Resolved
That the report be submitted as the response of Lincolnshire County Council (as Sc 4/4 authority) to the East Midlands Regional Assembly’s request for strategic planning advice relating to Central Lincolnshire.
Central Lincolnshire Joint Strategic Planning Committee decided this item on Thursday 14 January 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be submitted as the response of Lincolnshire County Council (as Sc 4/4 authority) to the East Midlands Regional Assembly’s request for strategic planning advice relating to Central Lincolnshire.
1. A letter including the response of this committee to the Regional Plan Partial Review Issues and Options consultation paper was sent to the East Midlands Regional Assembly (EMRA) in October 2009. This was subsequently reported to the inaugural Joint Committee on 20 November 2009. Lincolnshire County Council (as statutory Sc 4/4 authority) also made a response on behalf of the whole county administrative area.
2. The circumstances under which the Partial Review is now being progressed have changed since the Review was launched in early 2009. In particular, there has been increasing concern raised by some local authorities in the region that the Review is premature and unrealistic in promoting additional housing growth in a period of economic and political uncertainty. The continuing slump in house building and the proposed re-modelling of regional governance in 2010 has intensified these doubts.
3. In response to these concerns, EMRA is seeking CLG advice on not proceeding with the housing provision element of the Partial Review, with the exception being Lincolnshire where there remains a need to consider the Gainsborough Growth Point and the implications of the Lincolnshire Coastal Study. At the time of writing, no decision has been made.
4. There are two guiding principles in responding to these unfolding events: managing uncertainty and ensuring the sustainable growth of Central Lincolnshire. There are two possible ways of achieving this.
PROPOSED RESPONSE
Joint Core Strategy
5. The current Regional Plan (March 2009) includes Policy 13a (Regional Housing Provision) which provides a figure for Central Lincolnshire of 40,600 for the period 2006 – 2026. It also says: “Local authorities can test higher numbers through their development plan documents provided that they are consistent with the principles of sustainable development set out in PPS1 and tested through sustainability appraisal.”
1 6. This caveat provides a useful and (quicker) way of meeting the needs of the Gainsborough Growth Point through preparation of the Joint Core Strategy and associated documents. The main advantages are that it:
• Removes reliance on the Partial Review to provide additional housing which can then be decided locally in terms of quantity and location via the JPU and Joint Committee; • Can articulate the regeneration justification for additional housing in Gainsborough more rigorously than a regional document; and, • Allows a more realistic approach to delivery and phasing based on a local understanding of the housing market, infrastructure provision and developer interest
7. Given the overall uncertainty about the future of regional planning and the delay in preparing local development documents, the Joint Committee and Lincolnshire County Council request that the Lincoln Policy Area Sub Regional Strategy be retained in any reviewed Regional Plan, to be replaced by the Joint Core Strategy for Central Lincolnshire when it is adopted. This will ensure that a fully tested statutory spatial strategy is in place during the plan preparation period.
Regional Plan Partial Review
8. The intention of EMRA to progress the housing review of Central Lincolnshire in response to the needs of the Gainsborough Growth Point is welcome but problematic. There is a threat to soundness in proposing new housing figures for a single Housing Market Area (HMA) without a regional housing figure in place (i.e. an absence of context/justification or whether additional housing in Central Lincolnshire is being diverted from other HMAs).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Regional Plan ReviewReport | 20 KB | DownloadRead as text |
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Jul 2026 | Election of Chairman 2026/2027That Councillor Wright be elected Chairman of the Central Lincolnshire Joint Strategic Planning Committee for the mun... | Decided | Open |
| 6 Jul 2026 | Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ... | Decided | Open |
| 6 Jul 2026 | MinutesThat the minutes of the Central Lincolnshire Joint Strategic Planning Committee held on Monday 13 th October 2025 wer... | Approved | Open |
| 6 Jul 2026 | 2025/26 Central Lincolnshire Joint Strategic Planning Committee Annual ReportThat the 2025/26 Annual report was approved as a fair summary of activity of the Central Lincolnshire Joint Strategic... | Approved | Open |
| 6 Jul 2026 | Central Lincolnshire Budget Update ReportThat the Committee noted the outturn for 2025/26 and the current budget forecast for 2026/27-2029/30 including the co... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.