Resolved
Approved the minutes of the meeting held on 3 May 2012. : The minutes of the meeting held on 3 May 2012 were approved as a correct record. Actions: All to note
Executive Board approved this item on Thursday 14 June 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Approved the minutes of the meeting held on 3 May 2012. : The minutes of the meeting held on 3 May 2012 were approved as a correct record. Actions: All to note
NORTH KESTEVEN DISTRICT COUNCIL
MINUTES of the meeting of Executive Board held in the Council Chamber - Council Offices, Kesteven Street on Thursday, 3 May 2012 (2.00 - 3.05 pm).
PRESENT: Councillor M D Gallagher Councillor Mrs S D Waring Councillor G Hazelwood Councillor R A Wright Councillor S D Ogden
OTHER MEMBERS IN ATTENDANCE:
Councillor J Cook
OFFICERS IN ATTENDANCE:
Ian Fytche Chief Executive Alan Thomas Deputy Chief Executive Karen Bradford Corporate Director Lindsay Tomlinson Senior Democratic Services Officer
188 APOLOGIES FOR ABSENCE
An apology was received from the Chairman, Councillor Mrs Brighton. Councillor Gallagher chaired the meeting in her absence.
189 DECLARATIONS OF INTEREST (IF ANY)
There were no declarations.
190 MINUTES
The minutes of the meeting held on 12 April 2012 were approved as a correct record.
191 FORWARD PLAN
The Board received the Forward Plan for the period 1 June to 30 September 2012.
Vote: Unanimous
RESOLVED: That the Forward Plan for the period covering 1 June to 30 September 2012 be approved.
192 SLEAFORD SWIMMING POOL REDEVELOPMENT
Following approval of the Feasibility Study for the redevelopment of Sleaford Swimming Pool in November 2011 a range of consultation events and surveys had been undertaken during February 2012.
Significant support had been shown for maintaining a sauna/steam room and a new Toddler Splash Zone. With regard to the changing facilities there had been a strong feeling from users that the plans should retain some element of same-gender changing. The proposed additional studio had now been removed from the design; however it was proposed to relocate the existing studio and increase the size of it. The amended design allowed for the extension of the fitness suite. The amended Stage C report incorporated these preferences into the proposals.
The additional cost for the amended proposals was estimated at £200,000 taking the project budget from £2.65 million to £2.85 million. In order to cover the additional costs a number of additional funding options were being pursued. Any shortfall in the funding options would need to be met from borrowing which could require up to an additional £17,000 per year to be funded from the Council’s General Fund.
As a result of the consultation responses around the closure of the swimming pool the project timescales had been revised with the construction phase being reduced to 11 months from the initial 12 months proposed. The revised programme had brought forward the proposed pool’s closure to 8 October with the opening of the new facilities scheduled for September 2013.
A review of all equipment and fixtures was due to be carried out in April /May 2012 to determine what would be fit for transfer to the new facility and what would need to be replaced.
Members discussed the amendments to the proposals and asked some technical questions about the build process. Members were keen to stress the positive nature of the consultation process and suggested that further consultations should be undertaken throughout the build process and after completion.
Vote: Unanimous
RESOLVED: 1. To note project progress and feedback from the consultation process. 2. That the Stage C proposals be approved 3. That the revised budget of £2.85 million be approved and any shortfall in funding be met from borrowing. 4. That consultation continues throughout the process and that a thorough consultation with users will be undertaken 6 months after completion of the project.
193 NORTH KESTEVEN NATIONAL PORTFOLIO ORGANISATION
Following the merger in 2010 of the Council’s arts organisations to form the North Kesteven National Portfolio Consortium, the consortium had applied to become one of the new National Portfolio Organisations for Arts Council England. The application had been successful but was conditional on the agreement of a satisfactory business plan with programme of activity, key priorities and key performance indicators.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 42 KB | DownloadRead as text |
Follow Executive Board at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... | Approved | Open |
| 3 Nov 2026 | Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... | Noted | Open |
| 3 Nov 2026 | NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... | Approved | Open |
| 3 Nov 2026 | Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... | Approved | Open |
| 3 Nov 2026 | Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.