INFORMATION NOTE: MUSEUM COLLECTION FACILITY UPDATE

Decided Scrutiny 3 papers

AI summaryNorth Hertfordshire councillors noted a project update on the new museum collection facility at Unit 1, Letchworth. Design work is due to end in March 2026, with renovation starting after the sitting tenant leaves in July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedMembers asked questions on the update
MoneyNot stated
What happens nextDesign work ends March 2026Works contractor procured by June 2026
Who it affectsNorth Hertfordshire museum collectionWill relocate from Burymead Road, Hitchin

What was decided

The Overview and Scrutiny Committee received the Information Note on the Museum Collection Facility Project from the Executive Member for Enterprise and asked questions.

Why

Members of Overview and Scrutiny requested an Information Note and update on the project for the committee's January 2026 meeting. Report 2.8

The existing museum collection facility on Burymead Road, Hitchin has been deteriorating, with efforts to address this ongoing for several years. Report 2.1

What happens next

Officers aim to appoint a Professional Technical Services team early in 2026 to carry out design work and surveys, with design works concluding around March 2026. Report 4.1, 4.2

A works contractor is to be procured and mobilised by June 2026, with renovation starting in July 2026 once the sitting tenant has left and completing in December 2026. Report P26

Collection relocation is planned for January 2027 to early 2028, with Burymead Road fully vacated by mid to late 2028. Report P26

Options considered

  • Rejected: Option A: Do Nothing. Discounted by Cabinet on 19 November 2024 Report P7, 2.4
  • Rejected: Option B: Prolong the life of the existing facilities. Discounted by Cabinet on 19 November 2024 Report P7, 2.4
  • Rejected: Option G: Relocate the museum collection to another council owned facility. Discounted by Cabinet on 19 November 2024 Report P7, 2.4
  • Rejected: Option D: Redevelop the existing site. Budget was approved to develop further understanding but Unit 1 was selected instead Report P8, 2.5
  • Chosen: Option E: Purchase of a freehold or long leasehold building. Cabinet approved acquisition of the long leasehold of Unit 1, Works Road on 18 March 2025 Report P8, 2.7
  • Rejected: Option C: Renovate the existing facilities. Retained to explore further but Unit 1 was selected instead Report P9
  • Rejected: Option F: Leasing a building. Retained to explore further but Unit 1 was selected instead Report P9
  • Rejected: Option H: A partnership solution with other local museum providers. Retained to explore further but Unit 1 was selected instead Report P9

Implications

  • Financial: The Council has agreed an extension to the sitting tenant's lease to July 2026, securing ongoing income while avoiding a void period. Report 3.6
  • Risk: Standard project management documentation is in place, including Risk, Lessons and Issues Logs and Highlight Reports. Report 3.2
  • Other: An expression of interest for additional grant funded roles has progressed to a full application stage. Report 3.3
  • Other: A Communications Plan has been drafted and adopted, with outreach to relevant stakeholders underway. Report 3.4
  • Staffing: An indicative plan for recruiting and engaging volunteers to support the project has been drafted, intended to follow the renovation phase. Report 3.7

Who and where

  • North Hertfordshire museum collection, currently held at Burymead Road, Hitchin Report 1.1, 2.1
  • Future volunteers to be recruited to support the project from late 2026 Report 3.7, P26
  • Stakeholders engaged through the project's Communications Plan Report 3.4

Timeline

  • 12th November 2024: Overview and Scrutiny Committee considered the options appraisal Report 2.3, P33
  • 19th November 2024: Cabinet approved discounting of some options and budget allocation for leading options Report 2.4, P34
  • 11th March 2025: Overview and Scrutiny Committee reviewed the proposal to purchase the long leasehold of Unit 1, City Park Report 2.6, P35
  • 18th March 2025: Cabinet approved acquisition of the long leasehold of Unit 1, Works Road Report 2.7, P36
  • Early 2026: Professional Technical Services team to be appointed Report 4.1
  • March 2026: Design works to conclude Report 4.2, P26
  • June 2026: Works contractor to be procured and mobilised Report P26
  • July 2026: Existing tenant departs and renovation works begin Report 3.6, P26
  • August 2026: Collection strand project roles to be recruited Report P26
  • December 2026: Volunteers recruited and trained, and renovation works complete Report P26
  • January 2027 to early 2028: Collection relocation takes place Report P26
  • Mid to late 2028: Burymead fully vacated Report P26

Plain English for the jargon

  • Long leasehold interest: A leasehold interest held for a long period, giving the holder many of the benefits of ownership.
  • Sitting tenant: A tenant already in occupation of a property when it changes hands.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48

Resolved

Councillor Tamsin Thomas, as Executive Member for Enterprise presented the Information Note entitled ‘Museum Collection Facility Update’, following which Members asked questions.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 3 pages

Summary

1.1This Information Note provides an update on the Council project to deliver a new facility to house the museum collection of North Hertfordshire.

2. STEPS TO DATE

2.1Efforts to address the deteriorating conditions at the current museum collection facility on Burymead Road, Hitchin have been ongoing for several years with numerous options explored.

2.2In late 2024 a detailed options appraisal was prepared with the intention of gaining support for the pursuit of a small number of specific solutions available and to formally discount other options from consideration.

2.3The options appraisal and accompanying report was taken to Overview and Scrutiny Committee on 12th November 2024, where members of the committee signalled their support for some options to be discounted, whilst a limited budget was to be allocated for officers to explore some of the leading proposed solutions.

2.4Cabinet approved the discounting of some options and the allocation of budget to pursue leading options on 19th November 2024.

Options discounted were as follows: Option A – ‘Do Nothing’ Option B – ‘Prolong the life of the existing facilities’ Option G – ‘Relocate the museum collection to another council owned facility’

Options where budget was approved to develop further understanding were as follows: Option D – ‘Redevelop the existing site’ Option E – ‘Purchase of a freehold/long leasehold building’

Options retained to explore further were as follows: Option C – ‘Renovate the existing facilities’ Option F – ‘Leasing a building’ Option H – ‘A partnership solution with other local museum providers’

2.5One such option which officers explored further was to secure the long leasehold interest in a local suitable property coming to the open market. Unit 1, City Park, Letchworth was one such building and officers were able to use the allocated budget available to carry out due diligence and pull together a business case and report on the building. This facility was considered to boast a number of distinct advantages over other options. It represented a comparatively cost effective proposition, which both allowed for the long term future preservation of the collection to be secured whilst it also would allow for sufficient contingency in terms of space.

2.6A proposal to purchase the long leasehold interest in Unit 1, City Park was presented to Overview and Scrutiny Committee on 11th March 2025 for review and the committee signalled its support of this proposal which was then taken to Cabinet.

2.7Cabinet approved the acquisition of the long leasehold interest of Unit 1, Works Road at its meeting of 18th March 2025, with a view to this being converted into the new long term home for the museum collection of North Hertfordshire.

2.8Members of Overview and Scrutiny requested an Information Note and update on the project be presented to the committee at its January 2026 meeting.

3. INFORMATION TO NOTE

3.1The long leasehold interest in Unit 1, City Park has been formally acquired. At the time of acquiring the long leasehold interest, the property had a sitting tenant in place until January 2026.

3.2The Project Board has been formed, and all standard project management documentation has been prepared and is being followed (Terms of Reference, Project Plan, Risk, Lessons and Issues Logs, along with Highlight Reports).

3.3An expression of interest to secure additional grant funded roles to support the project has been submitted and the Council have been invited to submit a full application to be considered further.

3.4A Communications Plan for the project has been drafted and adopted, with outreach and engagement with relevant stakeholders actively taking place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Indicative Top Level Gantt Chart.docxAppendix 1 1 pages Download
PDF
Aspirational Images.docxAppendix 2 1 pages Download
PDF
INFORMATION NOTE: MUSEUM COLLECTION FACILITY UPDATEReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. INFORMATION NOTE: MUSEUM COLLECTION FACILITY UPDATEThis decision
  2. Information note: council activity update and action trackerDecided
  3. Information note: annual review of safeguarding and protecting children and adults 2025-26Decided
  4. Information note: waste and recycling updateDecided
  5. Information note - national scheme of delegationDecided
  6. Information note - secretary of state directionDecided

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open