RECOMMENDED TO CABINET: (1) That Cabinet notes expenditure of £6.923million in 2022/23 on the capital programme, paragraph 8.3 refers. (2) That Cabinet approves the adjustments to the capital programme for 2023/24 as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in by £1.222million. (3) That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.7 and the requirement to keep the capital programme under review for affordability. Page 75 Agenda Item 9 (4) That Cabinet approves the application of £6.300million of capital receipts/set aside towards the 2022/23 capital programme, paragraph 8.7 refers. (5) Cabinet is asked to note the position of Treasury Management activity as at the end of March 2023. (6) Cabinet is asked to recommend this report to Council and ask Council to: 1) Approve the actual 2022/23 prudential and treasury indicators. 2) Note the annual Treasury Report for 2022/23. REASONS FOR REFERRALS : (1) Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded. (2) To ensure the Council’s continued compliance with CIPFA’s code of practice on Treasury Management and the Local Government Act 2003 and that the Council manages its exposure to interest and capital risk.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Report to Finance, Audit and Risk Committee, 13 pages
Executive summary
1.1As at the end of financial year 2022/23, there is a reduction in Capital spend compared to quarter 3 of £1.447million. The majority of this change is due to revisions to the profile of planned project spend, with £1.222million that will now instead be incurred in 2023/24.
1.2During the year the Council has generated £1.310million of interest from its investments. This is more than the budgeted total of £1.277million at Quarter 3, and significantly more than the original budget of £0.119million.
1.3The Council has repaid £0.019million of borrowing during the year as it has matured. The Council has £0.367million of remaining borrowing. This borrowing is at a fixed rate for a fixed period. The premium incurred from repaying this borrowing early means that it is not worthwhile to do so.
1.4The Council complied with its legislative and regulatory requirements throughout the year.
Recommendations
2.1That Cabinet notes expenditure of £6.923million in 2022/23 on the capital programme, paragraph 8.3 refers.
2.2That Cabinet approves the adjustments to the capital programme for 2023/24 as a result of the revised timetable of schemes detailed in table 2, increasing the estimated spend in by £1.222million.
2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.7 and the requirement to keep the capital programme under review for affordability. 2.4 That Cabinet approves the application of £6.300million of capital receipts/set aside towards the 2022/23 capital programme, paragraph 8.7 refers.
2.5Cabinet is asked to note the position of Treasury Management activity as at the end of March 2023.
2.6Cabinet is asked to recommend this report to Council and ask Council to:
1) Approve the actual 2022/23 prudential and treasury indicators. 2) Note the annual Treasury Report for 2022/23.
Reasons for recommendations
3.1Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.
3.2To ensure the Council’s continued compliance with CIPFA’s code of practice on Treasury Management and the Local Government Act 2003 and that the Council manages its exposure to interest and capital risk.
Alternative options considered
4.1Options for capital investment are considered as part of the Corporate Business Planning process.
4.2The primary principles governing the Council’s investment criteria are the security of its investments (ensuring that it gets the capital invested back) and liquidity of investments (being able to get the funds back when needed). After this the return (or yield) is then considered, which provides an income source for the Council. In relation to this the Council could take a different view on its appetite for risk, which would be reflected in the Investment Strategy. In general, greater returns can be achieved by taking on greater risk. Once the Strategy has been set for the year, there is limited scope for alternative options as Officers will seek the best return that is in accordance with the Investment Strategy.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.
5.2There are regular meetings with Treasury advisors (Link).
6. FORWARD PLAN 6.1 This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 21st April 2023.
Background
7.1In February 2022, Council approved the Integrated Capital and Treasury Strategy for 2022/23 to 2031/32.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit and Risk Committee at North Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.