/25Approved
  6. Investment strategy (capital and treasury) end of year review 2024/25Noted

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies