21/03380/FP Land To The North And East Of Great Wymondley, Hertfordshire

Approved Planning 4 papers

Planning Control Committee approved this item on Thursday 17 November 2022. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

That the application 21/03380/FP be GRANTED planning permission subject to the reasons set out in the report of the Development and Conservation Manager and the removal of Condition 7, to be replaced with two further conditions. Therefore the current Condition 9 would become Condition 10, with the other Conditions included within the report changing number accordingly. The additional conditions were: “Condition 7: No development including ground works and ground preparation works shall take place until a surface water drainage scheme, based on suitable drainage principles and an assessment of the hydrological and hydrogeological context of the development, has been submitted to and approved in writing by the Local Planning Authority. The drainage strategy should demonstrate the surface water run-off generated up to and including 1 in 100-year + climate change critical storm will not exceed run-off from the undeveloped site following the corresponding rainfall event. The scheme shall subsequently be implemented in accordance with the approved details before the development is completed. The scheme shall also include: A detailed response to the Letter from the LLFA dated 15 November 2022 which addresses the points of concern with the proposed surface water drainage scheme and overland flow management scheme. Carry out any necessary amendments to the proposed surface water drainage scheme and hydraulic modelling for the overland management scheme for LLFA approval. Once the baseline information is agreed the following information should be provided; Demonstrate an overall betterment of the existing pre-development overland flow paths for the 1 in 30-year event, ensuring the flow paths are maintained and not made worse for events above the 1 in 30-year event and up to the 1 in 100 year + climate change event. Detailed engineered drawings of the proposed SuDS /flood risk mitigation features including their location, size, volume depth and any inlet and outlet features including any connecting pipe runs and all corresponding calculations/modelling to ensure the scheme caters for all rainfall events up to and including the 1 in 100 year + 40% allowance for climate change event. Detailed engineered drawings of all proposed discharge locations including headwall details, evidence of land ownership and relevant permissions. A condition survey of these specific locations should also be provided and any mitigation required should be carried out prior to development taking place. Demonstrate appropriate SuDS management and treatment and inclusion of above ground features. Provision of half drain down times for surface water drainage features within 24 hours. Silt traps for protection of any residual tanked elements where appropriate. Construction phase surface water and flood mitigation management plan. Details of how the scheme shall be maintained and managed after completion including adoption of details. Reason: To prevent the increased risk of flooding, both n and off site in particularly to Priory Lane and Little Wymondley . Condition 8: Upon completion of the surface water drainage/flood management works for the site in accordance with the timing/phasing arrangements, the following shall be submitted to and approved in writing by the Local Planning Authority: ...
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Planning Control Committee, 63 pages

Location: Land To The North And East Of Great Wymondley Hertfordshire

Applicant: [name removed]: Proposed solar farm measuring 88 hectares with associated battery storage containers, transformers stations, storage buildings, fencing etc including means of access (amended plans received 30.05.2022).

Ref. No: 21/03380/FP

Officer: Shaun Greaves

Date of expiry of statutory period 15 March 2022

Extension of statutory period 16 December 2022

Reason for Delay:

Ongoing negotiations, further information received, and additional consultation exercise that was undertaken as a result.

Reason for referral to Committee

The site area for this application for development exceeds 1 ha and therefore under the Council’s scheme of delegation, this application must be determined by the Council’s Planning Control Committee.

Members should be aware that if they are minded to approve the application, this would be a ‘resolution for grant’ subject to referral of the application to the Secretary of State, as the site is within the Green Belt and over an identified threshold set out in The Town and Country Planning (Consultation) (England) Direction 2021 for consulting the Secretary of State in the event the local planning authority has resolved to grant planning permission for certain types of development.

The purpose of the Direction is to give the Secretary of State an opportunity to consider using the power to call in applications under Section 77 of the Town and Country Planning Act 1990. To use the call-in power requires that the decision be taken by the Secretary of State rather than the local planning authority. Paragraph 3 of the 2021 Direction states:

This Direction shall apply in relation to any application for planning permission which – (a) is for Green Belt development, development outside Town Centres, World Heritage Site development or flood risk development; and (b) is received by a planning authority on or after 21 April 2021.

Paragraph 4 of the 2021 Direction states:

For the purposes of this Direction, “Green Belt development” means development which consists of or includes inappropriate development on land allocated as Green Belt in an adopted local plan, unitary development plan or development plan documents and which consists of or includes –

(a) The provision of a building or buildings where the floor space to be created by the development is 1000 square metres or more; or (b) (b) any other development which, by reason of its scale or nature or location, would have a significant impact on the openness of the Green Belt. The proposal is for a Solar Farm of a large scale covering 85 hectares of fields and where there would be more than 1000 square metres of buildings in the form of inverter/transformer stations and battery storage containers. Therefore, the proposal falls within both (a) and (b) above.

1.0Site History

1.121/01269/PRE – Pre-application submission/advice on a proposed solar farm with associated battery storage containers, transformer stations, storage buildings, fencing etc. including means of access.

1.221/02228/SO – Screening Opinion – Proposed solar farm with associated battery storage containers, transformer stations, storage buildings, fencing etc including means of access

2.0Policies

2.1North Hertfordshire District Local Plan No. 2 Alterations (Saved Policies) Policy 2: Green Belt

Policy 11: Chilterns Area of Outstanding Natural Beauty

Policy 14: Nature Conservation

Policy 16: areas of archaeological significance and other archaeological areas 2.2 Wymondley Neighbourhood Development Plan (2011-2031) (Made 2018) The Wymondley Neighbourhood Plan (WNP) was made on 26th September 2019 and now forms part of the Development Plan.

Policy NHE1: Landscape character

Policy NHE2: Biodiversity

Policy NHE3: Wildlife ad Ecology

Policy NHE8: Landscaping schemes

Policy NHE9: Historic character and heritage assets

Policy GB1: Green Belt

Policy FR1: Flood risk

Policy SLBE1: Business development

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21/03380/FP Land To The North And East Of Great Wymondley, HertfordshireReport 63 pages DownloadRead as text
PDF
2103380FP: LLFA 15.11.2022Report 7 pages Download
PDF
PlanReport 1 pages Download
PDF
Planning Control Committee Meeting on 17 November 2022Report 3 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 21/03380/FP Land To The North And East Of Great Wymondley, HertfordshireThis decision
  2. 26/00006/fp land to north of, stevenage road, hitchin, hertfordshireRefused
  3. 24/02656/s73 land east of garden walk and north of newmarket road, garden walk, royston, hertfordshireAgreed
  4. 25/00571/FP Land North Of, Milksey Lane, Graveley, HertfordshireAgreed
  5. 21/00765/op land off barkway road and north of flint hall, barkway road, royston, hertfordshireRefused
  6. 24/02780/rm land north of highover farm to stotfold road, highover way, hitchin, hertfordshireDecided

More from North Hertfordshire Planning Control Committee

All decisions
MeetingDecisionOutcome
1 Oct 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
1 Oct 2026 Minutes - 3 september 2026That the Minutes of the meeting of the Committee held on 3 September 2026 be approved as a true record of the proceed... Approved Open
1 Oct 2026 Notification of other businessThere was no notification of other business. Decided Open
1 Oct 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
1 Oct 2026 Public participationThe Chair confirmed that the registered speakers were in attendance. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies