That planning permission be GRANTED subject to the completion of a satisfactory S106 Legal Agreement and the reasons and conditions set out in the report, subject to the following amendment to condition 9 to read: “The development hereby approved shall be carried out in accordance with the recommendations and mitigation measures set out in the submitted Bat Survey Report by Three Counties Ecology, the Preliminary Ecological Assessment and Potential Roost Assessment (August 2021).’”
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Location: Land On The South West Side Of Barkway Road Royston Hertfordshire
Applicant: Hanson
Proposal: Erection of ten dwellings (2 x 2-bed, 2 x 3-bed, 4 x 4-bed and 2 x 5-bed) with ancillary works including alterations to existing vehicular access, new access road, parking and landscaping.
Ref. No: 21/02957/FP
Officer: Tom Rea
Date of expiry of statutory period: 14th February 2022
Extension of statutory period: 30th September 2022
Reason for delay:
Ongoing negotiations, amendments to the proposals and finalising of a Section 106 Agreement
Reason for referral to Committee
The site area for this application for development exceeds 0.5 ha and therefore under the Council’s scheme of delegation, this application must be determined by the Council’s Planning Control Committee
1.0Site History
None although of note is the site frontage which was developed and has been completed following the grant of planning permission in 2016 (ref: 16/01151/1) . The permission was for one 5 x bedroom detached dwelling with detached single garage, two 4 x bedroom detached dwellings with detached single garages. Alterations to existing access and new access off Barkway Road. (As amended by plans received 26.5.16, 23.6.16, 25.7.16 and 6.9.16).
2.0Policies
2.1North Hertfordshire District Local Plan (Saved Policies)
Policy 6: Rural Area beyond the Green Belt Policy 9: Royston’s Development Limits Policy 14: Nature Conservation Policy 16: Archaeological Areas of Significance and other Archaeological Areas Policy 26: Housing Proposals Policy 51: Development effects and planning gain Policy 55: Car Parking Standards Policy 57: Residential Guidelines and Standards
2.2National Planning Policy Framework (2021)
Section 2: Achieving sustainable development Section 5: Delivering a sufficient supply of homes Section 6: Building a strong competitive economy Section 8: Promoting healthy and safe communities Section 9: Promoting sustainable transport Section 11: Making effective use of land Section 12: Achieving well-designed places Section 14: Meeting the needs of climate change Section 15: Conserving and enhancing the natural environment
2.3North Hertfordshire District Local Plan 201 – 2031 (Emerging Local Plan)
Site RY11 – Land at Barkway Road Policy SP1: Presumption in favour of sustainable development Policy SP2: Settlement Hierarchy Policy SP6: Sustainable Transport Policy SP7: Infrastructure requirements and developer contributions Policy SP8: Housing Policy SP9: Design and Sustainability Policy SP10: Healthy Communities Policy SP11: Natural Resources and Sustainability Policy SP12: Green infrastructure, biodiversity and landscape Policy D1: Sustainable Design Policy D3: Protecting living conditions Policy D4: Air Quality Policy HS3: Housing mix Policy NE1: Landscape Policy NE8: Sustainable Drainage Systems Policy NE12: Renewable and low carbon energy development Policy T2: Parking
2.4Supplementary Planning Guidance
Design SPD Planning Obligations SPD Vehicle Parking Provision at New Development North Hertfordshire and Stevenage Landscape Character Assessment
2.5Hertfordshire County Council
Local Transport Plan (May 2018) Guide to developer infrastructure contributions (July 2021)
3.0Representations 3.1 Statutory consultees:
Royston Town Council: Raises an objection on the following grounds: o The development is overbearing on existing houses and is too close to the boundary of Shepherd Close. o There will be shadowing and loss of light to existing properties. o Mature trees on the site will be removed. o There is a risk of flooding due to the gradient of the site. o Access is onto Barkway Road which is already severely congested and which becomes a single lane road due to parking provision.
Wildlife Trust: Comments: Objection: Ecological report not submitted, biodiversity net gain not assessed, bat surveys not completed, no buffers to adjoining woodland and hedge in conflict with the emerging local plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.