Central Lincolnshire Joint Strategic Planning Committee noted this item on Monday 12 April 2010. Below is the council's own wording, with the papers it was decided on.
That, members of the JSPC note the contents of this report and the current position relating to CIL, be approved. That, members of the JSPC recommend to the Districts and the County Committees to the establishment of appropriate Joint Officer Working Group(s) to report progress back to the JSPC and County and District Committees in June 2010, be approved.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report to Central Lincolnshire Joint Strategic Planning Committee
Committee: Central Lincolnshire Joint Strategic Planning Committee Meeting Date: 12 April 2010 Report presented by: Michael Braithwaite Author: Suzanne Roberts Email: [email protected] Tel: 01522 873419
Report Title: The Community Infrastructure Levy Regulations and Understanding the Implications for the Central Lincolnshire
Purpose of Report To brief members of the Joint Strategic Planning Committee (JSPC) on the publication of the final Community Infrastructure Levy (CIL) regulations and agree a course of action to undertake further analysis of the impact these regulations will have will have on District, County and JSPC functions, management arrangements and infrastructure delivery.
The final CIL Regulations were published in February 2010 and are due to take effect from 06 April 2010 following parliamentary approval. The regulations allow for a transition period of up until 06 April 2014 to introduce a CIL, thereafter the use of section 106 to fund infrastructure will be formally scaled back. An overview of the final CIL regulation is appended to this report.
North Kesteven, West Lindsey and the City of Lincoln jointly responded to the draft regulations last year. Lincolnshire County Council responded individually. The joint response is appended to the report on CIL put before the JSPC on 20 November 2009. This report sought approval to respond to an approach from CLG which asked whether any specific CIL functions should be devolved from the Districts to the JSPC through the drafting of the CIL regulations. It was decided that it was not an appropriate time to do this and the JSPC resolved to:
1. Note the benefits and risks of taking on the CIL function of preparing and reviewing the Charging Schedule following the introduction of the CIL Regulations; 2. Agree that each Partner Authority be asked to agree that JSPC lead on the discussions and negotiations on the introduction of CIL; 3. Agree that each Partner should consider the benefits of the production of a Joint Charging Schedule undertaken by the JSPC.
Now that the final regulations have been published it is necessary to develop the understanding of the CIL, its implications for the JSPC and the Partner Authorities and progress specific evidence and appropriate instruments in order to work towards the potential introduction of CIL in parallel with the preparation of the Joint Core Strategy and Infrastructure Delivery Plan.
It is suggested that specific detailed investigation now needs to be undertaken with the involvement of a number of affected departments across the four Authorities to understand the benefits, risks and opportunities associated with introducing a CIL charge or charges in Central Lincolnshire. It is suggested that this work could be broken down into three areas:
1.Transfer of CIL functions and the Scope of the Charging Schedule: Exactly what functions can be legally transferred to the JSPC needs to be fully understood together with the appropriate mechanisms for undertaking any transfer. For example the JSPC could take on the role of setting the CIL (through the Charging Schedule) and overseeing spending but collection would need to remain with the Districts through the direct link with the grant of planning permission. The benefits, risks and opportunities associated with transfer of each function and the scope of the Charging Schedule, and its relationship with the IDP, will need to be considered in terms of the implications for the Districts, the Joint Planning Unit and Committee and the County Council.
This would require an Officer working group represented by all partner authorities and include expertise in planning policy, law and existing section 106 collection and management systems. Any decisions will have huge implications for the management and spending of funds on key infrastructure in Central Lincolnshire.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.