Resolved
That the draft budget for the Joint Planning Unit be approved 2. That the need to review working arrangements beyond the current financial year be noted.
Central Lincolnshire Joint Strategic Planning Committee approved this item on Monday 2 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That the draft budget for the Joint Planning Unit be approved 2. That the need to review working arrangements beyond the current financial year be noted.
Committee: Central Lincolnshire Joint Strategic Planning Committee Meeting Date: 2nd April 2012 Report presented by: Head of the Joint Planning Unit Author: Head of the Joint Planning Unit Email: [email protected] Tel: 01529 308043
Report Title: Budget Update – April 2012 Purpose of Report To update Members on the budget position for the Joint Planning Unit and advise each authority of the requested contribution for the next financial year.
Introduction
After the creation of the Joint Planning Unit on the 1st May 2010 each of the partner authorities was asked for a contribution towards the running cost of the Unit. A figure was proposed for the following two years, based on the workload set out in the Local Development Scheme.
The contributions proposed at that time were.
Year 1 Year 2 Year 3
City of Lincoln 89,400 115,700 171,400
North Kesteven 89,400 115,700 171,400
West Lindsey 89,400 115,700 171,400
Lincolnshire CC 47,500 61,200 90,700
These sums were to be added to the available grants to support the work of the Joint Committee, The grants, as reported to the committee in April 2011 are as follows:
Lincoln Policy Area Growth Fund £504,000 Eco Towns Funding £375,000 Housing and Planning Delivery £100,000 Grant (Joint Working Supplement) RIEP £80,000
The original request was based on the full years operation of the unit and the full estimated running costs for the team and to pay for the various work, whether this was publication and consultation or gathering the evidence required to form a foundation and justification for new policies.
The funding arrangements for Councils have changed dramatically with the development of the recession and the changes to overall public funding. The most significant effect of this change is the reduction in the Eco Towns Grant by 50% from £750,000 to £375,000. On the positive side the maximum available RIEP funding has been increased to £80,000 All the second tier authorities have confirmed that they will continue to contribute at the level proposed in April 2010. The County Council has confirmed its commitment, as revised in 2011,topay £47,500 for each of the first three years, No facility was built into the budget for the hosting of the Joint Committee meetings as each partner makes arrangements for a quarter of the meetings. Also the support costs for accommodating the team, including Human resources, IT support and costs for office space have been absorbed by the partner authorities.
As agreed by the Joint Committee in September 2011 the Joint Unit is now accommodated at City Hall, Lincoln. Three members of staff who would be adversely affected by the move still work out of the District Council offices in Sleaford as a transitional arrangement. RIEP funding is being used to pay for the office move.
Budget for 2011/12
Budget Headings 2011/12 Budget 2011/12 Projected Outturns Running Costs (Staff. 553,500 499,900 etc) Project Costs 437,200 312,200 Income Partner Contributions (394,600) (394,600) Eco Towns Grant (327,700) (332,000) RIEP (25,000) (25,000) Growth Fund (246,000) (60,500)
This delivers a balanced budget for the year 2011/12, taking into account the level of progress on production of the Core Strategy and staff vacancies. The Eco Towns Grants and RIEP funding will in effect be exhausted, but Growth Point Funding remains for use in future years.
Projected Budget for 2012/13 . Budget Headings Running Costs (Staff, etc) 568,100 Project Costs 178,500 Income Partner Contributions (561,700) Growth Fund (184,900)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget AppendixAppendix | 14 KB | Download |
PDF |
Budget Update: April 2012Report | 77 KB | DownloadRead as text |
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Jul 2026 | Election of Chairman 2026/2027That Councillor Wright be elected Chairman of the Central Lincolnshire Joint Strategic Planning Committee for the mun... | Decided | Open |
| 6 Jul 2026 | Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ... | Decided | Open |
| 6 Jul 2026 | MinutesThat the minutes of the Central Lincolnshire Joint Strategic Planning Committee held on Monday 13 th October 2025 wer... | Approved | Open |
| 6 Jul 2026 | 2025/26 Central Lincolnshire Joint Strategic Planning Committee Annual ReportThat the 2025/26 Annual report was approved as a fair summary of activity of the Central Lincolnshire Joint Strategic... | Approved | Open |
| 6 Jul 2026 | Central Lincolnshire Budget Update ReportThat the Committee noted the outturn for 2025/26 and the current budget forecast for 2026/27-2029/30 including the co... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.