That the work programme for completing the impact of the Habitats Regulation Assessment on the Core Strategy be agreed; That progress on the Habitats Regulation Assessment, which will form part of the evidence base for the Local Development Framework, be noted; and That the decision on the Scoping report be delegated to the Chairman and Vice Chairman of the Joint Planning Committee to allow continual progress on the production of the Core Strategy
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report to Central Lincolnshire Joint Strategic Planning Committee
Committee: Central Lincolnshire Joint Strategic Planning Committee Meeting Date: 6 June 2011 Report presented by: Michael Braithwaite Author: Charlotte Robinson Email: [email protected] Contact No: 01522 873816 Report Title: Habitats Regulation Assessment
Purpose of Report To inform the Joint Strategic Planning Committee on progress on the Habitats Regulation Assessment of the Central Lincolnshire Core Strategy.
Summary Introduction The purpose of a Habitats Regulation Assessment (HRA) of the Central Lincolnshire Core Strategy is to ensure protection of the integrity of European sites as part of the planning process. The requirement for HRA is outlined in Article 6 (3) and (4) of European Habitats Directive (92/43/EEC; ‘Habitats Directive’) which provides legal protection for habitats and species of European importance. The Habitats Directive provides the legislative means to protect habitats and species through the establishment and conservation of a network of sites of nature conservation importance known as the Natura 2000 network. The term ‘Habitats Regulation Assessment’ is frequently used to encompass the decision making process as to whether the Plan should be subject to appraisal, the screening process for determining whether an ‘Appropriate Assessment’ is required, as well as any Appropriate Assessment that may be required. An Appropriate Assessment is only required where the plan-making body determines that the plan is likely to have a significant effect on a European site, either alone or in combination with other plans or projects.
What are Natura 2000 network of sites? The HRA refers to the assessment of the potential effects of a development plan on one or more European Sites (collectively termed ‘Natura 2000’ sites). The Natura 2000 is a Europe- wide network of sites of international importance for nature conservation established under the Habitats Directive. The network comprises Special Protection Areas (SPAs) for birds and Special Areas of Conservation (SACs) for habitats and species. The Government also expects candidate SACs (cSACs), potential SPAs (pSPAs), and Ramsar sites (wetland sites) to be included within the HRA.
Stages of the Habitats Regulation Assessment HRA should conclude whether or not a proposal or policy in a development plan is likely to adversely affect the integrity of the Natura 2000 Site in question. In line with the Amended Habitats Regulations and current guidance documents on HRA, the HRA process is made up of four main stages:
Stage 1: Evidence Gathering for HRA
Stage 2: Screening for likely significant effects Stage 3: Appropriate Assessment (only required if a policy or policies is found to have significant effects on a European site);
Stage 4: Mitigation measures and alternative solutions.
Links with Strategic Environmental Assessment (SEA) and Sustainability Appraisal (SA) SEA involves the identification and evaluation of impacts of a plan or programme on the environment. SA broadens SEA to also address economic and social impacts, therefore covering the three dimensions of sustainable development. SEA and SA is required for the Core Strategy under the SEA Directive and Planning and Compulsory Purchase Act 2004.
There are clear parallels with HRA, SEA and SA as all three are processes for assessing and minimising the impacts of plans. However, Government guidance on HRA recommends that although HRA can be undertaken alongside SEA/SA, the outputs need to be clearly distinguishable and so reported in separately.
Progress on the Core Strategy HRA The Joint Planning Unit and Natural Englandagreed a project plan and proposed methodology for the HRA in March 2011. The methodology proposed a ‘long list’ of European sites which could potentially be affected by the Core Strategy. Comments on the project plan and methodology were sought from Natural England, the statutory nature conservation body for HRA, including approval of the final list of European sites to be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.