Resolved
Approved support for the submitted planning and conservation area consent applications for Phase 1 of the East-West Link as progress towards the delivery of the strategic transport objectives set out in the Transport Strategy for Lincoln.
Executive Board approved this item on Thursday 12 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Approved support for the submitted planning and conservation area consent applications for Phase 1 of the East-West Link as progress towards the delivery of the strategic transport objectives set out in the Transport Strategy for Lincoln.
To advise Executive Board on the progress of the East-West Link proposals in Lincoln and the status of the planning and conservation area consent applications have now been lodged with the County Council for determination.
• In 2004 a Transport Strategy for Lincoln (the LTS) was produced and adopted by the 4 partnering authorities (LCC, NKDC, WLDC and CoL). This document set out the future of the transport requirements for the Greater Lincoln Area in order to achieve a sustainable planned economic growth of the City and its environs. This strategy was adopted by the partners in 2008. • The East-West Link is one of the key schemes identified in the LTS, the others being the Lincoln Eastern Bypass and the provision of a Park and Ride service. • It is intended that the Link be provided in 3 Phases; the first phase being of greatest urgency due to the planned increased closure times of the High Street level crossing by Network Rail from 2014 (from some 20 to 40 minutes every hour). This Phase is the section from Lincoln High Street to Pelham Bridge with completion anticipated during 2014. • Planning and Conservation Area Consent applications have now been submitted to the County Council for assessment and determination of the Phase 1 works (Conservation Area Consent being required due to the demolition of the building at the corner of Tentercroft Street/High Street). • The estimated cost of Phase 1 is £22.7 million. This includes the road, the new building, a scheme for the pedestrianised High Street and other highway works that need to be carried out to help ease traffic congestion alongside the East-West Link.
1. That Members note the progress of the scheme and offer support to the submitted planning and conservation area consent applications for Phase 1 of the East-West Link as progress towards the delivery of the strategic transport objectives set out in the LTS. IMPLICATIONS Relationship to Community Strategy None
Customer Impacts None
Financial Impacts None
Impact on Performance and data quality None
Human Resources Representation at Steering Group Meetings
Sustainability Impact Assessment N/A
Equality Impact Assessment N/A
Value for Money N/A
Risk Management N/A
Legal Considerations None
Ethics and Probity N/A
Communications Press Notice to indicate support REASON FOR RECOMMENDATION
To agree the response of NKDC to the County Council on the submitted planning and conservation area consent applications.
OTHER OPTIONS CONSIDERED
None
APPENDIX NO. TITLE
None N/A
BACKGROUND PAPERS The following background papers within Section 100D of the Local Government Act 1972 were used in the preparation of this report but if none were used then please state Title Location of Background Papers
A Transport Strategy for the Lincoln Area Development Management (Revision 1) – February 2008
The Lincoln East West Link Road, Phase Development Management One Consultation Report – October 2010
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Briefing Note on East-West LinkReport | 85 KB | DownloadRead as text |
Follow Executive Board at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... | Approved | Open |
| 3 Nov 2026 | Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... | Noted | Open |
| 3 Nov 2026 | NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... | Approved | Open |
| 3 Nov 2026 | Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... | Approved | Open |
| 3 Nov 2026 | Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.