Executive Board, Thursday 28 July 2011 at 2.00pm

Financial Monitoring Report for Quarter 1

Approved Executive 7 papers

Executive Board approved this item on Thursday 28 July 2011. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

Approved the transfer of the New Home Bonus grant to the New Homes Bonus Reserve; 2. Approved the transfer of £100,000 from the Planning Delivery Grant reserve to the Regeneration Reserve. 3. Noted the progress made on the Savings Action Plan; 4. Noted the financial position.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board, 3 pages

CAPITAL EXPENDITURE MONITORING STATEMENT 2011-12

Budget Carried Total Profiled to Quarter Actual Projected Outturn Scheme NKDC External Forward Approved 1 2 3 4 To date % Total Funding 2011/12 Budget Spent £ £ £ £ £ £ £ £ £ £

Housing Stock 5,295,300 549,800 429,300 6,274,400 581,350 2,267,700 4,492,225 6,274,400 790,161 13% 6,274,400 Housing General Fund 250,000 264,000 44,600 558,600 139,650 279,300 418,950 558,600 160,893 29% 558,600

General Fund 1,021,900 0 846,800 1,868,700 472,568 648,535 824,503 1,868,700 385,303 21% 1,868,700 Fees (non Housing) 88,800 0 88,800 22,200 44,400 66,600 88,800 27,327 31% 88,800

GRAND TOTALS 6,656,000 813,800 1,320,700 8,790,500 1,215,768 3,239,935 5,802,278 8,790,500 1,363,684 16% 8,790,500 14% 37% 66% 100%

Housing Stock

New Build 1

Hillside Estate, Ruskington 0 0 1,600 1,600 0 800 1,200 1,600 (2,608) (4,208) 1,600 West Grove, Martin (Straw) 0 0 63,800 63,800 15,950 31,900 47,850 63,800 43,843 (19,957) 63,800 Elizabeth Ave, North Hykeham 0 0 1,700 1,700 0 850 1,275 1,700 (12,317) (14,017) 1,700 Cumberland Ave, Wellingore 0 0 300 300 0 150 225 300 (4,395) (4,695) 300 Grayson Green, Wellingore 0 0 900 900 0 450 675 900 (3,297) (4,197) 900 Hoplands, Kirkby La Thorpe, Sleaford 0 0 700 700 0 350 525 700 (18,542) (19,242) 700 Brumby Crescent, Waddington (Straw) 0 0 0 0 0 0 0 0 (7,437) (7,437) 0 New Build 2 Archer Road, Branston 356,300 0 0 356,300 89,075 178,150 267,225 356,300 147,173 (209,127) 356,300 Eslaforde, Sleaford 549,000 0 0 549,000 137,250 274,500 411,750 549,000 171,341 (377,659) 549,000 Pinfold Lane, Ruskington 450,000 0 0 450,000 112,500 225,000 337,500 450,000 205,701 (244,299) 450,000 New Build (challenge fund) 0 0 0 0 4,379 4,379 0 New Build 3 Pound Road 549,900 549,800 1,099,700 0 549,850 824,775 1,099,700 (2,235) (1,101,935) 1,099,700 Total New Build 1,905,200 549,800 69,000 2,524,000 354,775 1,262,000 1,893,000 2,524,000 521,606 (2,002,394) 2,524,000

Engineering 40,000 0 3,000 43,000 0 0 20,000 43,000 (340) (43,340) 43,000 Disabled Adaptations 300,000 0 300,000 28,000 125,000 210,000 300,000 35,457 (264,543) 300,000 Other Works (Canopies, Chimney Stacks etc) 100,000 0 4,700 104,700 0 20,000 70,000 104,700 265 (104,435) 104,700 Replacement Windows/Doors 500,000 0 4,500 504,500 2,000 50,000 300,000 504,500 2,328 (502,172) 504,500 Energy Conservation 300,000 0 79,600 379,600 32,000 100,000 300,000 379,600 31,984 (347,616) 259,600 Roofing 80,000 0 6,600 86,600 18,000 35,000 86,600 86,600 18,935 (67,665) 86,600 Compensation Payments 10,000 0 0 10,000 2,500 5,000 7,500 10,000 406 (9,594) 10,000 Kitchens and Bathrooms 400,000 0 96,100 496,100 5,000 100,000 300,000 496,100 4,831 (491,269) 496,100 Heating 700,000 0 0 700,000 13,000 150,000 500,000 700,000 35,739 (664,261) 700,000 Estate Improvements 170,000 0 44,000 214,000 0 40,000 125,000 214,000 3,339 (210,661) 214,000 Off Street Parking 225,000 0 39,100 264,100 9,000 75,000 200,000 264,100 10,201 (253,899) 264,100 Sheltered schemes-DDA & Fire Risk 100,000 0 10,600 110,600 5,000 32,650 75,000 110,600 5,331 (105,269) 110,600 Non Sheltered Schemes-DDA & Fire Risk 0 0 48,900 48,900 0 48,900 48,900 48,900 15,195 (33,705) 48,900 Carbon Monoxide Testing 40,000 0 0 40,000 0 0 20,000 40,000 0 (40,000) 40,000 Land at archer road 0 0 0 0 0 0 0 0 0 0 0 Smoke alarms 0 0 0 0 0 0 0 0 0 0 120,000 Fees 425,100 23,200 448,300 112,075 224,150 336,225 448,300 104,884 (343,416) 448,300

Housing Stock 3,390,100 0 360,300 3,750,400 226,575 1,005,700 2,599,225 3,750,400 268,555 (3,481,845) 3,750,400 CAPITAL EXPENDITURE MONITORING STATEMENT 2011-12

Budget Carried Total Profiled to Quarter Actual Projected Outturn Scheme NKDC External Forward Approved 1 2 3 4 To date % Total Funding 2011/12 Budget Spent £ £ £ £ £ £ £ £ £ £ 6% 27% 69% 100%

Housing General Fund

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4Report 3 pages DownloadRead as text
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 2 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 5Appendix 5 8 pages Download
PDF
Financial Monitoring Report for Quarter 1Report 3 pages Download
PDF
Quarter 1 ReportReport 5 pages Download

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Financial Monitoring Report for Quarter 1This decision
  2. Financial Monitoring - Q2 ReviewNoted
  3. Financial Services Monitoring - Quarter 3 ReviewNoted
  4. Financial Monitoring - 2nd QuarterRefused
  5. Financial Services Monitoring - Quarter 1 UpdateNoted

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies