26/00262/FP LAND AT NEW POUND FARM EAST SIDE OF, OLD HALE WAY, HITCHIN, HERTFORDSHIRE, SG4 0SA
DecidedPlanning2 papers
AI summaryNorth Hertfordshire District Council grants planning permission for one detached dwelling at New Pound Farm, Hitchin, subject to Environment Agency clearance and standard conditions.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedOne detached dwelling, subject to conditions
MoneyNot stated
What happens nextAwait Environment Agency responseConditions to be discharged before development starts
Who it affectsLand at New Pound Farm, HitchinErection of one detached dwelling
What was decided
Planning permission was granted for the erection of one detached dwelling, subject to the receipt of no objection from the Environment Agency and any recommended conditions being added. Report 5.1
The grant is subject to conditions covering time limit, approved plans, materials, ecology, contamination, and landscaping. Report 5.1, P3, P8, P10, P14
Why
The application is for a single dwelling and the report set out conditions to ensure acceptable appearance, ecological protection, contamination safety, and visual amenity. Report P7, P9, P13, P16
No alternative options were considered applicable by officers. Report P1
What happens next
The applicant must submit a Biodiversity Gain Plan and seek approval of reserved details, including materials, landscaping, and a contamination risk assessment, before development begins. Report P6, P10, P14, P20
Development must start within three years of the permission date. Report P3
Options considered
Chosen: Grant planning permission subject to Environment Agency clearance and conditions. Recommended by the Development and Conservation Manager. Report 5.1
Rejected: Alternative options. None applicable. Report P1
Implications
Environment and climate: Ecological measures must be carried out in line with the July 2024 Ecological Impact Assessment, and a Biodiversity Gain Plan is required. Report P8, P20
Risk: A Preliminary Risk Assessment and possible further contamination assessments must be carried out before development starts, following Environment Agency 2023 guidance. Report P10, P11, P12, P13
Who and where
The applicant Report P18
The local planning authority (North Hertfordshire District Council) Report P6, P10, P14
Timeline
3 years from the date of this permission: The development must be begun before this deadline. Report P3
Before the development is commenced: Materials details must be submitted and approved in writing. Report P6
Before the first occupation of the development: Approved hard standing and boundary treatments must be completed. Report P15
First planting season following occupation or completion: Approved soft landscaping must be carried out. Report P16
Plain English for the jargon
Preliminary Risk Assessment: A report documenting the ground conditions of a site in relation to potential contamination.
Biodiversity Gain Plan: A plan submitted for approval showing how a development will achieve required biodiversity net gain.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item73
Resolved
That application 26/00262/FP be GRANTED planning permission subject to: A) The receipt of no objection from the Environment Agency and the addition of any recommended conditions. B) The conditions as set out in the report of the Development and Conservation Manager.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Location: Land At New Pound Farm East Side Of Old Hale Way Hitchin Hertfordshire SG4 0SA
Applicant: [name removed]: Erection of one detached dwelling.
Ref. No: 26/00262/FP
Officer: Thomas Howe
Date of expiry of statutory period:
30 March 2026
Extension of statutory period:
8 October 2026
Reason for Delay:
To overcome planning objections, and to find a suitable committee date.
Reason for Referral to Committee:
Councillor Ian Albert has called the application into planning control committee on 30 March 2026 in agreement with the objections from Ickleford Parish Council. Other reasons include the harm to the openness of the Green Belt and does not overcome concerns raised in the previous application for the same site.
1.0Site History:
1.124/02009/FP - Erection of one detached 2-bed farm workers dwelling. – Refused. Appeal Dismissed (Appeal Ref: APP/X1925/W/25/3362553)
1.224/01920/FP - Altered vehicular access to facilitate the use of land as a community car park together with the installation of new gates and fencing and associated landscaping. - Refused
1.324/00577/FP - Side lean-to pole extension and external steps. Insertion of rear windows and solar panels to existing side roofslope to facilitate additional storage at first floor level. – Conditional Permission
1.422/02694/AG - Single storey side extension to existing agricultural barn – Prior Approval not Required
1.522/02693/AG - Erection of polytunnel – Prior Approval not Required 1.6 20/00617/AG - Agricultural building to store machinery and other such equipment required to farm the land. - Prior Approval not Required
1.721/01962/FP - Retention of new vehicular/pedestrian bridge over the River Hiz and new farm track (retrospective application) – Conditional Permission
2.0Policies:
2.1Decisions must be taken in accordance with the development plan unless there are material considerations that indicate otherwise (section 70(2) of the Town and Country Planning Act 1990 and section 38(6) of the Planning and Compulsory Purchase Act 2004). The National Planning Policy Framework represents up-to-date government planning policy and is a material consideration that must be taken into account where it is relevant to a planning application. If decision takers choose not to follow the National Planning Policy Framework, where it is a material consideration, clear and convincing reasons for doing so are needed.
2.2Section 38(5) of the Planning and Compulsory Purchase Act 2004 sets a hierarchy of development plan documents and material considerations such as the NPPF, in that where a conflict is identified, the conflict must be resolved in favour of the policy which is contained in the last document to be adopted, approved or published.
2.3North Hertfordshire District Local Plan (The Local Plan) 2011 – 2031
Policy SP1: Sustainable Development in North Hertfordshire Policy SP2: Settlement Hierarchy and Spatial Distribution Policy SP5: Countryside and Green Belt Policy SP9: Design and Sustainability Policy HS3: Housing mix Policy D1: Sustainable Design Policy D3: Protecting living conditions Policy D4: Air quality Policy NE2: Landscape Policy NE4: Biodiversity and geological sites Policy NE7: Reducing flood risk Policy NE8: Sustainable drainage systems Policy NE10: Water conservation and wastewater infrastructure
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.