North Hertfordshire District Council
Finance, Audit and Risk Committee, Wednesday 10 September 2025 at 7.30pm

FIRST QUARTER CAPITAL PROGRAMME MONITORING 2025/26

Approved Finance 2 papers

Finance, Audit and Risk Committee approved this item on Wednesday 10 September 2025. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

That Finance, Audit and Risk Committee considered any governance and risk issues in relation to the Cabinet recommendations, RECOMMENDED TO CABINET: (1) That Cabinet notes the forecast expenditure of £27.624M in 2025/26 on the capital programme, paragraph 8.3 refers. (2) That Cabinet approves the adjustments to the capital programme for 2026/27 onwards, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend in 2026/27 by £0.838M and £0.608M in 2027/28. (3) That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. (4) That Cabinet recommends to Council that they approve a capital budget of £1.275M (£0.319M in 25/26, £0.478 in 26/27 and £0.478M in 27/28) for the Government’s new energy efficiency Warm Homes Scheme. This will be fully funded from Government grants, paragraph 8.5 refers REASON FOR RECOMMENDATION: Cabinet was required to approve adjustments to the capital programme and ensure the capital programme is fully funded. That Finance, Audit and Risk Committee considered any governance and risk issues in relation to the Cabinet recommendations. RECOMMENDED TO CABINET: (1) That Cabinet notes the forecast expenditure of £27.624M in 2025/26 on the capital programme, paragraph 8.3 refers. (2) That Cabinet approves the adjustments to the capital programme for 2026/27 onwards, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend in 2026/27 by £0.838M and £0.608M in 2027/28. (3) That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability. (4) That Cabinet recommends to Council that they approve a capital budget of £1.275M (£0.319M in 25/26, £0.478 in 26/27 and £0.478M in 27/28) for the Government’s new energy efficiency Warm Homes Scheme. This will be fully funded from Government grants, paragraph 8.5 refers REASON FOR RECOMMENDATION: Cabinet was required to approve adjustments to the capital programme and ensure the capital programme is fully funded.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Finance, Audit and Risk Committee, 8 pages

Executive summary

1.1To update Cabinet on progress with delivering the capital programme for 2025/26, as at the end of June 2025.

1.2To update Cabinet on the impact upon the approved capital programme for 2025/26 – 2034/35. The current estimate is a decrease in spend in 2025/26 of £0.412M and an increase in spend in future years of £1.446M (£0.838M in 2026/27 and £0.608M 2027/28). The most significant individual changes to the forecast spend in 2025/26 is the removal of the £0.563M budget for Solar for Business, the addition of the Government’s new energy efficiency scheme – Warm Homes £0.319M, reprofiling £0.250M into 2026/27 for resurfacing Broadway Gardens and increasing phase 2 of the Decarbonisation project by £0.122M.

Recommendations

That Finance, Audit and Risk Committee consider any governance and risk issues in relation to the Cabinet recommendations, which are:

2.1That Cabinet notes the forecast expenditure of £27.624M in 2025/26 on the capital programme, paragraph 8.3 refers.

2.2That Cabinet approves the adjustments to the capital programme for 2026/27 onwards, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend in 2026/27 by £0.838M and £0.608M in 2027/28.

2.3That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability.

2.4That Cabinet recommends to Council that they approve a capital budget of £1.275M (£0.319M in 25/26, £0.478 in 26/27 and £0.478M in 27/28) for the Government’s new energy efficiency Warm Homes Scheme. This will be fully funded from Government grants, paragraph 8.5 refers. 3. REASONS FOR RECOMMENDATIONS

3.1Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.

Alternative options considered

4.1Options for capital investment are considered as part of the Corporate Business Planning process.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Consultation on the capital expenditure report is not required. Members will be aware that consultation is incorporated into project plans of individual capital schemes as they are progressed.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 25th July 2025.

Background

7.1In February 2025, Council approved the Integrated Capital and Treasury Strategy for 2025/26 to 2034/35. The reports for Capital and Treasury have been split for the quarterly monitoring updates.

8. RELEVANT CONSIDERATIONS

8.1The Council has £127.0M of capital assets that it currently owns. The Investment Strategy set out the reasons for owning assets that are not for service delivery, including an assessment of Security, Liquidity, Yield and Fair Value. There have been no significant changes in relation to these since the last quarter. Capital Programme 2025/26 8.2 The full capital programme is detailed in Appendix A and shows the revised costs to date, together with the expected spend from 2025/26 to 2035/36 and the funding source for each capital scheme. 8.3 Capital expenditure for 2025/26 is estimated to be £27.624M. This is an increase of £6.561M on the forecast in the Investment Strategy 2025/26 report (reported to Council 27th February 2025). Table 1 below details changes to capital programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital App A 2526RecV3.pdfAppendix 3 pages Download
PDF
FIRST QUARTER CAPITAL PROGRAMME MONITORING 2025/26Report 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. FIRST QUARTER CAPITAL PROGRAMME MONITORING 2025/26This decision
  2. First quarter revenue budget monitoring 2026/27Noted
  3. First quarter capital budget monitoring review 2026/27Noted
  4. First quarter treasury management review 2026/27Noted
  5. First quarter revenue budget monitoring 2026/27Approved
  6. First quarter capital budget monitoring review 2026/27Approved

More from North Hertfordshire Finance, Audit and Risk Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Apologies for absenceThat Councillor Stewart Willoughby be elected as Chair for this meeting of the Finance, Audit and Risk Committee. Apo... Decided Open
9 Sep 2026 Minutes - 10 june 2026That the Minutes of the Meeting of the Committee held on 10 June 2026, as amended, be approved as a true record of th... Approved Open
9 Sep 2026 Notification of other businessThere was no other business notified. Decided Open
9 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
9 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies