Planning Control Committee, Thursday 13 August 2026 at 7.00pm

25/02885/OP LAND AT MILL LANE, LONDON ROAD, ST IPPOLYTS, HITCHIN, SG4 7NN

Agreed Planning 4 papers

AI summaryNorth Hertfordshire Planning Control Committee grants outline planning permission for up to 41 homes at St Ippolyts, subject to a Section 106 agreement including school expansion contributions and amended conditions on biodiversity, roads and building height.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to three amended conditions on biodiversity, roads and height
MoneyMultiple S106 contributions soughtIndex linked to BCIS 1Q2024, payable to Hertfordshire County Council
What happens nextS106 Legal Agreement to be completedDelegated powers given to Development and Conservation Manager
Who it affectsFuture residents of 41 homesPlus local schools, childcare, library and other county services

What was decided

Outline planning permission was granted for up to 41 dwellings with associated infrastructure and open space, with all matters reserved except means of access. Report P5

The decision is subject to the completion of a Section 106 Legal Agreement, with delegated powers to the Development and Conservation Manager to agree Heads of Terms for the sports pavilion and other minor changes.

Three conditions were amended: Condition 7 (Construction Environmental Management Plan for Biodiversity, informed by the November 2025 Ecological Impact Assessment), Condition 12 (parking, internal roads and turning areas to be detailed at reserved matters stage) and Condition 20 (no residential development to be more than two storeys in height).

Why

Hertfordshire County Council's Growth and Infrastructure Unit sought financial contributions to mitigate the impact of the development on county services including education, childcare, libraries, youth services, waste, and fire and rescue. Report P6, P21, P25, P27

The contributions are calculated using the size, type and tenure of the dwellings, based on the methodology in the Guide to Developer Infrastructure Contributions approved by the County Council's Cabinet on 12 July 2021. Report P26, P30, P31

The applicant can recalculate contributions at the reserved matters stage if the dwelling mix changes, and the obligation is needed because the County Council cannot adopt its own Community Infrastructure Levy charge. Report P21, P23

What happens next

Complete the Section 106 Legal Agreement, with any necessary extension of time taken to do so.

Reserved matters applications to follow, with detailed plans for hard surfaces, visibility, cycle storage and other matters required under the amended conditions. Report P23

Hertfordshire County Council requested to be kept informed of progress so planning obligation instructions can be given if the application is minded to be granted, or evidence submitted at any appeal. Report P33

The money

  • £416,769 Primary education contribution towards expansion of St Ippolyts Primary School, index linked to BCIS 1Q2024 and BCIS Regional Factor Report P10
  • £435,973 Secondary education contribution towards expansion of The Priory Secondary School, index linked to BCIS 1Q2024 and BCIS Regional Factor Report P11
  • £9,240 Childcare contribution for 0 to 2 year old capacity at North Herts Rural West Family Centre Reporting Locality, index linked to BCIS 1Q2024 Report P12
  • £649 Childcare contribution for 5 to 11 year old capacity at St Ippolyts Primary School, index linked to BCIS 1Q2024 Report P13
  • £70,944 SEND contribution towards new Severe Learning Difficulty special school places (EAST), index linked to BCIS 1Q2024 and BCIS Regional Factor Report P14
  • £11,011 Library service contribution towards increasing capacity at Hitchin Library, index linked to BCIS 1Q2024 Report P15
  • £6,646 Youth service contribution towards resource requirements to support youth work, index linked to BCIS 1Q2024 Report P16
  • £7,882 Waste service contribution towards increasing capacity at Letchworth Recycling Centre or a new recycling centre in Baldock, index linked to BCIS 1Q2024 Report P17
  • £11,023 Waste service contribution towards increasing capacity through the new Northern Transfer Station, index linked to BCIS 1Q2024 Report P17
  • £1,020 Fire and Rescue service contribution towards new appliances and equipment at Hitchin Fire Station, index linked to BCIS 1Q2024 Report P18
  • £420 HCC monitoring fee per distinct trigger within the legal agreement, adjusted for inflation against RPI January 2024 Report P19, P20

Options considered

  • Chosen: Grant outline planning permission subject to Section 106 agreement and amended conditions. Delegated to Development and Conservation Manager to agree Heads of Terms and complete the legal agreement, with conditions amended to address biodiversity, road safety and local context

Implications

  • Financial: Developer must pay financial contributions to Hertfordshire County Council towards education, childcare, SEND, library, youth, waste and fire and rescue services, all index linked to BCIS 1Q2024. Report P10, P11, P12, P13, P14, P15, P16, P17, P18
  • Legal: A Section 106 Legal Agreement must be completed before the permission is finalised, with recalculation possible at reserved matters stage if the dwelling mix changes. Report P23
  • Other: Condition 7 requires a Construction Environmental Management Plan for Biodiversity, informed by the November 2025 Ecological Impact Assessment, before any development or ground works take place.
  • Other: Condition 20 restricts all residential development to no more than two storeys in height to keep the new buildings in keeping with the local context.

Who and where

  • Future residents of up to 41 new homes at Mill Lane, St Ippolyts, Hitchin Report P5, P8
  • St Ippolyts Primary School, including provision for 5 to 11 year old childcare and primary school expansion Report P10, P13
  • The Priory Secondary School, for secondary school expansion Report P11
  • Hitchin Library service users Report P15
  • Young people using youth services in the area Report P16
  • Householders using Letchworth Recycling Centre and the new Northern Transfer Station Report P17
  • Residents served by Hitchin Fire Station Report P18
  • Children and young people with Severe Learning Difficulties needing new special school places in the EAST area Report P14

Timeline

  • 4 August 2026: Hertfordshire County Council Growth and Infrastructure Unit dated its updated response seeking planning obligations Report P3
  • 13 August 2026: North Hertfordshire Planning Control Committee considered and granted the application subject to conditions and Section 106
  • 2026 to 2032: Trajectory for the 41 units, with completions in 2026, 2027, 2028, 2029, 2030 and 2032 as set out in the county council response Report P8

Plain English for the jargon

  • BCIS: Building Cost Information Service, the index used to uprate the county council's developer contributions
  • CEMP: Construction Environmental Management Plan, a document setting out how construction works will avoid harm to the environment
  • CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure
  • HCC: Hertfordshire County Council, the upper tier authority providing services such as education, libraries, waste disposal and fire and rescue
  • S106: Section 106 Legal Agreement, a planning obligation under which a developer agrees to pay contributions or provide works as part of a planning permission
  • SEND: Special Educational Needs and Disabilities, covering additional support for children and young people with learning difficulties
  • SLD: Severe Learning Difficulty, used here to describe the type of special school places the SEND contribution would fund
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43

Resolved

That application 22/00956/OP be GRANTED planning permission subject to: A) Providing delegated powers to the Development and Conservation Manager to agree the outstanding S106 Heads of Terms related to the sports pavilion, and any other minor changes to conditions and informatives as required; and B) The completion of the S106 Legal Agreement and any necessary extension of time taken to complete this; and C) The conditions and informatives as set out in the report of the Development and Conservation Manager, with amendments to Conditions 7, 12 and 20, as follows: ‘ Condition 7 No development shall take place (including ground works or vegetation clearance) until a construction environmental management plan (CEMP: Biodiversity) has been submitted to and approved in writing by the local planning authority. The CEMP (Biodiversity) should be informed by the November 2025 Ecological Impact Assessment and include the following: a) Risk assessment of potentially damaging construction activities. b) Identification of "biodiversity protection zones". c) Practical measures to avoid or reduce impacts during construction. d) The location and timing of sensitive works to harm to biodiversity features. e) Use of protective fences, exclusion barriers and warning signs. The approved CEMP shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority. Reason: To protect wildlife and biodiversity. LP Policy NE4. Condition 12 Parking / Internal roads / Turning areas: The detailed plans should be submitted in connection with approval of reserved matters application which shall show to the satisfaction of the Local Planning Authority: o The details of all hard surfaced areas within the site. This includes, but is not limited to, all roads, footways, forecourts, driveways, parking and turning areas, and foul and surface water drainage. o The level of footway and carriageway visibility from each individual vehicle access, and the level of visibility from and around each main junction within the site, within which there shall be no obstruction to visibility between 600mm and 2m above the carriageway level. o That service vehicles, including refuse and emergency vehicles, can safely and conveniently access and route through the site, to include the provision of sufficient turning and operating areas. o The provision of sufficient facilities for cycle storage. All these features shall be provided before first occupation and maintained in perpetuity. Reason: To provide adequate visibility for drivers within the site, to promote alternative modes of travel, and for the overall free and safe flow of all site users. Condition 20 No residential development shall be more than two storey in height. Reason: To ensure that the new development is in keeping with local context. LP Policy D1.’
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Planning Control Committee, 4 pages

Growth & Environment Executive Director: Mark Doran

North Hertfordshire Council Growth & Infrastructure Unit Hertfordshire County Council Council Offices Postal Point: CHN114 Farnham House Gernon Road Six Hills Way Letchworth Garden City Stevenage, Hertfordshire SG1 2FQ www.hertfordshire.gov.uk Hertfordshire Respond to: [email protected] SG6 3JF

4 August 2026

Dear Planning Officer

Updated response by HCC’s Growth & Infrastructure Unit to 25/02885/OP Land At Mill Lane, London Road, St Ippolyts, Hitchin, SG4 7NN

I am writing in respect of planning obligations sought towards non-transport services to minimise the impact of development on Hertfordshire County Council Services for the local community. Based on the information to date for the development of 41 dwellings we would seek financial contributions towards the following projects:

HOUSES FLATS A) Open A) Open B) B) Number of Market & Number of Market & Affordable Affordable Bedrooms Shared Bedrooms Shared Rent Rent Ownership Ownership 1 4 0 1 2 1 2 5 4 2 2 1 3 7 7 3 1 0 4+ 6 1 4+ 0 0 Total 22 12 Total 5 2

Trajectory Year 2026 2027 2028 2029 2030 2032 Units 41

1 PLEASE NOTE; If the tenure or mix of dwellings changes, please notify us immediately as this may alter the contributions sought

Primary Education Contribution towards the expansion of St Ipployts Primary School and/or provision serving the development (£416,769 index linked to BCIS 1Q2024 and BCIS Regional Factor)

Secondary Education Contribution towards the expansion of The Priory Secondary School and/or provision serving the development (£435,973 index linked to BCIS 1Q2024 and BCIS Regional Factor)

Childcare Contribution towards increasing the capacity of 0-2 year old childcare facilities at North Herts Rural West Family Centre Reporting Locality and/or provision serving the development (£9,240 index linked to BCIS 1Q2024)

Childcare Contribution towards increasing the capacity of 5-11 year old childcare facilities at St Ippolyts Primary School and/or provision serving the development (£649 index linked to BCIS 1Q2024)

Special Educational Needs and Disabilities (SEND) Contribution towards new Severe Learning Difficulty (SLD) special school places (EAST) and/or provision serving the development (£70,944 index linked to BCIS 1Q2024 and BCIS Regional Factor)

Library Service Contribution towards increasing the capacity of Hitchin Library and/or provision serving the development (£11,011 index linked to BCIS 1Q2024)

Youth Service Contribution towards increasing capacity through resource requirements to support the delivery of youth work with young people in the area and/or provision serving the development (£6,646 index linked to BCIS 1Q2024)

Waste Service: Recycling Centre Contribution towards increasing capacity at Letchworth Recycling Centre or a new recycling centre in Baldock and/or provision serving the development (£7,882 index linked to BCIS 1Q2024) Transfer Station Contribution towards increasing capacity through the new Northern Transfer Station and/or provision serving the development (£11,023 index linked to BCIS 1Q2024)

Fire and Rescue Service Contribution towards increasing capacity through the provision of new appliances and/or equipment necessary to support additional fire and rescue service delivery at Hitchin Fire Station and/or provision serving the development (£1,020 index linked to BCIS 1Q2024)

Monitoring Fees – HCC will charge monitoring fees. These will be based on the number of triggers within each legal agreement with each distinct trigger point

2 attracting a charge of £420 (adjusted for inflation against RPI January 2024). For further information on monitoring fees please see section 5.5 of the Guide to Developer Infrastructure Contributions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/02885/OP HCC Growth & Infrastructure Unit Updated ResponseReport 4 pages DownloadRead as text
PDF
25/02885/OP LAND AT MILL LANE, LONDON ROAD, ST IPPOLYTS, HITCHIN, SG4 7NNReport 32 pages Download
PDF
25/02885/OP Written UpdateReport 2 pages Download
PDF
PlanReport 1 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 25/02885/OP LAND AT MILL LANE, LONDON ROAD, ST IPPOLYTS, HITCHIN, SG4 7NNThis decision
  2. Tpo00226 (2026) land at mill lane (london road end) st ippolyts, sg4 7nnDecided
  3. 23/02948/fp - land north of 2 millers close, picknage road, barley, hertfordshireDecided
  4. 23/00523/op land east of ashmill poultry farm, high street, barkway, hertfordshireRefused
  5. 20/02779/fp land at, windmill close, barkway, hertfordshireApproved
  6. Land at windmill close, barkwayDecided

More from North Hertfordshire Planning Control Committee

All decisions
MeetingDecisionOutcome
1 Oct 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
1 Oct 2026 Minutes - 3 september 2026That the Minutes of the meeting of the Committee held on 3 September 2026 be approved as a true record of the proceed... Approved Open
1 Oct 2026 Notification of other businessThere was no notification of other business. Decided Open
1 Oct 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
1 Oct 2026 Public participationThe Chair confirmed that the registered speakers were in attendance. Decided Open