Finance, Audit and Risk Committee approved this item on Wednesday 7 December 2022. Below is the council's own wording, with the papers it was decided on.
RECOMMENDED TO COUNCIL: That Council considers the proposed changes and recommends their adoption to Full Council. REASON FOR DECISION: The Contract Procurement Rules (CPR’s) are part of the Constitution (under Section 20) and must be regularly reviewed and updated as part of the Council’s governance and procurement review processes, contributing to the Council’s system of effective internal control.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Report to Finance, Audit and Risk Committee, 6 pages
Executive summary
1.1This report sets out the proposed changes to the Contract Procurement Rules for review and referral that, in summary, seeks to make the following changes: Updates to reflect the Procurement Function moving from Legal to the Resources Directorate Update to section 3 to add guidance relating to the treatment of below threshold Concession Contracts. Clarifying Officer responsibilities with regard to posting award notices and retaining signed contracts on the E-Sourcing system Adding guidance on TUPE requirements.
Recommendations
2.1That Committee considers the proposed changes and recommends their adoption to Full Council.
Reasons for recommendations
3.1The Contract Procurement Rules (CPR’s) are part of the Constitution (under Section 20) and must be regularly reviewed and u p d a t e d as part o f t h e C o u n c i l ’ s g o v e r n a n c e a n d procurement review processes, contributing to the Council’s system of effective internal control.
Alternative options considered
4.1Not updating the CPRs would increase the risk of non-compliant Procurement at the Council which could lead to procurement challenges and increased costs.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1This report and appendices are being presented to FAR Committee for consideration, prior to recommendation to Council. The proposed changes have been approved by the Council’s Contract and Procurement Group, chaired by the Service Director, Resources, and attended by the Executive Member for Finance and IT, who has responsibility for Procurement. 1 6. FORWARD PLAN
6.1This report does not contain a recommendation on a key Executive decision and has therefore not been included in the Forward Plan.
Background
7.1The CPRs are reviewed on a periodic basis to ensure they remain relevant and appropriate for the Council’s needs. This review has been undertaken by the Contract and Procurement Group, led by the Service Director, Resources and the Controls, Risk and Performance Manager.
7.2This is a light touch review to update on changes to the management of the Procurement function and other guidance for Officers to ensure that procurement requirements are met.
7.3Next year, if the new Procurement Bill is published (which will have implications for these Rules and the Procurement Strategy) there may be a requirement for greater changes, as we will need to update our internal guidance to match the new Regulations in force. If the Bill is passed into law, we will have a six-month period in which to implement the changes.
8. RELEVANT CONSIDERATIONS
8.1The changes to the Contract Procurement Rules are provided at Appendix A, detailing the proposed tracked changes. A summary of these proposed key changes is outlined below.
8.2Management of the Procurement Function Procurement previously sat under the Legal and Community Directorate from 2019 to 2022. In July 2022, the management of the procurement function transferred back to the Resources Directorate. A full-time procurement officer was appointed at the same time. Any reference to guidance on the procurement process, the procurement documents and interpretation of the rules has been updated to show that these functions now sit under Procurement.
8.3Concession Contracts below Regulated Threshold
Section 3.10 of the rules currently states that the rules do not apply to Concession Contracts. It sets out the regulations to be followed for Concession Contracts above the regulated amount (currently £5,336,937.00), however, it does not mention what rules should be followed for Concession Contracts below this value as legislation is silent on below threshold Concession Contracts. This change seeks to address the gap in guidance for Officers.
8.4Posting Award Notices
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.