Recommend to Council 1. That, in principle the existing Sleaford Leisure Centre be replaced with a new facility based upon option 4 in the feasibility study, subject to adequate external grants being approved. 2. That a further report be submitted to the Executive Board, and Council, once the external funding opportunities have been resolved.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Committee: Executive Board Meeting Date: 4th November 2010 Report presented by: Deputy Chief Executive Author: Alan Thomas Email: [email protected] Tel: 01529 308301 Report Title: Proposal to Redevelop Sleaford Leisure Centre 1. Introduction In January 2009 the Board approved the development of a feasibility study for replacing the existing facilities at the Sleaford Leisure Centre, based upon a joint initiative with Lincolnshire County Council.
Various options have been explored since that date, the main one being the development of a joint facility with Lincolnshire County Council and the Primary Care Trust (PCT) on land owned by the County Council adjacent to the District Council offices. A great deal of time and effort went into developing this option but, unfortunately, this initiative has now stalled due to funding difficulties experienced by the PCT and also the fact that a grant of £600,000 provisionally allocated to this Council was recently withdrawn.
Officers have therefore concentrated on three main options for redeveloping the Leisure Centre. The first option is to rebuild a new facility on the existing site. The second option is to develop a facility in conjunction with Lincolnshire County Council on its’ land adjacent to the District Council offices. This latter option would be a significantly smaller project compared with the previous joint initiative including the PCT. The third option would be to work with the current owner of the Harpers Fitness Station in East Road to develop a new Leisure Centre on that site.
Feasibility Studies have been commissioned for two of the above options and the remainder of this report sets out the findings from those studies and discusses the issues and options around the development of a new Leisure Centre.
This report concludes that a new leisure facility for Sleaford should be developed on the site of the existing Leisure Centre, subject to external funding being available for the project.
2. The need for a new Leisure Centre in Sleaford The Council first developed swimming facilities on the existing site as an outdoor lido in 1872. In 1980 the main pool was reconstructed by building within the original pool shell and then in 1981, a single storey building was constructed to enclose the pool. Additional land to the south and east of the pool was acquired by the Council and some of this land has been leased to the Sleaford and District Indoor Bowls Club for a period of 60 years. In 1984 two single storey extensions were constructed to provide a small fitness gym and health suite.
In October 2007 the Council undertook a survey of 3,000 households regarding “Swimming in Sleaford”. Those who were surveyed were asked to comment upon their use of the existing Leisure Centre, options for the future and their views on refurbishment or replacement.
The main findings from the survey were as follows:-
• 35.5% of users would not be prepared to travel more than 2 miles to use a swimming pool. • 72.2% would travel to the facilities by car and 31.5% would walk. • 33.8% would prefer a 25m swimming pool with a shallow teaching/learner pool. • 49.6% of those surveyed preferred a new pool on the existing Leisure Centre site. The existing Sleaford Leisure Centre has reached a stage in its life where it is difficult to meet customer standards and expectations. There is a significant amount of repair and maintenance that is required to the Leisure Centre but this work, amounting to over £360,000, has not been undertaken pending a decision on replacing the existing facilities.
The repair and maintenance costs are expected to escalate in future years as the existing facility deteriorates further. It is estimated that over £1.25million will need to be spent on repair and maintenance to existing facilities over the next 10 years.
3. Options available to develop a new Leisure Centre
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.