Internal Audit Progress to November 2012

Noted Finance 4 papers

Audit Committee noted this item on Monday 19 November 2012. Below is the council's own wording, with the papers it was decided on.

Item29

Resolved

That the report be noted. Note- The representatives from KPMG left the meeting at 17.45.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Audit Committee, 16 pages

Internal Audit - Progress Report 2012 / 13

Date: November 2012 Contents

Introduction 1

Key Messages 1

Internal Audit work completed from 01/09/12 to 31/10/12 1

Other Significant Work 2

Audits in Progress 2

Performance Information 3

Other matters of Interest 3

Appendices Appendix 1 – Assurance Definitions 7 Appendix 2 - Outstanding recommendations as at 31/10/2012 8 Appendix 3 – Internal Audit Plan & Schedule 2012/13 9 Appendix 4 – Presentation from Audit Committee Forum (KPMG) Appendix 5 - Presentation from Audit Committee Forum (Audit Lincolnshire)

Contact Details: Lucy Pledge CMIIA Head of Audit & Risk Management

County Offices, Newland, Lincoln, LN1 1YG : 01522 553692  [email protected] Audit Lincolnshire – Internal Audit Progress Report

Introduction 1 The purpose of this report is to:  Advise of progress being made with the Audit Plan  Provide details of the audit work during the period  Provide details of the current position with agreed management actions in respect of previously issued reports  Raise any other matters that may be relevant to the Audit Committee role

Key Messages

2 Delivery of the audit plan is progressing well. Our main focus since the last progress report has been the completion of the housing benefit subsidy claim testing.

3 We were due to commence an audit of the housing allocations system, specifically focussing on the new choice based lettings system. We understand that the implementation of this new system has been delayed, and we therefore propose that this audit is deferred into the 2013/14 financial year. We would like to use these days to widen the scope of the upcoming project management audit, as it has been recognised that this is potentially an area of improvement for the Council.

Internal Audit work completed from 01/09/12 to 31/10/12 4 The following audit work has been completed and a final report issued:

Full Assurance Substantial Limited No Assurance Assurance Assurance

 Building  Council Tax  N/A  N/A Control

Note The Audit Committee should note that the assurance expressed is at the time of issue of the report but before the full implementation of the agreed management action plan. Definitions levels are shown in Appendix 1.

4 In the audits given Full and Substantial Assurance, we confirmed that the Council has sound processes in place:

 Building Control – we confirmed that the team has introduced charges in accordance with new regulations. They regularly review their charges and

Page 1 of 15 Audit Lincolnshire – Internal Audit Progress Report

publish them on the Council’s website. Income is monitored, and the team works hard to try and generate additional income where possible.

 Council Tax – this review looked at the new shared service, and tested council tax transactions for both North Kesteven District Council and City of Lincoln Council. On the whole, controls were found to be in place and working adequately. Procedural guidance for the new teams is yet to be completed, and some historical issues from City of Lincoln are being investigated.

Other Significant Work 7 Other work undertaken includes:

Combined Assurance Model The report format has now been agreed, and management is currently analysing the results and preparing commentary to be included in the report. The draft report will be presented to the Corporate Management Team in December for sign off, and the final version will be presented to the Audit Committee in January.

Housing Benefits Subsidy Testing Testing of the 2011/12 Housing Benefits Subsidy Claim (on behalf of the Audit Commission) has been completed. We identified no material errors, and this has been confirmed by external audit. The claim has been qualified again this year, but this is due to the reconciliation of benefit granted to benefit paid.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Appendices 1-3Report 16 pages DownloadRead as text
PDF
Internal Audit Appendix 4Appendix 23 pages Download
PDF
Internal Audit Appendix 5Appendix 19 pages Download
PDF
Internal Audit Progress to November 2012Report 2 pages Download

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Internal Audit Progress to November 2012This decision
  2. Internal Audit Annual Opinion Report 2025/26Noted
  3. Internal Audit Progress ReportNoted
  4. Internal Audit Combined Assurance ReportDecided
  5. Q1 and Q2 Internal Audit Plan 2026/27Approved
  6. Internal Audit Strategy 2026 – 29Approved

More from North Kesteven Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. Approved Open
20 Jul 2026 Follow Up ItemsThat the Follow-Up Items report be noted. Noted Open
20 Jul 2026 Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... Approved Open
20 Jul 2026 Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. Noted Open
20 Jul 2026 Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies