Project Plan for Central Lincolnshire Core Strategy

Decided Planning 2 papers

Central Lincolnshire Joint Strategic Planning Committee decided this item on Monday 19 July 2010. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

That the approach to project management as outlined in the report be supported and the endorsed the proposed milestones and target dates for the component projects of the Central Lincolnshire Core Strategy as set out in Appendix 1.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Central Lincolnshire Joint Strategic Planning Committee, 6 pages

Purpose of report

To advise the Committee of project planning work undertaken for the Central Lincolnshire Joint Core Strategy, and to seek endorsement of the key milestones and targets proposed.

At its meeting on June 14th, the Committee approved a revised Local Development Scheme (LDS) that prioritised the Core Strategy as the first document for preparation by the Joint Planning Unit (JPU).

The LDS sets out a broad timetable for the Core Strategy, and identifies the target dates for the main stages in its preparation from preliminary stakeholder engagement to final adoption, including the number and timing of public consultations.

Project management is critical for delivery of this Core Strategy timetable, enabling the JPU’s staff and time resources to be used effectively and efficiently. It also allows progress in preparing the Core Strategy to be monitored and reported. Current national guidance on LDFs also makes it clear that effective project management is essential to ensure timely delivery and procedural soundness of LDF documents.

Based on training provided recently to JPU staff by the Planning Advisory Service (PAS), the following main elements of project management are proposed for the Core Strategy (and other LDF documents subsequently):

1. Definition of roles within project, including project sponsor, project manager and task manager 2. Definition of the overall project aims and objectives 3. Identification of component projects or sub-projects 4. Timetabling and tasking for sub-projects 5. Resource planning and risk analysis 6. Project closure and review

Work has been largely completed on Elements 1 – 3 in relation to the Core Strategy. Element 4 has also been undertaken for the first stage of the Core Strategy, covering the period up to and including the Issues & Options consultation timetabled for the Autumn. A summary of the proposed sub-projects is set out in Appendix 1, including the scope, objectives and lead officers for each sub-project, together with key milestones and committee for the period up to Issues & Options. The full project planning work is available in the JPU office.

Clearly, detailed timetabling and tasking will need to be rolled forward to subsequent stages of Core Strategy preparation in due course, but is not undertaken yet due to the level of uncertainty and consequent danger of abortive work. Further sub-projects will be added as Core Strategy preparation progresses Recommendations

1. That the Committee supports the approach to project management outlined in this report, and endorses the proposed milestones and target dates for the component projects of the Central Lincolnshire Core Strategy as set out in Appendix 1.

IMPLICATIONS Relationship to Community Strategy Opportunities for aligning the timetables and processes of the Core Strategy and Community Strategy are being investigated as part of the project planning work. In particular, there may be opportunities to align or combine consultation events. This is currently under discussion between JPU staff and LSP co-ordinators for the partner authorities.

Financial Impacts Project management aims to optimise the use of available resources, and ensure that they are used efficiently and effectively. It should therefore reduce the overall cost of preparing the Core Strategy and other LDF documents.

Impact on Performance The project plan aims to enhance performance by ensuring that staff and other resources are marshalled to ensure effective and efficient delivery. It should minimise risks associated with a lack of project management, such as poor project delivery, poorly defined roles, and vague objectives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Core Strategy Project: Appendix 1Appendix 3 pages Download
PDF
Project Plan for Central Lincolnshire Core StrategyReport 6 pages DownloadRead as text

At this meeting

Whole meeting

More from North Kesteven Central Lincolnshire Joint Strategic Planning Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 Election of Chairman 2026/2027That Councillor Wright be elected Chairman of the Central Lincolnshire Joint Strategic Planning Committee for the mun... Decided Open
6 Jul 2026 Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ... Decided Open
6 Jul 2026 MinutesThat the minutes of the Central Lincolnshire Joint Strategic Planning Committee held on Monday 13 th October 2025 wer... Approved Open
6 Jul 2026 2025/26 Central Lincolnshire Joint Strategic Planning Committee Annual ReportThat the 2025/26 Annual report was approved as a fair summary of activity of the Central Lincolnshire Joint Strategic... Approved Open
6 Jul 2026 Central Lincolnshire Budget Update ReportThat the Committee noted the outturn for 2025/26 and the current budget forecast for 2026/27-2029/30 including the co... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies