North Hertfordshire District Council
Overview and Scrutiny Committee, Monday 13 June 2022 at 7.30pm

END OF YEAR MONITORING REPORT ON KEY PROJECTS FOR 2021 - 22

Noted Scrutiny 2 papers

Overview and Scrutiny Committee noted this item on Monday 13 June 2022. Below is the council's own wording, with the papers it was decided on.

Item106

Resolved

That delivery against the key projects for 2021-2022 was noted and commented on by the Overview & Scrutiny Committee and that those marked as completed can be removed from future reports. REASON FOR DECISION: To enable achievements against the key projects for 2021/22 to be considered. That delivery against the key projects for 2021-2022 was noted and commented on by the Overview & Scrutiny Committee and that those marked as completed can be removed from future reports. REASON FOR DECISION: To enable achievements against the key projects for 2021/22 to be considered.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 5 pages

Executive summary

This monitoring report provides a year end update on the delivery of the key projects for 21/22, first identified to the Committee in March 2021.

Recommendations

2.1That delivery against the key projects for 21/22 be noted and commented on by the Overview & Scrutiny Committee.

Reasons for recommendations

3.1To enable achievements against the key projects for 2021/22 to be considered.

Alternative options considered

4.1There are no alternative options as this is a monitoring report.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1No external consultation has been undertaken in the preparation of this report as it is a monitoring report. Members will, however, be aware that a report setting out the key projects was brought to this Committee on 16 March 2021.

6. FORWARD PLAN 6.1 This report does not contain a recommendation on a key Executive decision and has therefore not been referred to in the Forward Plan.

7. BACKGROUND 7.1. This report provides details on the status of the key projects for 21/22. It does not include any projects initiated after the document was agreed and is not a full report on all the projects that the Council is undertaking

7.2This report summarises the status of each of the key projects. The following symbols have been used to summarise progress.

Status key Project Halted / funding not available/ Extremely Late Project behind original due date/ unlikely to hit original due date. Project not due for completion in this year or has not reached due date Project Completed. .

8. RELEVANT CONSIDERATIONS

8.1The end of year monitoring report against key projects for 2021/22 is included in Appendix A.

8.2Appendix A includes the original milestones which were reported to this Committee in March 2021 and progress made against those actions. In addition, updates may have been provided to Executive Members and where relevant through the Members Information Service. Progress against some, will also have been monitored through the Capital monitoring reports to the Finance Audit and Risk Committee and to Cabinet.

8.3For Q4, 11 projects are being reported, 7 with Amber status, 1 with Green status and 3 projects marked as complete. The number of projects with an Amber status reflects that this is the end of year report and a number of the milestones were set as 31st March. Therefore a number of projects have either completed, or are shown as Amber (i.e. the milestone set for 31st March was not achieved).

8.4The following projects were completed during Q4:  Community lottery- as the lottery has been fully launched.  Property acquisitions- this has been embedded in to the normal work of the team, and opportunities will continue to be identified and investigated.  Community Tree programme- all the trees have been distributed.

8.5The following projects have moved to Amber status during Q4 (from Green).  Provide housing at market rents- the conversion work at Harkness Court is being finalised and it is expected that marketing and lettings will commence in August.  Trial / Experimental EV Charging Points- Finalising work to appoint a private sector partner through a mini-competition and then submit grant submissions. Expected that the grant submissions will be made in the summer.  Disposal of surplus land. Two land sales have been completed. Two of the sales have been delayed but expecting that they will complete in 2022/23.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4th Quarter Monitoring against Key Projects for 2021/2022Appendix A 9 pages Download
PDF
END OF YEAR MONITORING REPORT ON KEY PROJECTS FOR 2021: 22Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. END OF YEAR MONITORING REPORT ON KEY PROJECTS FOR 2021 - 22This decision
  2. Performance monitoring for 2021/22 - year endNoted
  3. Performance monitoring for 2020/21 - year endNoted
  4. Mid year amendments to performance monitoring targets for 20/21Approved
  5. Year end performance indicators monitoring report 2016/17Noted

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies