SOLAR FOR BUSINESS SCHEME

Noted Scrutiny 2 papers

AI summaryNorth Hertfordshire District Council's Overview and Scrutiny Committee considered and noted the Solar for Business closure findings. [D] No businesses signed up; £95,000 had been allocated from UKSPF, and the remaining UKSPF budget was reallocated. [7.10] [P9] [10.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe committee reviewed why the Solar for Business pilot closed. [D] [3.1]
Money£563k capital and £51k revenue£95,000 came from UKSPF. [P9] £8,220 revenue costs were incurred. [10.1]
What happens nextUpdate budget for 2026/27Changes will remove the revenue saving, with net nil impact. [10.2]
Who it affectsBusinesses and council projectsNo businesses signed up; closure released capacity for other projects. [7.10] [14.2]

What was decided

The Overview and Scrutiny Committee considered and noted the findings of the Solar for Business Project Closure Report.

The closure decision had already been taken before the committee considered the findings. Report 14.1, P39

Why

The committee's purpose was to allow scrutiny of the reasons for closure. Report 3.1

The Project Oversight Group found that continuing would not be the best use of resources because suitable businesses were hard to attract and could not take up the offer. Report 8.1

No businesses signed up for installations. Reasons included insufficient bill savings, concerns about roof reinforcement costs, plans to invest directly and a lease considered too long. Report 7.10

What happens next

Update the 2026/27 budget by removing the revenue saving and updating capital cost forecasts, with net nil impact. Report 10.2

Consider further market engagement with businesses before going to market. Report 8.2

Continue exploring support for businesses to take up low carbon technologies, including grants or sharing good practice. Report 8.5

The money

  • £518,725 Capital funding allocated at the March 2024 Cabinet meeting to test the pilot. Report P9
  • £95,000 UKSPF funding allocated alongside the capital funding. Report P9
  • £563k Capital budget for the project. Report 10.1
  • £51k Revenue budget for the project. Report 10.1
  • £95k UKSPF contribution to the total project budget. Report 10.1
  • £8,220 Revenue costs incurred by the pilot project. Report 10.1

Options considered

  • Rejected: Continue the pilot project. The Project Oversight Group found that continuing would not be the best use of resources because suitable businesses could not be attracted and could not take up the offer. Report 8.1
  • Chosen: Close the pilot project. The closure decision had already been taken when the committee considered the findings, and the report records no formal alternative options. Report 14.1, P39, 4.1

Implications

  • Financial: There are no current financial implications. The remaining UKSPF budget was reallocated, the capital budget was removed from the capital programme, and the 2026/27 changes have net nil impact. Report 10.1, 10.2
  • Legal: There are no current legal implications. Concerns about the rules for subsidies arose during development, and the lease and power purchase agreement templates may support future projects. Report 9.1, 7.4, 8.5
  • Equalities: Public bodies must give due regard to equality duties. This report has no equalities implications. Report 12.1, 12.2
  • Risk: There are continuing reputational risks from not delivering the scheme, while the council continues to act on climate change and support businesses to reduce emissions. Report 11.3
  • Staffing: There are no current human resource implications, and closure released capacity for other projects. Report P39
  • Other: The report is not subject to the Social Value Act or go local requirements. Report P34
  • Climate: There are no known environmental impacts from the closure. Capacity was released for decarbonisation phase 2, which was anticipated to save 100 tonnes CO2e directly each year, and for delivery of the Warm Homes: Local Grant. Report 14.1, 14.2
  • Climate: If successful, the pilot aimed to save 92.21 tonnes CO2e in year one and up to 1844.23 tonnes over 20 years. Report 14.2

Who and where

  • Businesses in North Herts Report 7.7, 7.10
  • North Hertfordshire District Council Report 8.1, 10.1
  • Other council climate projects Report 14.2
  • People in low income homes Report 14.2
  • Businesses seeking low carbon technology support Report 8.5

Timeline

  • March 2024: The Cabinet allocated £518,725 capital funding alongside £95,000 from UKSPF to test the pilot. Report P9
  • 16 December 2024: The Project Oversight Group directed creation of a lessons and closure report and reallocation of the vast majority of UKSPF funding. Report 7.11
  • end of March 2025: The deadline for spending the UKSPF part of the budget passed. Report 7.6
  • 4 March 2025: A lessons learned document was presented to the Project Oversight Group. Report 7.11
  • 6 May 2025: The updated closure report was presented to the Political Liaison Board of the Executive and the Leadership team. Report 5.1, 7.11
  • 2026/27: The budget update will remove the revenue saving and update capital cost forecasts. Report 10.2
  • 2040: The council's goal was a net zero district. Report 7.2

Plain English for the jargon

  • UKSPF: The UK Shared Prosperity Fund, which provided part of the project funding. [P9]
  • Power purchase agreement: An agreement under which businesses use generated electricity and provide revenue to the council over 25 years. [7.2]
  • Lease Agreement: A long term agreement with businesses and potentially their landlords, for up to 25 years. [7.4]
  • Project Oversight Group: The group that provided project governance, met every two months and advised on issues and risks. [7.5]
  • kWp: The unit used to state the pilot's total targeted solar panel capacity. [7.2]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item36

Resolved

That the Overview and Scrutiny Committee considered and noted the findings of the Solar for Business Project Closure Report (Appendix A). REASON FOR DECISION: To enable the Committee to scrutinise the reasons for closure of the project.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 6 pages

Executive summary

The purpose of the report is to provide an overview of the key lessons learned and project closure reasons for the Solar for Business pilot project.

Recommendations

2.1For Overview and Scrutiny to consider and note the findings of the Solar for Business Project Closure Report (Appendix A).

Reasons for recommendations

3.1To enable the Committee to scrutinise the reasons for closure of the project.

Alternative options considered

4.1None.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1The Executive Member for Environment (then Environment and Leisure) was consulted prior to the decision on project closure. A report was presented to the internal Political Liaison Board of the Executive and the Leadership team, on 6 May 2025, presenting an overview of the Solar for Business Project Closure Report (Appendix A) for their information.

6. FORWARD PLAN

6.1This report does not contain a recommendation on a key Executive decision and has therefore not been referred to in the Forward Plan.

7. BACKGROUND 7.1. At the March 2024 Cabinet meeting, £518,725 capital funding alongside £95,000 from the UK Shared Prosperity Fund (UKSPF) was allocated to support testing a pilot Solar for Business scheme in North Herts.

7.2The project aim was to successfully pilot installing solar panels on the roofs of at least five businesses in the district, with an installed capacity totalling 750 kWp and to have a power purchase agreement in place with businesses on use of the generated electricity, providing revenue to NHDC over 25 years. There were two intended benefits from the project: firstly, generation of renewable energy aligned with the council’s sustainability priority, contributing to the council’s goal of a net zero district by 2040; and secondly, installations also needed to generate revenue for the council, paying back the investment over time. Both benefits needed to be realised for this scheme to be considered viable.

7.3The pilot was based on and adopted similar principles to a successful project delivered by West Suffolk District Council, which had led to installations on over 70 businesses in their district. The project aims were based on delivering a similar scheme, targeting businesses with larger roof spaces and high electricity usage, to generate the most renewable electricity that is used on site. Officers engaged with West Suffolk throughout the project and West Suffolk shared expertise and materials to inform the pilot project. It was not possible to replicate West Suffolk’s scheme exactly with differences further discussed in section 8.3.

7.4Wider input was sought during project development, meeting with Warrington Borough Council as they had trialled this scheme on a single commercial property, to learn from their experiences. No other local authority has been identified that has successfully delivered this scheme. Conversations with West Suffolk and Warrington highlighted potential challenges, including having to agree both long-term power purchase agreements and lease agreements with businesses and potentially their landlords for up to 25 years. There were also concerns in relation to subsidy control. Further external feedback was provided later in the scheme, discussed in 8.1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 13 Appendix A: Solar for Business Project Closure Report finalAppendix 7 pages Download
PDF
SOLAR FOR BUSINESS SCHEMEReport 6 pages DownloadRead as text

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open