Agreed that an exception be made to the requirements of the Council’s Contract Procedures and Constitutional arrangements on the use of Procurement Lincolnshire services for contract over the value of £75,000 in relation to the tendering of painting, pre-paint, car parking improvements and health and safety improvements and agreed that the District Council undertake the tendering process for these works in 2010/11; Agreed that a contract be established with the Council’s existing contract with Service Master for undertaking void works to the Council’s properties for the remainder of the financial year.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
To seek approval from the Executive Board to tender key contracts in 2010/11 outside of the Lincolnshire Procurement processes.
Summary
The Council’s key housing maintenance contracts of both capital and void works terminated at the end of March 2010. For some time the Council has been working with Lincolnshire Procurement to establish a new countywide framework for housing maintenance contracts. The principle behind this work has been that all stock holding Authorities will be able to use the framework to procure contractors for improvements to housing stock.
The first key stage of this work is to establish frameworks of three contractors for each of the main types of work e.g. painting, kitchens, roofing, windows, heating etc. Once these three contractors are in place, each local authority will then tender for programmes of work.
The current timescale for undertaking this work is:
• 30 June - Completion of first stage tenders • July – Analysis of tenders • August – Setting up framework contracts • September onwards – frameworks available for tendering individual programmes of work
This timescale has only recently been made available to the Council. It causes a number of specific problems in that the Council would be unable to procure contractors for completion of works before, at the very earliest, September this year. The specific concerns are as follows:
• Painting Work – It would be pointless for the Council to initiate a painting programme from September as this would be the very end of the painting season. This includes pre-paint (preparation work) and even if provided earlier the Council would be unable to spend the entire budget. • Voids Work – The Council is currently continuing with the previous voids contractor without having a formal agreement in place. There is a need to formalise this. • Car Parking Improvements – There is an urgent need to develop some programmes of work particularly linked to development of new properties on Council sites. • Health and Safety Work – Fire risk assessments undertaken earlier in the year identified the need for urgent work to some properties which Lincolnshire Procurement are not currently looking to tender for the Council.
Taking into account these concerns, it is recommended that the Council develops solutions to these problems outside of the Lincolnshire Procurement framework.
Recommendations 1. That the Council undertake tendering of painting, pre-paint, car parking improvements and health and safety improvements outside of Lincolnshire Procurement and that an exception be made to the requirements of the Constitution on the use of Lincolnshire Procurement for contracts in excess of £75,000. 2. That a contract be established with the Council’s existing contract with Service Master for undertaking void works to the Council’s properties for the remainder of the financial year. IMPLICATIONS Relationship to Community Strategy Quality of Housing Services links to the community wellbeing theme. Achievement of the decent homes standard and the quality of accommodation refers to the managing change theme.
Customer Impacts The delay in tendering housing maintenance works would impact on the quality of services provided to customers. The recommendations are intended to mitigate these impacts.
Financial Impacts The budgets for the work involved in 2010/11 are as follows: • Painting - £123,600 • Pre-painting - £61,800 • Car Parking - £225,000 • Fire Risk - £240,000 • Voids - £192,000
Impact on Performance and data quality The recommendations are intended to improve performance against current plans for procuring capital works.
Human Resources No implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.