Procurement Lincolnshire TFG Report

Approved Scrutiny 1 paper

Performance & Resources Overview and Scrutiny Panel approved this item on Monday 30 July 2012. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

RESOLVED That the recommendations of the Procurement Task and Finish Group be endorsed and submitted to the Executive Board for formal adoption.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Performance & Resources Overview and Scrutiny Panel, 10 pages

Background

Scope of Review

Method of Review

Evidence for Recommendations

Conclusion

Recommendations

List the recommendations:

Procurement Lincolnshire should seek appropriate feedback from all users and suppliers post project. This would enable effective future benchmarking.

Procurement Lincolnshire Annual Reports to be made available to the Performance and Resources Overview and Scrutiny Panel. In addition, the quarterly reports should be sent to the Chairman, who may then circulate to the Panel.

The profile of Procurement Lincolnshire should be maintained and enhanced. This could be conducted via their website, promotional material; such as their booklet; and the respective Economic Development Teams, in order to raise awareness of Procurement Lincolnshire to businesses.

4 Background Procurement Lincolnshire is a Shared Service partnership and part of a wider Lincolnshire Shared Service programme, which aims to be innovative in transforming the way in which services are organised and delivered to improve the customers’ experience.

Together, the eight partner authorities spend in excess of £480 million per year on the procurement of goods, services and works. The Task and Finish Group wanted to ensure that the amount NKDC spend with Procurement Lincolnshire represents good value for money.

The amount of expenditure required to automatically trigger the use of Procurement Lincolnshire is £75k; the trigger amount refers to the total contract cost, not an annual amount.

At a contract cost of below £75k but above £25k, many partners use certain aspects of the service, such as the electronic vault/e-tendering process. Procurement Lincolnshire is open to use for any tendering exercise large or small. However, as it requires a certain amount of rigidity in its administration, officers may choose to utilise the less formal “three quotes” process, for smaller contracts.

The thresholds for EU procurement regulations were confirmed, at £4.3m for work contracts and £173k for goods and services. Governance for Procurement Lincolnshire has recently changed and Procurement Lincolnshire now reports to the Procurement Advisory Board. There is an additional board which acts as a working group, called the Strategic Board. Quarterly reports are submitted to the Strategic Board, which includes NKDC’s Deputy Chief Executive. The Joint Lincolnshire Scrutiny Panel undertook a review of Lincolnshire Procurement in 2011, and most of the recommendations from the report had been implemented. Where recommendations have not yet been complied with, this is because Procurement Lincolnshire is awaiting Government guidance.

The findings from the Task and Finish Group took a little longer to finalise than anticipated, due to illness within the Group.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement Lincolnshire TFG ReportReport 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Procurement Lincolnshire TFG ReportThis decision
  2. Procurement Lincolnshire Annual UpdateNoted
  3. Procurement Lincolnshire Annual ReportNoted
  4. Procurement Lincolnshire Annual Report - 2012/2013Noted
  5. Procurement Lincolnshire Service Level AgreementApproved
  6. Task and Finish Group report: Procurement LincolnshireApproved

More from North Kesteven Performance & Resources Overview and Scrutiny Panel

All decisions
MeetingDecisionOutcome
15 Nov 2021 An introduction to a Scrutiny ReviewThat word ‘streamlined’ be removed from the recommendations. 2. That the recommendations be approved. Approved Open
25 Feb 2019 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
12 Nov 2018 DCLG Select Committee ReportIt was therefore agreed to postpone proceedings until a new Scrutiny Officer was in position and the Government Repor... Agreed Open
12 Nov 2018 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
17 Sep 2018 Forward PlanIt was agreed that items should be brought to Scrutiny at a much earlier stage. Conclusion: Members noted the Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies