It was agreed that a progress report on this action would be brought to a future meeting in July 2011. The Panel noted there had been achievements with some actions reported as being on target or ahead of target. However the report only detailed those actions where the target was not being met. It was agreed that for future update reports, the actions reported on target or ahead of target would also be included. CONCLUSIONS: 1. The Panel noted the report. 2. Action 1.2.2 - improve and develop safer cycle routes throughout the District should be reviewed. 3. That a progress report on the transfer of the national bus pass scheme to Lincolnshire County Council be brought to the Scrutiny Panel in July 2011.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report to Development and Information Overview and Scrutiny Panel, 6 pages
Panel: Development and Information Overview and Scrutiny Panel Meeting Date: Monday 8th November 2010 Author: Luisa McIntosh Email: [email protected] Contact No: 01529 308196 (ext 2696) Report Title: Corporate Priorities Progress Report
Purpose of Report To provide the panel with half yearly update reports on the Better Connections, Managing Change and Vibrant Economy corporate priorities.
Summary In 2008 the District Council and the Local Strategic Partnership (LSP) aligned their priorities. Since that time the LSP has had responsibility of writing – with support from the Corporate Management Team – monitoring and reporting on all five Priority Development Plans (PDP) for each of the priorities. These PDPs detail actions that will be carried out over the course of the year, the lead officer or partner responsible for the action, an indicator (where possible), the target, and a column for recording progress. Progress on actions within each PDP is provided quarterly by the person responsible for the action. An overview of this progress is provided below:
Better Connections The Better Connections priority focuses on key challenges which are: − Challenge one: Wherever possible, reduce the need for residents to travel within or outside of the District. − Challenge two: To improve the choice of transport facilities for residents and visitors within the District − Challenge three: To provide more cost effective means of travelling around the District. − Challenge four: To ease the congestion caused by increased travellers within the District and reduce the number of speeding motorists. − Challenge five: Develop digital connectivity, improve access to services and to reduce digital exclusion
At the half year point, all actions have been recorded as being on target, ahead of target or are reported annually. This is except for the following which have been marked with a star which equates to the action being behind target, but with no additional action required, or a black star which means the action is behind target and remedial action is required:
Challenge One:
Action 1.2.2: Improve and develop safer cycle routes throughout the District - increase the number/ length of cycle routes available in the District. This target needs to be reviewed as there is no funding available for this action.
Action 1.2.4: Ensure that adequate walkways/ footways exist between towns and villages – increase the length of footpaths. Again, this target needs to be reviewed as there is no funding available. Action 1.2.7: Investigate options and funding to develop a Bike IT programme for North Kesteven. Work will be starting imminently on this action.
Action 1.3.2: Develop more outreach operations - increase the opportunity for wider service provision by visiting officers. No update provided – this will follow.
Challenge Two:
Action 2.1.4: Continued development of the Better Transport Forum – hold two meetings per year. This action is behind target as the priorities consultation took precedence over the event that was scheduled for September. Following the outcome of the priorities consultation, it is likely that this target will need to be reviewed.
Action 2.1.9: Undertake improvements at the Metheringham Station to develop a transport interchange between the buses and trains. Progress is now being made and we hope to be back on target in the next few months.
Challenge Three:
Action 3.2.1: Review advertising campaigns informing residents of the National Free Bus pass and travel tokens schemes. The administration of the National Bus Pass service is to transfer from District Council to Lincolnshire County Council from April 2011. Work towards the transfer has commenced. The future position regarding travel tokens from April 2011 is under review and subject to a report to a forthcoming Executive Board.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development and Information Overview and Scrutiny Panel at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
Decentralisation and Localism Bill· That the Panel noted the emerging content of the Localism Bill; · That the Panel noted the emerging action plans an...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.