Resolved
That the updated Growth Fund project expenditure be noted; and That the proposed new projects to be supported by the Growth Fund be approved.
Central Lincolnshire Joint Strategic Planning Committee noted this item on Monday 3 September 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That the updated Growth Fund project expenditure be noted; and That the proposed new projects to be supported by the Growth Fund be approved.
Committee: Central Lincolnshire Joint Strategic Planning Committee Meeting Date: 3 September 2012 Report presented by: Phil Hughes, Strategic Planning Manager, Lincolnshire County Council Author: Phil Hughes, Lincolnshire County Council Email: [email protected] Tel: 01522 554806
Report Title: Lincoln Growth Fund Update Purpose of Report
To provide an update on latest Growth Fund expenditure.
Introduction
1. The Growth Fund plays a vital role in supporting the delivery of the Central Lincolnshire Core Strategy and the wider Local Plan. In addition, it is also used to pay for the Witham Valley Country Park Project Officer and transport studies. As the Growth Fund continues to be drawn down in support of the growth agenda, the remaining budget will need to be used sparingly as it depletes. There is no time limit but it is expected that the fund will be totally spent before the end of 2014/15. It is important that all spending remains transparent and that project proposals are discussed and approved prior to implementation and payment.
2. It is worth restating the process required to approve suitable projects:
a)Officers discuss proposed projects and agree priorities in relation to the Core Strategy work programme and transport needs;
b) A project brief is drafted which includes timetable, cost breakdown and management details;
c) LCC Strategic Planning Manager reports update on project progress, expenditure and new project proposals for approval by the Joint Committee;
d) Project costs are claimed in arrears from the Growth Fund via LCC, using a payment request voucher supported by invoices and evidence of expenditure.
Revenue Spending
3. Appendix 1 (attached) provides an update on project allocations, total actual spending and progress on revenue expenditure. A number of projects have been completed under budget and the underspend will be recycled to support new projects. In summary:
Growth Fund Revenue (Total) £ 833,889 Ringfenced £ 567,839 Spent £ 522,275 Left to Ringfence £ 266,050
Projects Update
4. Appendix 1 provides an update on the expenditure of all approved projects. A summary of progress is included below for unfinished projects:
1 East-West Link Road
5. The East West Link Road is at the planning application stage. The application was lodged in January 2012, has been validated and the consultation period is closed. The project team has just completed its response to the comments and objections received and it is hoped that the application will be determined in October. There is a Conservation Consent Application which will go to the Secretary of State for final determination and this may take until December 2012. LCC has recently acquired a Chinese Warehouse for c. £220,000 and an Industrial Unit for c. £210,000. In addition, terms have been agreed on two other properties, committing a further £1 million.
6. The overall programme aim remains the same, i.e. to commence physical construction early in 2013 and complete by the end of the year, subject to no major objections and consequent public inquiry. The estimated cost of the scheme is £20m of which £12m is associated with land assembly and £8m construction costs. The £12m land assembly will be expended during the period 2010/11 - 2012/13. The £8m construction costs will be incurred in 2013/14 financial year.
Infrastructure Viability Study
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
3 September 2012: Lincoln Growth Fund Update Appendix 1Appendix | 1 pages | Download |
PDF |
Lincoln Growth Fund UpdateReport | 4 pages | DownloadRead as text |
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Jul 2026 | Election of Chairman 2026/2027That Councillor Wright be elected Chairman of the Central Lincolnshire Joint Strategic Planning Committee for the mun... | Decided | Open |
| 6 Jul 2026 | Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ... | Decided | Open |
| 6 Jul 2026 | MinutesThat the minutes of the Central Lincolnshire Joint Strategic Planning Committee held on Monday 13 th October 2025 wer... | Approved | Open |
| 6 Jul 2026 | 2025/26 Central Lincolnshire Joint Strategic Planning Committee Annual ReportThat the 2025/26 Annual report was approved as a fair summary of activity of the Central Lincolnshire Joint Strategic... | Approved | Open |
| 6 Jul 2026 | Central Lincolnshire Budget Update ReportThat the Committee noted the outturn for 2025/26 and the current budget forecast for 2026/27-2029/30 including the co... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.