CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Finance, Audit and Risk Committee, Wednesday 7 January 2026 at 7.30pm

REVENUE AND CAPITAL BUDGETS FOR 2026/27 ONWARDS

Agreed Finance 4 papers

AI summaryNorth Herts Finance, Audit and Risk Committee asked to comment on Cabinet's draft 2026/27 budget proposals, including a 2.99% Council Tax rise and use of reserves to cover a £1,037k shortfall.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedNotes funding, confirms Council Tax rise, agrees proposals
Money2.99% Council Tax rise proposedMaximum allowed without local referendum
What happens nextFinal budget to Full Council26 February 2026
Who it affectsNorth Hertfordshire residents and council servicesIncludes LGR transition and waste EPR income

What was decided

Recommend Cabinet notes the Council's expected funding for 2026/27, including the provisional Local Government settlement released on 17 December 2025 covering 2026/27 to 2028/29. Report 2.1, 8.8

Recommend Cabinet confirms that budget forecasts be based on a 2.99% Council Tax increase, the maximum allowed without a local referendum, in line with the Medium-Term Financial Strategy. Report 2.2, 8.16

Recommend Cabinet agree which revenue and capital proposals should be taken forward into the budget-setting process for 2026/27, with the appendices attached for review. Report 2.3, 8.12

Why

To ensure all relevant factors are considered in arriving at a proposed budget and Council Tax level for 2026/27. Report P8

Government has now provided greater certainty over funding through Fair Funding 2 and a three-year provisional settlement, allowing officers to refresh forecasts. Report P1, 8.8

On current assumptions the Council can balance its budget without substantial savings, using General Fund reserves of £2.455 million, of which £2 million is earmarked for Local Government Reorganisation. Report 8.15

What happens next

A further report will be presented to Cabinet in February, with Business Ratepayers consulted via the website and email, before final approval by Full Council on 26 February 2026. Report 5.2, 5.4, P8

The next iteration will include a full review of estimates, reserve balances, and a section 25 report from the Director of Resources on the minimum General Fund reserve level. Report 11.2

Any saving proposal with a particular local impact may be referred by the relevant Community Forum to Cabinet before the budget goes to Full Council. Report 5.5

The money

  • 2.99% Proposed Council Tax increase, the maximum allowed without a local referendum Report 2.2, 8.16
  • £6-£6.5m Estimated Government funding for 2026/27, refreshed after Fair Funding 2 policy statement
  • £7.787m Estimated Extended Producer Responsibility payment for 2026/27 Report 8.8
  • £1.435m Extended Producer Responsibility payment received in 2025/26 Report 8.8
  • £1.28 million Estimated annual saving from new pension contribution rate of 16.9% of pay, down from 19.5% plus a £1.03m lump sum Report 8.10
  • £147k Ongoing additional costs identified in the Quarter 2 budget monitoring report Report 8.11
  • £2.455 million Total use of General Fund reserves to balance the 2026/27 and 2027/28 budgets Report 8.15
  • £2 million Reserves allocation within the £2.455 million for Local Government Reorganisation transition Report 8.15
  • (1,037) Forecast deficit for 2026/27 after revised spend and funding estimates Report P42
  • (1,418) Forecast deficit for 2027/28 after revised spend and funding estimates Report P42
  • 88 Forecast surplus for 2028/29 after revised spend and funding estimates Report P42
  • +1,180 (+5.3%) Change in provisional 2026/27 funding compared with 2025/26 Council totals Report P32
  • +855 (+3.9%) Change in provisional 2026/27 funding compared with the highest MTFS estimate Report P32

Options considered

  • Chosen: Increase Council Tax by 2.99% (maximum without referendum). Aligns with Government Core Spending Power assumptions and the agreed Medium-Term Financial Strategy Report 2.2, 8.16
  • Chosen: Use General Fund reserves to balance the budget in 2026/27 and 2027/28. Preferred by 35% of survey respondents as a first step, and affordable alongside planned LGR allocations Report 8.4, 8.15
  • Rejected: Increase or introduce fees and charges. Considered by residents as the next preference after reserves, at 25% and 22% respectively Report 8.4
  • Rejected: Reduce the frequency or quality of services. Least popular options in the resident survey at 15% and 3% Report 8.4

Implications

  • Financial: Available and forecast capital reserves will not be sufficient to fund the capital programme, so the Council will need to borrow, using internal cash where possible and incurring a Minimum Revenue Provision charge. Report 10.3
  • Financial: Funding estimates for 2027/28 and 2028/29 are indicative only and could change before final settlement. Report 8.8
  • Financial: EPR payments for 2026/27 onwards are not guaranteed, so a 20% annual drop-off is still assumed after 2025/26. Report 8.8
  • Legal: Cabinet must keep the budget under review, and Members are reminded of the duty to set a balanced budget and maintain prudent General Fund and reserve balances. Report 9.1, 9.2, 9.3
  • Legal: Finance, Audit and Risk Committee has a role to assist Cabinet and Council through in-depth analysis of finance, audit and risk policy issues. Report 9.4
  • Risk: The next Cabinet report will include a section 25 assessment from the Director of Resources on the minimum General Fund reserve level, with the margin acting as a proxy for financial risk. Report 11.2
  • Equalities: Any individual proposal that is significant in value or affects more than two wards will require an equality analysis before efficiencies or growth are agreed. Report 12.2
  • Staffing: HR and training budgets within the LGR reserve will support staff through change, and efficiency proposals affecting staff will follow HR policy communication and consultation. Report 8.13, 15.1

Who and where

  • North Hertfordshire residents, who took part in the summer budget survey and would see a 2.99% Council Tax rise Report 8.1, 8.4, 2.2
  • Business Ratepayers, who will be consulted on the February budget proposals Report 5.4
  • Council staff, who may be affected by LGR transition and any efficiency proposals Report 8.13, 15.1
  • Community Forum areas where a saving proposal has a particular local impact Report 5.5

Timeline

  • 6 June to 1 August 2025: Resident budget survey ran over the summer Report 8.1
  • 4 November 2025: Estimated 2026/27 Extended Producer Responsibility payment of £7.787m provided Report 8.8
  • 20 November 2025: Government published its funding policy statement including Fair Funding 2 detail
  • 24 November 2025: Council notified of provisional pension contribution rates of 16.9% of pay from 2026/27 Report 8.10
  • 17 December 2025: Provisional Local Government finance settlement released, covering 2026/27 to 2028/29 Report P1, 8.8
  • 7 January 2026: This Finance, Audit and Risk Committee meeting
  • Early February 2026: Further Cabinet report on the budget Report 5.2, 11.2
  • 26 February 2026: Final budget to be approved by Full Council Report P8
  • April 2028: Current timetable for vesting to new Unitary Council arrangements Report 7.2

Plain English for the jargon

  • MTFS: Medium-Term Financial Strategy, the financial background for the Council's corporate business planning process
  • CSP: Core Spending Power, the Government's measure of total resources available to a Council, including Council Tax, Business Rates and other general funding
  • EPR: Extended Producer Responsibility, payments to Councils from producers for the cost of collecting and disposing of packaging
  • LGR: Local Government Reorganisation, the move to new Unitary Council arrangements
  • MRP: Minimum Revenue Provision, a revenue charge Councils must make to repay borrowing over the life of an asset
  • FAR Committee: Finance, Audit and Risk Committee of North Hertfordshire District Council
  • Fair Funding 2: The Government's new funding formula for local authorities
  • LG Futures: An external specialist the Council uses to forecast Local Government funding
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48

Resolved

RECOMMENDATION TO CABINET: That Finance, Audit and Risk Committee comment on the recommendations to Cabinet which are: (1) That Cabinet notes the Council’s expected funding for 2026/27. (2) That Cabinet confirms (in line with the Medium-Term Financial Strategy) that budget forecasts should be based on increasing Council Tax by 2.99% (the maximum amount allowable without a local referendum). Noting that Government have assumed Council Tax will increase by the maximum allowed in calculating Core Spending Power. (3) That Cabinet agree which proposals (revenue and capital) should be taken forward as part of the budget-setting process for 2026/27 REASON FOR RECOMMENDATION: To ensure that all relevant factors are considered in arriving at a proposed budget and level of Council Tax for 2026/27, to be considered by Full Council on 26 February 2026.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Finance, Audit and Risk Committee, 8 pages

Executive summary

Government have committed to a new funding formula (known as Far Funding 2) and providing a 3-year funding settlement to Councils. When Council considered the Medium-Term Financial Strategy in December, a verbal update was provided on the expected funding position following a policy statement from Government in November. On 17 December 2025 the provisional Local Government settlement was released by Government. This provides much greater certainty over our funding for the next 3 years.

The budget workshops at the start of November considered: • resident feedback from the budget consultation that we carried over the summer, • budget proposals for 2026/27 onwards, • setting our budget priorities, and how we would make substantial savings if they were needed to balance our budget.

This report updates on changes to our spend and funding forecasts since the Medium-Term Financial Strategy, and seeks approval from Cabinet on the revenue and capital proposals that should be incorporated into the final budget report in February. It also seeks approval for the level of Council Tax increase to be assumed in that report. 2. RECOMMENDATIONS

That Finance, Audit and Risk Committee comment on the recommendations to Cabinet which are:

2.1That Cabinet notes the Council’s expected funding for 2026/27.

2.2That Cabinet confirms (in line with the Medium-Term Financial Strategy) that budget forecasts should be based on increasing Council Tax by 2.99% (the maximum amount allowable without a local referendum). Noting that Government have assumed Council Tax will increase by the maximum allowed in calculating Core Spending Power.

2.3That Cabinet agree which proposals (revenue and capital) should be taken forward as part of the budget-setting process for 2026/27 .

3. REASONS FOR RECOMMENDATIONS 3.1 To ensure that all relevant factors are considered in arriving at a proposed budget and level of Council Tax for 2026/27, to be considered by Full Council on 26 February 2026.

Alternative options considered

4.1The Medium-Term Financial Strategy (2026-30) set out a range of options that were dependent on the Council’s ongoing funding position following the provisional funding settlement.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Councillors were given an opportunity to comment on specific and general budget proposals at the budget workshops. However, it was agreed that (to facilitate open discussion) any comments would not be fed back to Cabinet.

5.2This report is the first draft of the budget and a further report to Cabinet will follow in February. Both reports will also be considered by the Finance, Audit and Risk (FAR) Committee. The final budget reports will be approved by Council.

5.3Residents were consulted over the summer on our general approach to budget setting and priorities. See paragraph 8.1.

5.4Business Ratepayers will be consulted on the proposals within the February report. This is the only statutory consultation that is required. This consultation will be via the website/ e-mail.

5.5If any saving proposal is anticipated to have a particular impact on a specific area (or areas) then it can be considered by the relevant Community Forum(s). Any comments could be referred to Cabinet when they are considering the budget to be referred on to Full Council.

6. FORWARD PLAN

6.1This report does not contain a recommendation on a key Executive decision and has therefore not been referred to in the Forward Plan.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Results from budget consultationAppendix A 2 pages Download
PDF
Revenue budget proposalsAppendix B 4 pages Download
PDF
Capital budget proposalsAppendix C 3 pages Download
PDF
REVENUE AND CAPITAL BUDGETS FOR 2026/27 ONWARDSReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. REVENUE AND CAPITAL BUDGETS FOR 2026/27 ONWARDSThis decision
  2. Budget 2026/27 (revenue and capital budgets)Noted
  3. Budget 2026/27 (revenue and capital budgets)Approved
  4. Budget 2026/27 (revenue and capital budgets)Approved
  5. Revenue and capital budgets for 2026/27 onwardsNoted
  6. Revenue and capital budgets for 2025/26 onwardsNoted

More from North Hertfordshire Finance, Audit and Risk Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Apologies for absenceThat Councillor Stewart Willoughby be elected as Chair for this meeting of the Finance, Audit and Risk Committee. Apo... Decided Open
9 Sep 2026 Minutes - 10 june 2026That the Minutes of the Meeting of the Committee held on 10 June 2026, as amended, be approved as a true record of th... Approved Open
9 Sep 2026 Notification of other businessThere was no other business notified. Decided Open
9 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
9 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies