LEISURE MANAGEMENT CONTRACT AWARD - PART 1

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 12 December 2023. Below is the council's own wording, with the papers it was decided on.

Item242

Resolved

That Cabinet agreed to award the Leisure and Active Communities Contract to the successful bidder highlighted in the Part 2 report. Subject to Standstill period. REASON FOR DECISION: The leisure management contracts expire on 31 March 2024. The recommendation ensures the procurement can be undertaken and completed within the project timescales, enabling the successful ongoing provision of leisure services in North Herts. That Cabinet agreed to award the Leisure and Active Communities Contract to the successful bidder highlighted in the Part 2 report. Subject to Standstill period. REASON FOR DECISION: The leisure management contracts expire on 31 March 2024. The recommendation ensures the procurement can be undertaken and completed within the project timescales, enabling the successful ongoing provision of leisure services in North Herts.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 8 pages

Executive summary

1.1This report seeks approval to award the Leisure and Active Communities Contract, due to commence on 1 April 2024.

Recommendations

2.1That Cabinet agree to award the Leisure and Active Communities Contract to the successful bidder highlighted in the Part 2 report. Subject to Standstill period.

Reasons for recommendations

3.1Our leisure management contracts expire on 31 March 2024. The recommendation ensures the procurement can be undertaken and completed within the project timescales, enabling the successful ongoing provision of leisure services in North Herts.

Alternative options considered

4.1None

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1A project board was established for consultation on the leisure management procurement project, which included senior officers and the Executive Member for Environment and Leisure, Cllr Steve Jarvis and Cllr Ian Albert, Executive Member for Finance and IT. The Service Director – Place is Project Executive.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on 13 October 2023.

Background

7.1In March 2022, the Council appointed leisure consultants The Sport, Leisure and Culture Consultancy (SLC) to carry out a bespoke diagnostic review, based on Sport England’s Strategic Outcomes Planning Guidance, to support the Council’s immediate strategic needs. As a result of the review, a Procurement Strategy was developed to support the leisure procurement project and a new Active North Herts Strategy developed that provides the Council and its stakeholder partners a clear policy position on its approach to the future delivery of sport, leisure, physical activity and wellbeing services across the district. SLC were also commissioned to support the procurement process as project coordinators and legal advisors Trowers and Hamlin were appointed for the procurement.

7.2On 14 March 2023, Cabinet approved the following recommendations to ensure the procurement was managed effectively and ensure the successful ongoing provision of leisure services in North Herts.

14 LEISURE MANAGEMENT CONTRACT UPDATE

RESOLVED: That Cabinet approved:

(1) A Competitive Procedure with Negotiation (CPN) procedure for the procurement of the Leisure Management contract.

(2) The delegation of powers to the Director of Place in consultation with project board, in relation to decisions associated with the development of the procurement strategy.

(3) The letting of a 10-year contract with an option to extend by up to 5 years.

(4) The combining of the existing three contracts into a single contract, using the nationally recognised Sport England contract format, in order to secure economies of scale and to attract the most interest from the operator market.

(5) To continue with the principle of the existing contractual shared risk approach to utilities and maintenance.

REASONS FOR DECISIONS: the leisure management contract. expire on 31 March 2024. These recommendations ensure the procurement will be managed effectively to ensure the successful ongoing provision of leisure services in North Herts. The Procurement offers an opportunity to review the existing specification and provide a clear policy position on its approach to the future delivery of sports, leisure, physical activity and wellbeing across the district.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LEISURE MANAGEMENT CONTRACT AWARD: PART 1Agenda 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. LEISURE MANAGEMENT CONTRACT AWARD - PART 1This decision
  2. Leisure management contract procurement - end project reportNoted
  3. Leisure management contract award - part 1Agreed
  4. Leisure management contract updateApproved

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies