EXTERNAL AUDIT PLAN AND STRATEGY 2025-26

Noted Finance 1 paper

AI summaryNorth Hertfordshire District Council's Finance, Audit and Risk Committee noted KPMG's external audit plan for the 2025-26 accounts, with a £1.8m materiality and £168,930 scale fee.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted KPMG's External Audit Plan and Strategy 2025-26
Money£168,930 scale fee2025-26 scale fee set by PSAA, total TBC pending variations
What happens nextAudit plan in progressRisk assessment to complete by 31 July 2026, closing meeting November 2026
Who it affectsNorth Hertfordshire District CouncilExternal audit of 2025-26 financial statements and value for money

What was decided

The Committee noted KPMG's External Audit Plan and Strategy for the year ending 31 March 2026.

Why

KPMG presented its planned audit approach, scope, materiality and risk assessment for the 2025-26 financial statements, covering rebuilding assurance after a series of prior disclaimers. Report P2, P6

The plan sets out four significant risks: valuation of land and buildings, valuation of investment property, valuation of post retirement benefit obligations, and management override of controls. Report P15, P19, P24, P26, P28

What happens next

KPMG will complete the rebuilding assurance risk assessment by 31 July 2026 and report any significant changes to the planned approach. Report P2, P6

KPMG plans a closing meeting with management in November 2026 and a further committee meeting in January 2027 to communicate misstatements and control deficiencies. Report P12

Value for money risk assessment work is ongoing and the output will be reported to a future meeting of the Committee. Report P17, P57

The money

  • £1.8m Materiality for the financial statements as a whole (2.6% of total expenditure) Report P8
  • £1.35m Performance materiality, set at 75% of materiality Report P8
  • £90k Threshold for reporting misstatements to the audit committee Report P9
  • 168,930 2025/26 scale fees as set by PSAA Report P77
  • 190,977 Total 2024/25 audit fees (including £26,648 prior year variation) Report P77
  • £32.3k 2024/25 non-audit fees used as benchmark for fee ratio Report P92
  • £27.7m Value of the investment property portfolio as at 31 March 2025 Report P24

Options considered

  • Chosen: Rebut presumption that revenue recognition is a significant fraud risk. Council tax, business rates, fees and charges, and grant income are predictable, low-judgement or traceable to third party data Report P31, P32, P33
  • Chosen: Rebut presumption that expenditure recognition is a significant fraud risk. Council's financial position while under pressure is not indicative of incentive to manipulate expenditure and no specific risk factors identified Report P35

Implications

  • Financial: Prior 2022/23, 2023/24 and 2024/25 audit opinions were disclaimed; rebuilding assurance work is needed for 2025-26, including a balance sheet assessment of movements over the disclaimed period. Report P6
  • Financial: Materiality has risen from £1.7m (2024/25) to £1.8m (2025-26), with performance materiality rising from £1.1m to £1.35m. Report P8
  • Financial: 2025-26 fee variations are to be confirmed, with a TBC build back fee variation and an expected variation for the LGPS Triennial valuation. Report P77, P79
  • Risk: Four significant risks are identified, all centred on valuation judgements and management override, reflecting estimation uncertainty in property and pension balances. Report P15, P19, P24, P26, P28
  • Other: KPMG is also providing Housing benefit grant certification as a non-audit service in 2025/26, with safeguards in place to address self-review and management responsibility threats. Report P91
  • Staffing: The engagement lead Salma Younis is in her second year of a permitted five to seven year rotation as audit director. Report P66

Who and where

  • North Hertfordshire District Council, as the audited body Report P1, P2
  • KPMG LLP, as external auditor appointed via PSAA Report P77, P92
  • Council taxpayers and residents relying on audited accounts and value for money commentary Report P50

Timeline

  • 20 February 2025: Disclaimer of opinion issued for 2023/24 accounts at statutory backstop date Report P6
  • 27 February 2026: Disclaimer of opinion issued for 2024/25 accounts at statutory backstop date Report P6
  • April 2026: Kick-off meeting with management Report P12
  • 10 June 2026: Finance, Audit and Risk Committee meeting to present the audit plan Report P2, P12
  • by 31 July 2026: Completion of rebuilding assurance risk assessment Report P6
  • November 2026: Planned closing meeting with management (preliminary) Report P12
  • January 2027: Planned committee meeting to communicate misstatements and control deficiencies (preliminary) Report P12

Plain English for the jargon

  • Materiality: The level at which misstatements could reasonably be expected to influence users' economic decisions on the financial statements
  • Performance materiality: A lower threshold set to reduce aggregation risk from individually immaterial misstatements
  • Disclaimer of opinion: An audit opinion stating the auditor cannot gather enough evidence to form an opinion on the accounts
  • Backstop date: Statutory deadline by which audit reports must be published, set under amendments to the Accounts and Audit Regulations
  • LARRIGs: Local Audit Reset and Recovery Implementation Guidance issued by the NAO to support rebuilding audit assurance after backstop-related disclaimers
  • Value for money: Statutory commentary on the Council's arrangements for financial sustainability, governance, and improving economy, efficiency and effectiveness
  • Triennial valuation: An actuarial revaluation of the Local Government Pension Scheme carried out every three years, used to set contribution rates
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

That the Committee noted the External Audit Plan and Strategy 2025-26.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Finance, Audit and Risk Committee, 26 pages

North Hertfordshire District Council Report to Finance, Audit and Risk Committee

External Audit plan and strategy for the year ending 31 March 2026 30 April 2026 Introduction The engagement How we deliver audit quality Audit quality is at the core of everything we do at KPMG and we believe team that it is not just about reaching the right opinion, but how we reach that opinion. We consider risks to the quality of our audit in our Salma Younis (FCA) is the engagement engagement risk assessment and planning discussions. To the Audit and Risk Committee of North Hertfordshire director on the audit. She has over 20 years of We are pleased to have the opportunity to meet with you on 10 public sector experience. She shall lead the We define ‘audit quality’ as being the outcome when : June 2026 to discuss our audit of the financial statements of North engagement and is responsible for the audit • An audit is executed consistently, in line with the requirements and Hertfordshire District Council, as at and for the year ending 31 opinion. intent of applicable professional standards within a strong system of March 2026. quality controls; and Other key members of the engagement team This report provides the Finance Audit & Risk Committee with an include Anna Lord (Manager) and Stanley • All of our related activities are undertaken in an environment of the opportunity to review our planned audit approach and scope for Croall (Assistant Manager) with 7 years and 5 utmost level of objectivity, independence, ethics and integrity. the 2025/26 audit. The audit is governed by the provisions of the years of experience respectively. Local Audit and Accountability Act 2014 and is carried out in We depend on well-planned timing of our audit work to avoid Yours sincerely, compromising the quality of the audit. This is also heavily dependent on compliance with the NAO’s 2024 Code of Audit Practice, auditing standards and other professional requirements. Salma Younis receiving information from management and those charged with governance in a timely manner. This report outlines our risk assessment and planned audit 30 April 2026 approach. Our planning activities are still ongoing and we will We aim to complete all audit work no later than 2 days before audit communicate any significant changes to the planned audit signing. As you are aware, we will not issue our audit opinion until we approach subsequently. Restrictions on distribution have completed all relevant procedures, including audit documentation.

We provide this report to you in advance of the meeting to allow This report is intended solely for the We are committed to providing you with a high-quality service. If you have you sufficient time to consider the key matters and formulate information of those charged with governance any concerns or are dissatisfied with any part of KPMG’s work, in the first your questions. of North Hertfordshire District Council and the instance you should contact Salma Younis ([email removed]), report is provided on the basis that it should the engagement lead to the Authority, who will try to resolve your Contents Page not be distributed to other parties; that it will complaint. If you are dissatisfied with the response, please contact the not be quoted or referred to, in whole or in national lead partner for all of KPMG’s work under our contract with Public Rebuilding assurance 3 part, without our prior written consent; and that Sector Audit Appointments Limited, Tim Cutler ([email removed]). Overview of planned scope including materiality 4 we accept no responsibility to any third party After this, if you are still dissatisfied with how your complaint has been in relation to it. handled you can raise your complaint as per the following process Significant risks and Other audit risks 6 Complaints. Audit Risks and our audit approach 7

Mandatory communications 14

Appendix 18

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXTERNAL AUDIT PLAN AND STRATEGY 2025-26Report 26 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. EXTERNAL AUDIT PLAN AND STRATEGY 2025-26This decision
  2. External audit - 2025/26 vfm risk assessmentNoted
  3. External audit - rebuilding assurance updateNoted
  4. External audit plan and strategy 2024-25Noted
  5. External audit - auditors annual report 2024-25Noted
  6. External audit plan & strategy 24/25 (kpmg)Noted

More from North Hertfordshire Finance, Audit and Risk Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Apologies for absenceThat Councillor Stewart Willoughby be elected as Chair for this meeting of the Finance, Audit and Risk Committee. Apo... Decided Open
9 Sep 2026 Minutes - 10 june 2026That the Minutes of the Meeting of the Committee held on 10 June 2026, as amended, be approved as a true record of th... Approved Open
9 Sep 2026 Notification of other businessThere was no other business notified. Decided Open
9 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open